Select Committee on Trade and Industry Written Evidence


ADDENDUM 3—REPORT ON SUPPLY/DEMAND SENT TO DTI IN MARCH 2005

ANALYSIS OF UK GAS SUPPLY/DEMAND FOR DTI ENERGY TEAM

SUMMARY

  This paper looks at the supply/demand balance for next winter under several scenarios, including the loss of Interconnector import. The analysis is based on real data of actual supply, demand and temperatures seen and reported publicly for the UK.

  Recent experience has highlighted vital flaws in the assumptions underpinning all previous UK gas supply/demand models. These are:

      (i)  That the Interconnector will import at maximum rates when demand and price are high in the UK market and

    (ii)  The level of deliverability of beach gas.

Supply Capability

  The supply capability of UK gas fields is reducing at an alarming rate. The reduction in supply capability has already exceeded the capacity of the Interconnector and the main UK storage facility at Rough. The capacity of UK gas fields is well short of winter demand requirements. The UK is critically dependent on storage, imports from Norway and Interconnector imports. For the past few winters the combination of supplies has been sufficient to meet demand but this is mainly due to having very mild winters and a higher capacity in the UK gas fields.

  The forecasts made by Transco for beach supplies to the UK seem to consistently over state the amount of gas available to meet UK demand. For winter '04/05 Transco assumed peak supplies of 364 mcm/day and sustained supplies of 346 mcm/day. In practice we have seen a peak of 331 and an average of 305 mcm/day from November to February. This "shortfall" of 30-40 mcm/day is more than the current Interconnector import capacity.

Next Winter

  Looking forward to next winter there are two key projects increasing the supply available to the UK. One is the new LNG facility at the Isle of Grain and the other is increased import capacity on the Interconnector. If both of these projects are delivered, the maximum supplies of gas available to the UK should be able to cope with a "one in three" winter demand but are not able to cope with winter demands that can be expected to occur one in every six winters.

  If there is a delay to the Interconnector project or gas is not available to fill the new capacity then supplies are not sufficient for demands that can be expected in a "one in three" winter.

  If the UK experiences the combination of cold weather and lack of supply from the Interconnector (as seen in March 2005), it is expected that significant shutdowns of the UK customer base will be required within two weeks. The combination of loss of Interconnector supplies and cold weather should not be considered as independent events. Instead, they are most likely to be coincident as cold weather in the UK is likely to coincide with cold temperatures on the continent increasing the likelihood in loss of gas imports.

SCOPE OF ANALYSIS

  This analysis was prompted by the experience during the recent three-week cold spell in the UK, which saw a combination of high UK demand and low Interconnector flow. This short cold spell saw key UK storage stocks fall to alarmingly low levels from a healthy position and prompted concerns about supply capability for next winter. This paper attempts to assess the supply/demand balance in the UK and assess whether the UK is likely to run short of gas next winter. Previous models of UK supply have assumed that high UK prices relative to continental wholesale prices would lead to maximum imports to the UK during high demand.

  During the recent cold spell UK prices reached £1.60/therm while imports through the Interconnector were close to zero. The average Day Ahead price over the 18-day period from 21 February to 10 March was around 65 pence per therm. This compares to a wholesale price of gas in Continental Europe is about 28 pence/therm at present.

ANALYSIS METHOD

  The analysis is done in six stages:
Stage 1:Define the relationship between temperature and gas demand for UK market.
Stage 2:Using data from 1970 to 2004 assess the probability of various temperature events.
Stage 3:Use the temperature data and the correlation from stage 1 to define likely UK gas demand scenarios.
Stage 4:Assessment of UK gas field production capacity for next winter.
Stage 5:Assess total supply capability for next winter.
Stage 6:Compare supply capability to demand requirements for next winter.


ANALYSIS RESULTS

Stage 1:  Define the relationship between temperature and gas demand

  The average monthly temperature data was taken from DTI table 1.1.8. The "Gas Output from the Transmission System" from DTI table 4.2 was used as a basis for demand.

  Combining these two sets of data gives the graph on the following page. It is easy to see that there is a very strong correlation between temperature and demand. Statistically there is a 98% correlation between the two. From this data it is possible to determine a formula (given in the graph below) linking the two sets of data. This includes the demand for the UK but does not include the use in the transmission system (about 2 mcm/day) or the use in Ireland (about 13 mcm/day).

  Including the demand from Ireland and the use in the transmission system the formula used in this analysis is:

        Gas Demand (mcm/day) = 0.525 * (temp C)2—28.8 * (temp °C) + 508



  This gas demand is made up of two basic categories. There is a stable demand of around 80 mcm/day consumed by sites directly connected to the NTS. This is a combination of power stations and large industrial demand and does not vary with temperature. The remaining demand is delivered via the LDZ's (Local Distribution Zones). This demand is a combination of domestic and small industrial/commercial customers. The LDZ demand is highly temperature dependant.

