Select Committee on Transport Minutes of Evidence


APPENDIX 17

Memorandum submitted by Road Block

  I would like to submit evidence to the committee on behalf of Road Block, a national alliance of community groups opposing road building.

  I would like to restrict myself to giving evidence on the cost escalation of road projects in the Highways Agency Targeted Programme of Improvements (TPI). Road Block has calculated that TPI schemes are averaging 67% cost escalation.

  I am using data supplied by the Department of Transport in response to a Parliamentary Question by Tom Brake MP on 19 December 2005. This list was placed in the Libraries and is enclosed. (see annex)

  Road Block has taken the TPI costs of roads when first approved, and the most recent cost estimate, and we have placed them in the enclosed table: TPI Schemes Dec05.

  The cost increases were then calculated in terms of monetary increase, and also the percentage increase. The schemes have been placed in order of schemes with the largest cost increases coming first.

  The list has been divided between schemes approved before and after the 2003 Treasury Green Book guidance where the costs of schemes have made allowance for inflation up to scheme completion, for non-recoverable VAT and for "optimism bias".

  For schemes before the April 2003 guidance, the average cost escalation is 67%.

  After the 2003 guidance, there seems to be have been little or no re-evaluation of the costs of TPI roads.

  Road Block believes that costs of some of the post April 2003 TPI schemes could be much higher than the information supplied to Tom Brake MP.

  For instance local residents against the A14 Ellington to Fen Ditton Improvement report that in the Highways Agency Stage 2 Scheme Assessment Report the cost is reported to be £543 million, not the £490 million given in the answer on 19 December 2005. This scheme is extremely controversial and is subject to a Judicial Review due to resident's complaints of lack of consultation.

  Road Block believes that often the appraisal for road schemes is still not satisfactory—the benefits of a road are often over emphasised, whilst the disbenefits are underplayed, to gain approval. Only later, once approval has been given, do the true costs emerge. The same situation is occurring with government funded local authority road schemes.

  Road Block believes that it is essential that cost estimates are updated regularly for TPI schemes, particularly those approved since April 2003. "Optimism bias" of between 5% and 45% (as outlined in the Green Book guidance) is clearly not enough, given the cost escalation of schemes prior to April 2003 of an average of 67%.

  There is a need for more robust and independent appraisal of schemes coming forward for approval into the TPI.

9 January 2006

Annex

  Tables (1) Targeted Programme of Improvement schemes and (2) local highway authority major road schemes which are currently approved for funding through the Local Transport Programme. Schemes within the Targeted Programme of Improvements are subject to regular review.

  The figures provided in table 1 are the latest agreed budget costs and may be subject to change as schemes progress.

  The latest estimated costs of local highway authority schemes in table 2 represent the Department's most recent information. Provisionally approved schemes with costs in excess of the original approval are subject to detailed scrutiny and appraisal processes before being considered for full approval.

  Table 3 provides a list of the new major road schemes that local authorities have provided in July 2005 for funding through the Local Transport Plan programme. Some of these schemes were originally submitted in previous years. No decisions have yet been taken on these schemes and will be the subject of advice from the region on their timing and priority.

 (1) HIGHWAYS AGENCY TARGETED PROGRAMME OF IMPROVEMENT SCHEMES


Scheme
Date of TPI EntryTPI Entry
cost(£m)
Latest agreed
budget cost (£m)


