Select Committee on Transport Ninth Report


2  The Department and its Agencies

Role and purpose of the Department's Agencies

7. The Department has a number of important functions delegated to arms-length Executive Agencies.[6]

8. The Trade Unions told us that 'the Department is not an integrated whole but a collection of businesses bound together'. We understand that there is no Department-wide intranet, no Department staff directory or email directory, and no common information technology systems or procedures.[7] This is disappointing. The Trade Union side believes that 'an absence of central control and common terms and conditions' works against the Department effectively delivering its policies.[8] We agree.

9. There remain serious concerns, not simply within individual agencies, but across the Driver and Vehicle Operator Group as a whole and stretching even further across other Agencies and the Department itself. In particular: there are tensions between the strategic aims of the Department and an inability to link this properly with Agency activity on the ground; the slow development, poor integration and costly and delayed implementation of information technology systems; and a lack of consistent internal working practices and conditions.[9] These are not new problems. The Committee has highlighted serious deficiencies in Agencies' work before, most recently in our work on the Department's 2005 Annual Report.

Shared Services

10. The Department is implementing a Shared Services project which will achieve savings by standardising, simplifying and sharing support service functions across the central Department and Executive Agencies, thereby helping to focus more resources on frontline operations. The project will incur significant up-front costs over the next four years. The Department estimates these at between £44 million and £49.5 million.[10] For the Driver and Vehicle Operator Group of Agencies and the Highways Agency, the Department estimated that costs incurred on the project to December 2005 were £463,000.[11]

11. Shared Services is expected to achieve annual savings of around £16 million, which will be largely achieved through savings on staff,[12] although the full annual savings will not be achieved until after 2008-09.[13]

12. The interim Business Case for the project appears to be sounder than those documents available to the Committee at earlier stages.[14] We have concerns however about some of the cost changes between earlier documents and the current Business Case, in particular whether:

  • the present level of optimism bias of £5.3 million is enough;[15]
  • there is too much reliance on external input.[16] This expertise could be brought in-house, possibly through fixed term contracts;
  • expected savings will be achieved;
  • the project received a satisfactory 'Gateway 0' review in April 2006;
  • the Trade Union side is sufficiently engaged and onboard with the project.

13. We expect the Department to keep a tight control on the project to ensure that the planned savings are delivered. The Department itself admits in the Business Case says that financial risk is 'high': 'There are … financial risks resulting from potential delays or non-delivery of functionality to the scope demanded, as any delays to full implementation will erode benefits'.[17] The Department has also conducted a 'sensitivity analysis' which shows the impact of a 25 per cent increase in costs or decrease in benefits on the project outcome.[18] It is clear that there is scope for financial disaster if costs are not tightly controlled.

14. Over the next four years the Department estimates that the Shared Services project will cost in excess of £44 million. The exact cost however remains unclear. It is important that lessons are learned from this complex project. We expect that any problems which may be encountered by the first Agencies to join will be addressed for later Agencies. It is critical that Shared Services is implemented 'on budget' and 'on time'. The financial and organisational ramifications of failure are certain to be significant. We expect the Department to keep us fully informed of progress against the project plan. Any delays and the implication of these on additional costs should be made clear.


6   See Annex for details. Back

7   Ev 121 Back

8   ibid Back

9   HC 684, pp22-24, paras 84-94 Back

10   Q20  Back

11   Freedom of Information Request F0001853 to the Department for Transport, 9 January 2006 Back

12   Q17 Back

13   DfT Shared Service Project - Outline Business Case Report, version 1.3a Back

14   This was the so-called Outline Business Case Report version 1.3a (OBC) dated May 2005 (updated September 2005). The Business Case referred to in this report is the Shared Services Programme: Updated interim Business Case version 0.7, January 2006 Back

15   'Optimism bias' is defined in the Treasury Green Book, paras 5.61-5.64. There is a demonstrated, systematic, tendency for project appraisers to be overly optimistic. This is a worldwide phenomenon that affects both the private and public sectors. Many project parameters are affected by optimism - appraisers tend to overstate benefits, and understate timings and costs, both capital and operational. To redress this tendency, appraisers should make explicit adjustments for this bias. These will take the form of increasing estimates of the costs and decreasing, and delaying the receipt of, estimated benefits. Back

16   For example, the OBC assumed 25,000 resource days at an external daily rate of £1134 a day. This has risen to the current estimate of 58,000 resource days at £1600 a day. One of the main reasons seems to be a significant increase in post-design requirement.  Back

17   Shared Services Programme: Updated interim Business Case version 0.7, paras 5.17-5.18 Back

18   ibid, para 8 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 27 July 2006