Select Committee on Trade and Industry Fourth Report


6  Wider policy concerns

186. The Government cannot consider the particular issues that apply to nuclear new build without taking account of its wider implications for other policy areas. Those which are of particular concern to us, and which are the subject of this chapter, are: the extent to which nuclear power can contribute to making the UK a low-carbon economy; its contribution to securing electricity supply; its possible effects on other areas of energy policy, such as renewables and energy efficiency; and the implications it presents for upgrading the grid network. All of these factors weigh heavily on the case either for or against nuclear power, and require due regard by the Government.

Reducing carbon dioxide emissions

187. The contribution that nuclear power makes to reducing the UK's carbon emissions is one of the main justifications given for supporting it as part of the energy mix. However, there has been debate surrounding the extent to which nuclear energy can really be considered a 'low-carbon' technology. In this section we examine whether or not this is true, and consequently, the extent to which nuclear power has a role to play in reducing emissions.

IS NUCLEAR POWER LOW CARBON?

188. Nuclear energy has been referred to by some as a 'zero carbon' source of electricity. Whilst it is correct to say that the use of uranium as a fuel does not emit carbon dioxide in the same way as fossil fuels, there are, nonetheless, a number of activities that go into producing nuclear power that, depending on the energy mix on which they are based, do result in carbon emissions. This was pointed out to us in both written and oral evidence.[288] For example, uranium ore mining, manufacturing the concrete and steel for the construction of the station, waste activities and plant decommissioning are all essential activities over the lifetime of a nuclear power station, which require energy to carry out. Figure 3 shows the results of a study estimating the emissions from the Torness nuclear power station in Scotland, across the various parts of the production cycle. It shows that the most polluting part of the fuel and plant cycle is the extraction of uranium, which is more significant than the actual construction and decommissioning of the power station.

189. In reality, no source of electricity generation can currently be considered genuinely zero carbon, because of the energy costs required in building, operating and decommissioning the power plant.[289] This is as true for renewable energy as it is for nuclear power, and will continue to be the case so long as the energy base on which such activities take place has an element of fossil-fuel powered generation within it. Various studies have attempted to compare the carbon status of different electricity sources. Figure 4 shows a comparison for what are considered low carbon technologies. For each technology, a high and low estimate is provided. This reflects the different sources of data, which have looked at different technologies, and made different assumptions, within each type of generation. The chart shows hydroelectricity, wind and nuclear as the lowest emitters. Photovoltaics and marine renewables require a relatively larger amount of energy in their manufacture, while the harvest and transport of fuel raises the energy cost for biomass. Figure 5 puts the results for low carbon technologies in context with a comparison against the estimated lifetime emissions from coal and gas-fired plant.

Figure 3: Carbon emissions across the lifetime of a nuclear power station



Source: AEA Technology, 'Carbon footprint of the nuclear fuels cycle - a study for British Energy', March 2006

Figure 4: Comparison of high and low lifetime carbon emissions for low carbon technologies (grams of carbon dioxide per kilowatt hour, g/kWh)



Source: Parliamentary Office of Science and Technology, 'Carbon footprint of different electricity sources', July 2006

Figure 5: Comparison of high and low lifetime carbon emissions for all technologies (grams of carbon dioxide per kilowatt hour, g/kWh)


Source: Parliamentary Office of Science and Technology, 'Carbon footprint of different electricity sources', July 2006

190. Although it is important to note that each of the estimates in these charts is based on different academic studies, there is no denying the huge difference between the carbon emissions of wind and nuclear power on the one hand, and coal and gas-fired generation on the other. There has been some concern raised that, as mining for uranium exhausts existing 'high grade' ores, greater energy will have to be expended on mining and subsequently enriching lower grade ores.[290] This may be the case, but as noted earlier in this Report, current evidence on future uranium supplies is optimistic. Even if the optimism about high grade ores is misplaced, the resulting emissions from mining would have to be of an order of magnitude greater than they are now to have any bearing on the overall conclusion that nuclear power is a low carbon technology, comparable with renewable energy. The potential future need to resort to lower grade uranium ores is an example of 'diminishing returns'. It is arguable that an analogous situation could apply for renewable sources of electricity. For example, with onshore wind, the first turbines would be built at the best sites. Subsequent turbines would be built at less optimal sites and, as a result, their carbon emissions per unit of electricity generated would also probably be higher.