A1(M) Ferrybridge—Hook Moor (DBFO)
Original TPI Scheme (July 1998)160 160
A2 Bean—Cobham Phase 2 Tollgate—Cobham Original TPI Scheme (July 1998)35 101
A2/A282 Dartford ImprovementOriginal TPI Scheme (July 1998) 3872
A14 Rookery Crossroads GSJOriginal TPI Scheme (July 1998) 510
A249 Iwade—Queenborough Improvement Original TPI Scheme (July 1998)79 81
A303 StonehengeOriginal TPI Scheme (July 1998) 125Under review.
Latest estimate is 470
A421 Great Barford BypassOriginal TPI Scheme (July 1998) 2558
A500 City Road & Stoke JunctionOriginal TPI Scheme (July 1998) 2455
M25 J12-15 WideningOriginal TPI Scheme (July 1998) 94120
M60 J5-8 WideningOriginal TPI Scheme (July 1998) 82116
All Attleborough BypassMarch 2000 1429
All Fiveways—Thetford Improvement March 20003060
A47 Thorney BypassMarch 2000 927
M6 Carlisle to Guardsmill extensionMarch 2000 46175
A63 Melton Grade Separated JunctionOctober 2000 1122
A14 Haughley New St—Stowmarket Improvement March 20011032
A3 Hindhead ImprovementMarch 2001 107239
A38 Dobwalls Bypass ,March 2001 1736
A595 Parton—Lillyhall Improvement March 20011830
Al Peterborough—Blyth Grade Separated Junctions March 20013183
M62 Junction 6 ImprovementMarch 2001 2438
A46 Newark—Widmerpool Improvement March 200182220
A30 Bodmin Indian QueensMarch 2001 4993
A483 Pant- Llanymynech BypassAugust 2001 1740
A5117/A550 Deeside Park Junctions Improvement February 20022243
A419 BlunsdonApril 2002 2965
A66 Temple Sowerby & Improvement at Winderwath April 20021939
Al Dishforth to LeemingJune 2002 125Combined cost = 325
Al Leeming to BartonJune 2002 100
Al Bramham—Wetherby (Including Wetherby Bypass) June 20023851
A64 Rillington BypassJuly 2002 812
M40/A404 Handy Cross Junction Improvement August 20021014
A47 Blofield to North Burlingham Dualling August 20021015
A66 Greta Bridge to Stephen Bank Improvement August 200269
A66 Carkin Moor to Scotch Corner Improvement August 2002711
A428 Caxton Common to Hardwick Improvement August 20022255
A30/A382 Merrymeet JunctionOctober 2002 712
6 Long Newton JunctionOctober 2002 68
A69 Haydon Bridge BypassDecember 2002 1424
A419 Commonhead JunctionDecember 2002 1216
M5 Junctions 19—20 Southbound Climbing LaneDecember 2002 912
M5 Junctions 19—20 Northbound Climbing LaneDecember 2002 616
M1 J19 ImprovementFebruary 2003 100123
A14 Ellington—Fen Ditton Improvement April 2003490490
A57/A628 Mottram—Tintwistle Bypass April 200390103
A45/A46 Tollbar End ImprovementApril 2003 5757
M1 Junction 6a to 10 WideningJuly2003 241289
M1 Junction 10 to 13 WideningJuly 2003 382382
Al Morpeth to Felton DuallingJuly 2003 8484
Al Adderstone to Belford DuallingJuly 2003 1414
A1/A19/A1068 Seaton Burn JunctionJuly 2003 3029
A19/A184 Testos Junction ImprovementJuly 2003 2121
A505 Dunstable Northern Bypass (A5 toJuly 2003 4848
A421 Bedford to M1 Junction 13July 2003 171171
A21 Tonbridge to PemburyJuly 2003 6565
M40 Junction 15 (Longbridge)July 2003 5757
A590 High & Low Newton BypassOctober 2003 2222
M20 Junction 10ANovember 2003 4646
A30 Carland Cross to Chiverton CrossNovember 2003 125125
A30 Temple to Higher Carblake Improvement November 20034141
A27 Southerham to Beddingham Improvement March 20041919
M1 J21-30April20041,915 1,915
M25 J 1 b-3 WideningApril 2004 6666
M25 J5-7 WideningApril 2004 214214
M25 J16-23April 2004 496496
M25 J23-27 WideningApril 2004 419419
M25 J27-30 WideningApril 2004 402402
A21 Kippings Cross to Lamberhurst Bypass May 20046868
A23 Handcross to Warninglid WideningMay 2004 4141
A453 Widening (M1 J24 to A52 Nottingham) May 20049090
M25 Junction 28/Al2 Brook Street Interchange March 200588
M27 Jl l to J12 Climbing LanesMarch 2005 2727
M27J3 to J4 WideningMarch 2005 5252
M1 J30 to J31 WideningMarch 2005 135135
Ml J31 to J32 WideningMarch 2005 2020
M1 J32 to J34S WideningMarch 2005 139139
M1 J34N to J37 WideningMarch 2005 246246
Ml J37 to J39 WideningMarch 2005 224224
Ml J39 to J42 WideningMarch 2005 202202
M1 J31 to J32 Northbound Collector/DistributorMarch 2005 2929
M62 J25 to J27 WideningMarch 2005 215215
M62 J27 to J28 WideningMarch 2005 8383


NOTE:

  The final column of the table show the latest agreed budget costs represent the approved full outturn costs to deliver the schemes and have been built up as follows:

—  base estimate of scheme cost, at 2001 prices time, including non recoverable VAT and an allowance for risk assessment;

—  plus allowance for "optimism" bias which was introduced in April 2003 following the new Treasury Green Book on investment appraisal and is between 5% and 45% depending on the quality of the risk assessment;

    —  plus inflation at 2.5% pa to the projected start date. The projected start date, and by implication these costs, are dependent upon completion of statutory procedures and availability of funds.