Stage 2:  Assess the probability of various temperature events

  The temperature data from DTI table 1.1.8 gives monthly average temperatures for each month from 1970 to 2004. Using this data it is possible to estimate the likelihood of various winter scenarios. Rather than look at rare events like a "one in 50" winter, we have used the data to assess scenarios that are quite likely. The table below shows the results of this analysis.
1970-2004Below 5C Below 4CBelow 3C Below 2CBelow 1C Below 0C



One Month
29 161163 1
Two Months2011 310 0
Three Months80 000 0
One Month83%46% 31%17%9% 3%
Two Months57%31% 9%3%0% 0%
Three Months23%0% 0%0%0% 0%


  In the period from 1970 to 2004 there are 35 winters. Of these, 29 have seen at least one month below 5°C, 20 have seen two months below 5°C and 8 have seen three months below 5°C. This can be converted into a probability; ie there is an 83% chance that a winter will have at least one month with temperatures below 5°C, a 57% chance of two months below 5°C etc. The blocks in yellow in the table above give the key probabilities used in this analysis. In summary for next winter the key probabilities are:

  There is a 9% chance (1 in 11) that we will experience one month below 1°C.

  There is a 17% chance (1 in 6) that we will experience one month below 2°C.

  There is a 31% chance (1 in 3) that we will experience one month below 3°C.

  There is a 46% chance (1 in 2) that we will experience one month below 4°C.

  There is a 31% chance (1 in 3) that we will experience two months below 4°C.

  These are relatively high probability events. It is easy to become complacent about the chance of cold weather because we have experienced several of the warmest winters on record over the past few winters. The chart below shows the lowest winter temperatures each year since 1970. The period in the mid 70's saw a dramatic change from "warm" to "cold" winters, demonstrating that it is entirely possible to see a sudden return to "cold" conditions.



Stage 3:  Develop a demand profile for winter 2005-06

  From the correlation from Stage 1 and the temperature profiles from Stage 2 it is possible to determine the likely demand requirements for next winter. The table below shows the demand expected for each temperature.
1970-2004Below 5C Below 4CBelow 3C Below 2CBelow 1C Below 0C


One Month
83% 46%31%17% 9%3%
Two Months57%31% 9%3%0% 0%
Three Months23%0% 0%0%0% 0%
Demand (mcm/day)377401 426453480 508


  This demand can be converted to graphical format giving a demand/probability profile as shown in Appendix 1.

Stage 4:  Assessment of UK gas field production capacity for next winter

  It is well recognised (Transco Winter Outlook Report and DTI commentary on gas supply figures) that the UK production of natural gas has been declining rapidly in recent years. The following graph shows the DTI data for UK gas production in each of the last nine winter periods. The graph shows the best month and the best "two-month" period for each winter. At the current rate of decline the UK sources will only be able to produce at a monthly average rate of 275 mcm/day by next winter. The reduction in capacity that has occurred since 1990 is more than the combined capacity of the Interconnector and long-range storage.


Stage 5:  Assess total supply capability for next winter

  The Supply capacity available to the UK comprises:

      (i)  UK gas production (described in Section 3);

    (ii)  Imports from Norway (this gas can flow to the UK or directly to Continental Europe);

    (iii)  Imports through the Interconnector (ICUK); and

    (iv)  Various storage facilities (generally filled in summer and emptied out during winter).

  When added to the other supply sources it is possible to define a "supply stack" for the winter. During 2005 there should be a new LNG import facility coming on line (Isle of Grain conversion project) and by the end of December 2005 the import capacity of the Interconnector should be increased by the installation of compressors at Zeebrugge. From these different supply options we have developed four supply scenarios as shown in the table on the next page.


Modelling Assumptions UK Gas Fields and Imports
Scenario 1 High Import Scenario 2 Current Import Scenario 3 Low Import Scenario 4 Export


UK Gas Fields
mcm/day 274274274 274
Norwegian Importsmcm/day 40372817
Interconnectormcm/day 47250-50
Isle of Grain LNGmcm/day 101000


Beach
mcm/day 314311302 291


  Scenario 1:  Maximum supply from all supply sources.

  Scenario 2:  Current import from Norway and ICUK, with new import from IOG.

  Scenario 3:  No imports from ICUK or IOG. Norway import at levels during winter 2003-04.

  Scenario 4:  Interconnector in export mode. Norway import at levels during winter 2002-03.

  The expected "Beach" supplies (UK production and Norwegian Imports) for each scenario are given at the bottom of the table. The beach supplies for the current winter (2004-05) averaged 305 mcm/day. If the beach supplies are declining at 7% per year (as reported by Transco and DTI) the expected beach supplies would be 284 mcm/day by winter 2005-06. All of the scenarios assume beach supplies that are higher than this.