THE IMPACT OF NUCLEAR POWER ON REDUCING EMISSIONS

191. Given that nuclear power can be considered a low carbon energy source, the extent to which it offsets emissions is dependent on the technology it is assumed to displace. The usual assumption is that this would be gas-fired generation, largely because of the low cost and the relative ease with which gas-fired stations can be built. The Sustainable Development Commission estimated that the UK's current fleet of nuclear reactors offsets between 8 and 20 million tons of carbon—equivalent to 5 and 12.6% of UK emissions—depending on whether you assume it to displace gas or coal-fired generation.[291] Indeed, Ofgem note in their submission to the Energy Review, that with about 20% of UK nuclear capacity due to close by 2010, without replacement, other generating capacity will have to reduce emissions by at least 2 million tons of carbon just to keep them at their current levels.[292]

192. The Sustainable Development Commission has conducted further analysis on the extent to which new nuclear build may offset carbon emissions in the future.[293] It estimates that a 10 gigawatt programme of new reactors built over a period up to 2034 would reduce future UK emissions by about 4%, assuming that gas-fired generation is displaced. Similarly, a larger 20 gigawatt programme would reduce emissions by about 8%. The Commission concludes that "whilst these cuts are certainly substantial, they are not a panacea solution to the challenges of a low carbon future".[294]

193. The Commission's analysis shows the scale of the challenge that the Government faces if it is to meet its objective of a 60% reduction in carbon emissions by 2050. It argues that this makes nuclear a relatively unimportant contributor to tackling climate change. Several of our witnesses disagreed with this view. The chief executive of EDF Energy asked: "The question is: with what technology do we replace the existing nuclear fleet? If we replace it by coal or gas it is clear that the targets for CO2 emissions will not be achieved".[295] Professor Keith Palmer told us: "I promise you that only one thing will replace it if we do not have new nuclear: a lot more gas-fired power stations".[296] The difference in opinions here is based on varying assumptions about what will take the place of current nuclear generation once it reaches the end of its operating life. If the Government were to do nothing, then clearly gas or possibly coal-fired generation would fill the gap. However, very significant progress on renewable energy or energy efficiency could also achieve this. After a number of years of development, renewable energy currently contributes about 2% of UK energy needs as opposed to about 8% for nuclear power.[297] This suggests that just to stand still in terms of carbon emissions, there would have to be a massive increase in renewables. This is not impossible, but there are a number of constraints that would have to be overcome to make progress towards making it possible.[298] If the Government is to be credible about achieving its carbon objectives, it has to address the issue of what will be the most cost-effective and practicable source of reducing carbon emissions, in considering the pros and cons of nuclear power.

194. There are some carbon emissions associated with the life-cycle of nuclear power stations, as there are with some renewable sources of electricity generation. However, nuclear power can still be considered a low carbon energy source on a par with hydroelectricity and wind power. The contribution nuclear power can make to the carbon reductions required to meet the Government's 2050 objective is relatively small. However, this reflects the scale of the challenge faced and the fact that electricity generation, though significant, is only one source of carbon emissions: space heating and transport emissions are of at least equal importance. The extent to which this should matter to the Government, with regard to nuclear power, depends on its determination to create a low carbon economy, and whether it believes other low carbon technologies or energy efficiency can fill the gap left by closing nuclear plant, which otherwise would almost certainly be filled by gas-fired generation.

Other approaches to reducing emissions

195. The media's coverage of the Energy Review has focused, rightly or wrongly, on the issue of nuclear power. However, as the previous section highlighted, further nuclear power could not, on its own, meet the Government's objectives for carbon reduction—this would require a package of measures, including further expansion of renewable energy and greater energy efficiency. Yet, over the course of our inquiry, we received evidence arguing that a policy decision in favour of nuclear power could detract from efforts in these areas.[299] This section examines these concerns.