  Since April 2003, the costs of schemes submitted for TPI entry approval have been reported on the above basis. That is, they make allowance for inflation up to scheme completion, for non-recoverable VAT and for "optimism bias" in line with revised Treasury guidance which was issued in April 2003. Before then, only net scheme costs, exclusive of VAT and projected inflation, were reported at TPI Entry and the two sets of figures are not directly comparable.

 (2)  LOCAL TRANSPORT PLAN MAJOR ROAD SCHEMES (OVER £5 MILLION)


Scheme
Date Fully Approved
(FA) or
Provisionally
Accepted (PA)
(i) gross cost of
scheme when first
submitted for
approval
(ii) most recent
estimate or final
gross cost of
the scheme


A228 Ropers Lane Phase 1
PA-Dec 2001
& FA-May 2003
£15.20m£18.956m
East Kent Access Phase 1PA-Dec 2000
& FA-July 2005
£12.954m£23.248m
A228 Leybourne & West Malling Corridor Improvement PA-Dec 2002
& FA-March 2005
£27.94m £28.47m
Kiln Lane Link, EpsomPA-December 2001 £10.60m£18.684m
A24 Ashington to SouthwaterPA-December 2002 £18.95m£26.220m
A24 Horsham to Capel ImprovementPA-December 2002 £38.56m£56.720m
A4146 Stoke Hammond/Linslade Western Bypass PA-December 2000
& FA-December2004
£44.66m£52.842m
Bletchley LinkNote-This scheme is no longer a major road
scheme and the promoters have now submitted a new Major Scheme Business Case
M4 J11 (Green Park Improvements) and Mereoak Roundabout PA-December 2001£43.67m Option 1
£64.64m
or
Option 2
£ 69.61m
Sittingbourne Northern Relief RoadPA-December 2004 £43.5m£43.5m
Bexhill Hastings Link RoadPA-December 2004 £47.12m£48.51m
Cradley Heath BypassPA-December 2000
FA-June 2004
£6.335m£10.761m
Brierley Hill Access NetworkPA-December 2003 £24.310m£35.000m
A38 Northfield Regeneration BypassPA-December 2000
FA-December 2004
£12.000m£19.380m
Owen Street Relief RoadPA-December 2000 £8.810m£17.150m
Selly Oak Relief RoadPA-December 2002 £42.500m£52.250m
Barford BypassPA-December 2000
FA-December 2004
£6.910m£10.380m
Rugby Western BypassPA-December 2000 £20.280m£26.818m
Hodnet BypassPA-December 1999 £12.515m£14.902m
Hanley Bentilee LinkPA-December 2000 £15.415m£21.562m
Tunstall Northern BypassPA-December 2003 £6.730m£7.004m
Leeds Inner Ring Road Stage 7FA-December 2000 £35.576m£50.538m
Hanley Bentilee LinkPA-December 2000 £15.415m£21.562m
Tunstall Northern BypassPA-December 2003 £6.730m£ 7.004m
Rugeley Eastern BypassPA-December 2000
FA-February 2004
£17.454m£22.844m
East Leeds Link RoadFA-December 2000 £19.380m£31.881m
Sheffield Inner Relief Road Stages II &III PA-December 2000
FA-July 2004
£30.000m £62.571m
Glasshoughton Coalfields Link RoadPA-December 2000 £6.815m£11.695m
A63 West Bawtry Road ImprovementsPA-December 2000 £5.028m£5.028m
Hemsworth to Al Link RoadPA-December 2000 £11.261m£22.776m
A628 Cudworth & West Green BypassPA-December 2001 £17.198m£17.198m
57(T) M1 Junction 31 to Todwick Crossroads PA-December 2001£6.264m £11.900m
A165 Reighton BypassPA-December 2002 £6.550m£6.564m
A39 Camelford BypassPA-December 2000 £6.8m£14.4m
A391 St Austell to BodminPA-July 2003 £30.35m£57m
Barnstaple Western BypassPA-December 2000
FA-December 2004
£32.5m£43.078m
A354 Weymouth Relief RoadPA-December2003 £54.567m£54.567m
Poole Bridge Regeneration InitiativePA-December 2001 £14.414m£46,880m
Brunel Link and Harnham Relief RoadPA-December 2000 £13.0m£21.803m
A57 Cadishead Way (Brinell Drive-City Boundary) PA-December 2002
FA-2003
£19.905m £19.405m
The Glossup Spur, TamesidePA-December 2000 £7.18m£8.08l m
Ashton Northern Bypass Stage 2, Tameside PA-December 2002£7.74m £8.29m
Wigan Inner Relief RoutePA-December 2002 £19.5m£19.5m
A34 Alderley Edge Bypass, CheshirePA-December 2002 £37.9m£40m
Carlisle Northern Development RoutePA-December 2000
FA-October 2004
£24.31m (traditional
funding)
£78.812m
(PFI Credits)
A58 Blackbrook Diversion, St HelensPA-December 2002 £7.899m£8.45m
Hall Lane Area Improvements, Liverpool PA-December 2000£9.0m £12.2m
Edge Lane West, LiverpoolPA-December 2004 £15.85m£15.85m
Bedford Western BypassPA-December 1999 £20m£24.812m
Ridgmont Bypass/Woburn LinkPA-December 1999 £7.745m£16.116m
A505 Baldock BypassPA-December 1999 £33.821m£47.408m
Stowmarket Relief RoadPA-December1999 £13.2m£17.695m
South Lowestoft Relief Road and Associated Measures PA-December 2000
FA-December 2004
£25.4m£30.621 m
Al 27/A1159 Priory Crescent, Southend on Sea FA-December 2000£3.5m £27.533m
A1198 Papworth Everard BypassPA-December 2001
FA-October 2005
£5.4m£8.740m
East Luton Corridor SouthPA-December 2001 Now a subject of a Community
Infrastructure Fund application
Sunderland Southern Radial RouteFA-September 2004 £17.026m£28.720m
Darlington Eastern Transport CorridorPA-December 2000 £5.700m£12.100m
A688 Wheatley Hill-Bowburn Link, Durham PA-December 2000£6.624m £9.180m
Pegswood Bypass, NorthumberlandPA-December 2001
& FA-October 2005
£8.140m£9.375m
North Middlesbrough Accessibility Improvements PA-December 2002£12.220m £12.220m
Sunderland Central RoutePA-December 2002 £16.540m£16.540m
A1056 Northern Gateway, North Tyneside PA-December 2003£9.916m £14.327m
A6096 Ilkeston-Awsworth Link, Derbyshire PA-December 2001£8.606m £12.270m
Markham Employment Growth Zone, Derbyshire PA-December 2001£21.5m £23.5m
A158/C541 Lincolnshire Coastal Access Improvement (including Phase 1-Partney Bypass Phase 1-PA
December 2000
FA-2004
Phase 2&3-PA-December 2000
£15.515m (for all
3 phases)
Phase 1-£7.791m
Phase 2- £14.15m
Phase 3-£9.38m
A1073 Spalding to Eye Improvement, Lincolnshire PA-December 2000£24.835m £70.4m
A43 Corby Link RoadPA-December 2002 £12.717m£15.2m
A509 Isham Bypass, NorthamptonshirePA-December 2003 £13.9m£14.6m
A612 Gedling Integrated Transport Scheme,
Nottinghamshire
PA-December 2002£7.067m £11.664m
Oakham BypassPA-December 2001 £7.650m£11.666m