Assuming all of the supply sources at maximum capacity the "supply stack" looks like:



  This shows the maximum capacity that is available by next winter. By using ALL of the storage facilities at maximum rate and assuming maximum imports from Norway and the Interconnector it should be possible to supply demand of 488 mcm/day for five days. After five days at this rate LNG storage would be empty and the maximum capacity falls to about 435 mcm/day. After only 18 days most of the Medium Range storage facilities would be empty and supply would fall to a level of about 418 mcm/day.

  This "supply stack" depends to a very large extent on assumptions about Norwegian imports and the Interconnector flows and to a lesser extent on the availability of LNG at the new Isle of Grain terminal. During the recent cold spell we saw the gas Interconnector reduce to virtually zero flow as a result of cold weather on the continent. It is reasonable to assume cold weather in the UK is likely to be associated with cold weather on the continent and therefore gas is less available from the continental sources at times when the demand for it is most urgent. This is the basis for Scenario 3, which assumes a reduction in Norwegian imports and zero imports from the Interconnector.

  The graph below shows the four supply scenarios.



Stage 6:  Compare supply capability to demand requirements for next winter

  The graphs in Annex 2 combine the supply and demand figures from the previous analysis. They are shown with the best supply option first.

Scenario 1:  Maximum Supply

  With maximum supply it is possible to meet the demand for any 3°C months but difficult if the temperature is 2°C or below. For months below 2°C there would need to be significant demand side response to reduce demand. There is a 17% chance (one in six) of demand response being required even with all new supplies available at maximum capacity.

Scenario 2: Current Imports

  The maximum supply case assumes the increased capacity through the Interconnector is available. This is scheduled to be on line at the end of December 2005. If this increase is not available, the supply picture is shown by the second graph in Annex 1. In this case the UK struggles to meet demand if the temperature is below 3°C. There is a 31% chance (one in three) of experiencing a month like this in the coming winter. Under this scenario very significant Site closures to reduce UK gas demand could be required. As can be seen from the graph the supply shortfall is about 80 mcm/day if the UK has a month below 1°C. This is the capacity of all the direct NTS demand which includes power stations.

Scenario 3: Low imports

  During the very recent cold spell the UK experienced a combination of events that give great cause for concern. The cold weather in the UK (temperatures were below seasonal normal but were not exceptionally low) was coincident with cold weather on the continent and supplies of gas through the Interconnector effectively stopped. Additionally it is understood LNG ships were not available to supply Zeebrugge. This set of real events is the basis of the third scenario. This is shown in the third graph in Annex 1. As can be seen from the graph this level of supply causes severe problems even under the mild 5°C demand conditions. This supply scenario would, very quickly, lead to closure of large parts of the UK supply system including parts of the Local Distribution Zones. Under this scenario there may not be enough gas to preserve supplies for domestic customers.

Scenario 4: Interconnector Exporting

  The fourth graph shows the impact of the Interconnector exporting during winter months. There is not enough UK supply to even begin to meet demand in this scenario. The UK would have to shut the Interconnector in this scenario to avoid a possible National Emergency. This would effectively convert this scenario to the same as scenario 3.

CONCLUSIONS

  This analysis shows that events we have already experienced during the current winter would lead to dramatic gas shortages during next winter. In recent years the UK has not faced severe shortages because we have had more supplies from UK gas fields and we have been fortunate to experience some of the warmest winters on record.

  There are two key core assumptions in this analysis that differ from any analysis we have seen previously. They are:

      (i)   Beach supply capability—in winter 2004-05 this has been much lower than assumed in the "Winter Outlook Report" published by Transco in October 2005. For winter 2004-05 Transco assumed peak supplies of 364 mcm/day and sustained supplies of 346 mcm/day. In practice we have seen a peak of 331 and an average of 305 mcm/day. This "shortfall" of 30-40 mcm/day is more than the current Interconnector import capacity. We consider that the beach flows reported do represent a good measure of the capability of the off-shore infrastructure given the (high) level of NBP prices in the prompt market. We question why there is such a large difference between the expected and actual beach flows. Our expectation is that there will be further decline for the coming winter.

    (ii)  Interconnector behaviour—it has been assumed that in winter the Interconnector will provide a base load flow up to its physical flow capacity. This winter, we have seen very real evidence that this assumption is not robust, especially at times of cold weather, when demand is highest.

  Looking forward to next winter, the UK needs all the new supply projects to be delivering and relatively mild weather to avoid supply shortages. If the increased Interconnector capacity is not available (it is only planned to come on line at the end of December) or we experience cold weather the UK can be expected to hit significant supply shortages during the coming winter.

SOURCE INFORMATION/REFERENCES

  This analysis draws on information from the DTI and Transco websites.

  DTI table 1.1.8 is used for temperature data going back to 1970.

  DTI table 4.2 is used for supply and demand data. This has been compared to data from the Transco Information exchange website to validate, where possible, the data to use.

  The ICUK website has been used as a source of historic flow data from the Interconnector.

  Independent information has been used as a source of Norwegian imports.

  Transco Winter Outlook Report—October 2005.





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 29 March 2006