RENEWABLES

196. The Government has a target to achieve 20% of the UK's electricity generation from renewable sources by 2020. To this end, it has established the Renewables Obligation (RO) as a dedicated support scheme for the development of renewable capacity that would not otherwise be economically viable under normal market conditions. It is a traded certificate scheme with increasing targets for renewable generation, rising to just over 15% in 2016. The mechanism effectively doubles the price generators get for their electricity. Because the RO effectively operates as a self-contained market for renewable energy within the electricity market, it is unlikely that a policy in favour of nuclear power would affect the incentives of developers to bring forward future renewable generation, at least up until 2016, when the RO targets stop increasing. The way in which the mechanism is designed means that, if developers stopped investing in new renewable capacity, this would increase the returns for those who already operated renewable capacity. In such a situation, so long as the RO remained in place, rational investors should still have the incentive to build further new capacity.

197. However, new nuclear build could nonetheless pose risks to the renewable sector. The Sustainable Development Commission notes that relatively little money (roughly £30 million) is being spent by the DTI on microgeneration capital grants.[300] Indeed, since the last Energy Review, the DTI has actually cut its R&D budget for renewables. This highlights the danger that even though there may still be an economic incentive for the market to invest in renewable energy through the Renewables Obligation, this does not mitigate the risk of political support for renewables diminishing. If investment in R&D drops off, then this would reduce the likelihood of future innovation in certain types of renewables, such as wave and tidal energy, which are not yet commercially viable. Finally, if the Government did decide in favour of new nuclear build, as discussed earlier, we would expect this to be backed by a move towards technology-blind long-term carbon pricing. Such a framework would, arguably, have to supersede the Renewables Obligation if the approach were to be truly technology-neutral. However, such a fundamental change to the means by which the renewables sector is currently supported could undermine future investment.

ENERGY EFFICIENCY

198. The impact of potential new nuclear build on progress with energy efficiency is less clear. The Sustainable Development Commission argued that further nuclear power would send out a message to energy consumers that the Government has plugged the 'energy gap'. In so doing, this might reduce the incentives to cut electricity demand.[301] Whilst we agree that this is a risk, we note that the promotion of energy efficiency should take place through separate policy instruments that seek to raise consumers' awareness of the carbon impact of their energy consumption, and also, for example, through regulation of building standards. In addition, we note the need to take action on energy efficiency across the whole of the energy sector, including in the transport and heating sectors—not just for electricity.[302]

199. The general public is unlikely to support new nuclear power stations unless they are part of a wider strategy that also encourages renewable energy and energy efficiency. There is a risk that a Government focus on new nuclear build would distract from efforts in these two areas. To prevent this, it would have to ensure that nuclear power did not receive preferential treatment, either in the planning system, or in a long-term carbon pricing mechanism. It would also have to demonstrate a genuine political commitment to these two means of reducing carbon emissions in building a long-term national consensus for its energy policy.

Providing grid capacity

200. Any new nuclear build will require direct connection to the UK's electricity transmission network, which is owned and operated by National Grid. Both the siting and size of a programme of new reactors would have an impact on the grid network, requiring investment in upgrades to the system. In this section we look at the extent to which new nuclear build would 'lock' the UK into a centralised grid network, and what the implications are of the timing and siting of new nuclear power stations.

A CENTRALISED GRID NETWORK?

201. The UK's current electricity grid network is essentially 'hierarchical'.[303] Almost all electricity flows from conventional large power generation into the transmission network, and then into largely passive distribution networks, operated by the local supply companies. This would be the case, too, for any new nuclear build. Increasingly, though, smaller scale generation, such as certain renewables, is being connected directly to the distribution networks. In the future, too, expansion of microgeneration could see electricity flowing back up through the system from households. This is known as decentralised generation.

202. The expansion of this different type of generation poses a challenge for Ofgem and National Grid because the electricity network has traditionally been designed for electricity to flow in one direction. The Sustainable Development Commission argued to us that if the Government decided to pursue a programme of new nuclear build, this would represent a continuation of the approach to date of electricity distribution being centralised. In so doing, this would 'lock' the UK into the same system for the next 50 or so years, reducing the likelihood that grid investments would be made that encouraged the connection of microgeneration and other forms of decentralised electricity. Whilst we agree that this would be a risk if the UK was to pursue a very large programme of new nuclear build, such as that which France has followed, other evidence we received suggests that, for a smaller programme, this would not lock the UK into a centralised network.[304] Indeed, the current transmission network pricing structure rewards decentralised generation because it does not entail the investment in grid upgrading that is required for larger power plant located far from the point of consumption.[305]