NOTE:(1)  Schemes not yet approved are subject to the completion of the relevant statutory processes and will require final approval by the Department.

(2)  Schemes that have been funded through the Local Transport Plan programme and have been completed between 1999-2005 are not included in the list.

(3)  Provisionally Approved schemes with costs in excess of the original approval are subject to detailed scrutiny and appraisal processes before being considered for Full Approval.

 (3)  LTP 2005—NEW MAJOR ROAD SCHEMES (OVER £5 MILLION) SUBMITTED IN JULY 2005


Scheme
(i)  gross cost of
scheme when first
submitted for approval
(ii)  most recent
estimate or final gross
cost of the scheme

A41 Expressway/A4031 All Saints Way Junction Improvement
£15.373m (2004)£19.837m (2005)
Rotherwas Access Road, Herefordshire£9.824m (2003) £10.280 (2005)
A509 Isham to Wellingborough Improvement, Northamptonshire £13.678m (2004)£13.575m (2005)
A47 Earl Shilton Bypass£14.106 (2003) £15.242m (2005)
Beverley Integrated Transport Plan£41.049m (2004) £28.089m (2005)
A140 Long Stratton Bypass, Norfolk£26.556m New submission
Pleasley Bypass Extension, Nottinghamshire £16.966mNew submission
A13/A130 Thames Gateway (Sadlers Farm Junction),Essex £70.97mNew submission
Waverley Link Road, Rotherham£8.130m New submission
Finningley and Rossington Regeneration Route Scheme, Doncaster £158.15mNew submission
Sunderland Strategic Transport Corridor £69.445mNew submission
Brownhills Transport Package£20.858m New submission
A4123/A461-Burnt Tree Island Improvement £10.303mNew submission
Taunton Third Way & Northern Inner Distributor Road £27.20mNew submission
Heysham to M6 Link Road, Lancashire£87.7m New submission
A684 Bedale—Aiskew—Leeming Bar Bypass, North Yorkshire £25.667mNew submission
East Durham Link Road£9.746m (2005) New submission







 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 27 July 2006