CONNECTING NEW NUCLEAR BUILD

203. The location of any new nuclear power plant would have a direct bearing on the cost of connecting it to the grid. As we discussed earlier in this Report, there is a possibility that new plant could be built next to existing nuclear power stations, or on the site of fully decommissioned plant. One of the reasons given for this is that such sites would already have the infrastructure in place to connect up a new power station. However, in their evidence to us, Ofgem pointed out that the ability to do this would depend on a number of issues. For example, if there was an existing nuclear power station onsite, an additional 1,000 or more megawatts of capacity from a new station would still require upgrading of the transmission network further down the line. Even where a new nuclear power station was taking over the connection of an old one, if the generating capacity of the previous station was significantly less this could entail upgrading to the grid network.[306]

204. National Grid has estimated the potential cost of upgrading the transmission network for a new nuclear programme at between £850 million and £1.4 billion, depending on its scope and the availability of sites.[307] These costs would have to be met by the developers and could bear heavily on the economic viability of certain sites, especially where there is no current infrastructure in place, or where generation is based some distance from consumption. A further concern is the long lead time required for any grid upgrades because of the need for these to receive planning consent. Ofgem noted the example of the upgrade to the North York line, which was 25 miles long, and took the best part of 12 years to pass through the planning process in the 1990s.[308] This issue is already a concern for the renewables industry.[309] The long lead times for nuclear power should make this less of a concern for the nuclear sector, although decisions on the required grid investment would need to be taken well in advance to prevent future hold-ups.

205. The UK has a centralised electricity grid network, although growth in renewable energy and, in the future, microgeneration are beginning to challenge this approach. We were told by National Grid that a new nuclear programme aimed at doing no more than replacing existing capacity would not act to prevent the further development of decentralised generation. The siting of new nuclear plant, whether near existing nuclear sites or not, will affect the level of investment required in upgrading the transmission network, which could be in the range of £850 million to £1.4 billion—these are costs that will have to be met by developers, thus influencing their investment decision.

Securing electricity supply

206. Concern about future security of electricity supply, given the UK's increasing dependency on gas imports, and the likely future increase in gas-fired generation, is one of the main reasons why the Government chose to hold another energy review so soon after the last one. As we have set out in this Report, we do not believe that the way to energy security is for the Government to fix the proportion of the energy mix that should come from particular technologies. Rather, it should ensure a level playing field for existing technologies, while supporting innovation in new ones. In this section we look at the potential risk of there being an 'energy gap' in the future electricity market, and the extent to which the market will be able to manage this.

WILL THERE BE AN 'ENERGY GAP'?

207. The Government's Energy Review states that with possible nuclear and coal plant closure over the coming years, potentially 20 gigawatts of generating capacity may need replacing in the next ten years. This represents about 30% of current electricity demand.[310] One of the concerns raised during our inquiry was that new nuclear build would not come online in time to fill this gap. The most optimistic predictions for new build are for a first power station to begin generating in 2017 at the absolute earliest. In the meantime, the gap would probably have to be filled by gas-fired generation, therefore increasing the UK's dependency on gas imports.

208. The Energy Review consultation document states that "potential lifetime extensions could serve to extend the period over which closures of nuclear plants take place".[311] The current AGR power stations, operated by British Energy, were originally built with an accounting life of 25 years. As operating experience has built up, the life of each station has been extended for each of seven AGRs, with the most recent, for Dungeness B, announced in September 2005. Table 5 shows the current position on station lifetimes across the British Energy fleet.

Table 5: The current position on British Energy's nuclear power station lifetimes (all AGRs except Sizewell B)

Station
Capacity (megawatts)
Scheduled closure date
Current lifetime
Life extensions already declared
Date of next NII Periodic Safety Review
Hinkley Point B
1,220
2011
35 yrs
10 yrs
Jan 2007
Hunterston B
1,190
2011
35 yrs
10 yrs
Jan 2007
Hartlepool
1,210
2014
30 yrs
5 yrs
Jan 2009
Heysham 1
1,150
2014
30 yrs
5 yrs
Jan 2009
Dungeness B
1,110
2018
35 yrs
10 yrs
Jan 2008
Heysham 2
1,250
2023
35 yrs
10 yrs
Jan 2010
Torness
1,250
2023
35 yrs
10 yrs
Jan 2010
Sizewell B
1,188
2035
40 yrs
0 yrs
Jan 2015

Source: British Energy

209. British Energy can re-assess the lifetime of its reactors in the run-up to their scheduled closure dates. In so doing, it considers the robustness of the reactors' graphite cores to further operation, as well as a number of other technical factors. It must seek approval from the Nuclear Decommissioning Authority for any extension, as this would have implications for the future liabilities of the plant (which the NDA has ultimate responsibility for), although this approval has to be granted if British Energy can prove that an extension would have a positive net present value. This process must conclude at least three years before the planned date of decommissioning. Independently of this, the Nuclear Installations Inspectorate operates a routine schedule of Periodic Safety Reviews (PSR) for each reactor every ten years. This looks at the safety case needed to continue licensed operation. For each of British Energy's reactors, the date of the next PSR is given in Table 3. The outcome of these reviews will inform the company's assessment of the scope for further lifetime extensions.[312]

210. British Energy told us that its aspiration is to maximise the operating life of its fleet. To this end, in June 2006 it announced that it had begun the technical evaluations to support life extensions for Hinkley Point B and Hunterston B, which are the two stations scheduled soonest for decommissioning. This work will conclude in March 2008. In their letter to us, British Energy said they "cannot make judgements about further life extension until this work is done". They went on to say that: "Ten-year life extensions may be possible for some stations, but we may find some station lives cannot be extended this long, and some may not be extended at all".[313]

211. Ofgem also highlighted the possibility of further lifetime extensions to the existing nuclear power stations in their oral evidence to us.[314] They went on to discuss the same issue in relation to coal-fired generation, noting that capital expenditure in the sector would potentially extend the lifetime of some of the power plant that DTI are currently assuming will close in the coming years. Ofgem's Chief Executive, Mr Alistair Buchanan commented on this that he thought "the forward looking analysis has not been broad enough and it has not been forward looking enough in order to have this kind of debate … as to what is likely to happen in the next ten to 20 years".[315]

212. This situation concerns us, as the apparent urgency of the current Energy Review seems to be predicated on the assumption that the country faces an imminent crisis. We agree that some generating capacity, such as the remaining Magnox power stations, will certainly be decommissioned in the coming years, and that the replacement of this poses a challenge for the market. However, whilst we acknowledge that it would not be sensible to presume lifetime extensions for all of the remaining nuclear fleet, equally it would not be prudent for the Government to make long-term policy decisions on the future energy mix in haste, and without full consideration of the evidence, simply because it has assumed that this capacity will certainly not be available. Indeed the fact that British Energy has begun to evaluate possible extensions for two of its reactors suggests the company believes there is a chance that they will carry on operating. We consider that a full and proper assessment of the projected future generating capacity should have been conducted to inform debate before the Government undertook its Review.

PROVIDING CAPACITY

213. In recent years, National Grid has continually reported reserve margins of 21 to 23%.[316] To date, this has been generally viewed as a sensible margin in terms of the grid's "ability to keep the lights on".[317] However, a number of factors may affect this view going forward. For example, if in the future, the market moves to a different balance of flexible versus inflexible plant, this will have to be reflected in the costs of the balancing system.[318] Because of the intermittency of wind power, the large projected increases in wind generation in coming years will require an increase in back-up capacity from elsewhere, to be brought into service on low-wind days. Also National Grid points out that its current system is set up to withstand the instantaneous loss of 1,320 megawatts of power. If new nuclear plant is built that is larger than this level—which is a definite possibility—then additional system operator costs would have to be incurred to secure against the loss of a larger station. National Grid estimate this to be in the region of £50 million to £80 million.

214. Factors such as these could, in future, push up the required capacity margin for the market, at a time when plant closures are potentially decreasing it (although, as noted earlier, it is unclear by how much). In their evidence, National Grid speculated that "they would look to see whether some sort of capacity payments mechanism … could encourage people to bring generation forward so that we can protect the margin", and hence electricity customers from volatile prices.[319] Dr Dieter Helm gave evidence to us suggesting the same. Whilst he acknowledged that the previous capacity arrangements were poorly designed under the Electricity Pool trading arrangements, he argued strongly that the current market did not provide an incentive for generators to invest in excess capacity.[320] We put this view to Ofgem, who argued equally strongly that this is not the case. They pointed to evidence that 40% of current capacity has been built since privatisation of the industry in 1990. They also noted that power companies would not have an incentive to create a crisis in the electricity market by failing to invest in new capacity, as this would only lead to political and regulatory intervention in the industry that could otherwise have been avoided.[321]

215. The issue of a capacity market is somewhat tangential to the arguments for or against nuclear power, although clearly an additional form of price certainty, which such a system would provide, would give greater clarity on the returns to all forms of generation, including nuclear power. As such, we would argue that the Government and Ofgem should continue to monitor the capacity margin and the market's response to changes in it over time, to determine whether intervention may be needed in the future.

216. There is a possibility that a proportion of the UK's existing nuclear power stations may receive life extensions over the coming years. If this is the case, then the potential 'energy gap' faced by the Government will not be as severe as that which the current Energy Review assumes. Whilst we accept that the long lead time on nuclear build requires a decision soon if new capacity were to come on stream before the end of the next decade, we question the haste with which the Government is seeking to conclude its current Review, especially given the short timeframe it has allowed for consideration of certain key pieces of evidence. Changes in the energy mix, such as increased wind power and potential new nuclear build, will in the future increase reserve capacity requirements. Developments in this area will require close monitoring by the Government and Ofgem as, if there is any sign of market failure, a swift policy response—perhaps in the form of some capacity payment—will be necessary.




288   For example, Q 111 (Sir Jonathon Porritt); Appendices 16 (EDF Energy) and 27 (Friends of the Earth)  Back

289   Q 2 (Prof William Gelletly) Back

290   www.stormsmith.nl Back

291   Sustainable Development Commission, The role of nuclear power in a low carbon economy, Paper 2: Reducing CO2 emissions - nuclear and the alternatives, March 2006 Back

292   Ofgem, Our energy challenge - Ofgem's response to the Government's Energy Review consultation, May 2006 Back

293   Op. cit. Back

294   Ibid. para. 1, page 30 Back

295   Q 226 (Mr Vincent de Rivaz) Back

296   Q 213 (Prof Keith Palmer) Back

297   Department of Trade and Industry, Digest of United Kingdom energy statistics, 2005 Back

298   See for example, Department of Trade and Industry, Renewables Innovation Review, 2005 Back

299   Appendices 2 (Airtricity), 20 (Environment Agency) and 46 (Royal Society for the Protection of Birds)  Back

300   Sustainable Development Commission, The role of nuclear power in a low carbon economy, March 2006 Back

301   Ibid. Back

302   Energywatch, Response to 'Our Energy Challenge...', 2006; Appendix 3 (Association for the Conservation of Energy) Back

303   Appendix 1 (ABB Ltd) Back

304   For example, Appendix 32 (Institution of Electrical Engineers); Q 457 (Prof Gordon MacKerron) Back

305   Q 501 (Mr Steve Smith of Ofgem) Back

306   Q 503 (Mr Steve Smith) Back

307   Q 139 (Mr Cocks) in Trade and Industry Committee, oral evidence on Increasing UK dependence on gas and coal imports, HC 1123 of Session 2005-06 (henceforward 'oral evidence on gas and coal') Back

308   Q 507 (Mr Alistair Buchanan) Back

309   See for example, National Audit Office, Renewable Energy, February 2005 Back

310   Department of Trade and Industry, Our energy challenge - securing clean, affordable energy for the long-term, January 2006, page 40. Back

311   Ibid. page 39 Back

312   Appendix 10 (British Energy) Back

313   Ibid. Back

314   Q 474 (Mr Alistair Buchanan) Back

315   Ibid. Back

316   Q 482 (Mr Alistair Buchanan) Back

317   Q 131 (Mr Murray) in oral evidence on gas and coal Back

318   National Grid, Response to DTI Energy Review Consultation, April 2006 Back

319   Q 131 (Mr Murray) in oral evidence on gas and coal Back

320   Q 287 (Dr Dieter Helm) Back

321   Q 484 (Mr Alistair Buchanan) Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 6 September 2006