Select Committee on Work and Pensions Minutes of Evidence


Annex

CMS RELEASE SCHEDULE AND FUNCTIONALITY

CMS RELEASE 1

  CMS R1.0 first went live in Livingston Jobcentre Plus on 14 July 2003 as the first major system component of the modernisation of Jobcentre Plus. It provided:

—    claim gathering for Income Support, Jobseeker's Allowance, Incapacity Benefit, Housing Benefit, Council Tax Benefit, Child Support Agency;

    —    determined eligibility for associated benefits;

    —    electronic interfaces with the Personal Details Computer System, the Departmental Central Index, the Income Support Computer System, JSA Payment System, Pensions Strategy Computer System (Incap) to obtain the most up to date personal details;

    —    electronic interface to the Labour Market System to undertake job searches and to book Financial Assessor/Personal Adviser appointments; and

    —    a full range of customer specific notifications.

  Following the pilot, national rollout commenced from 27 October 2003 in line with the Jobcentre Plus 2003-04 rollout schedule.

CMS RELEASE 1.8

Release 1.8 was initiated in recognition of some early application performance problems. This was implemented over four separate weekends from 17 May 2004 to 2 August 2004.

An ongoing Programme of minor releases between August and November 2004 introduced further improvements to CMS performance.

CMS RELEASE 2

CMS Release 2 was delivered on 13 December 2004. All sites live with CMS Release 1 on 10 December 2004 were successfully migrated to CMS Release 2 over the migration weekend Friday 10 December to Sunday 12 December 2004.

National rollout of Release 2 continues as part of the wider Jobcentre Plus Implementation to the remaining Legacy Jobcentres and Social Security Office sites and Contact Centres.

The key change with the introduction of CMS Release 2 was the electronic transfer of claim data recorded on CMS to ISCS and JSAPS to support benefit processing.

CMS RELEASE 2.1

CMS Maintenance Release 2.1 was implemented on 24 January 2005. The primary purpose of this release was to fix those defects identified during Release 2 System Integration Test, Product Assurance Test and Model Office testing that had not previously been cleared.

CMS RELEASE 2.2

CMS Maintenance Release 2.2 was implemented in April 2005. This Release fixed some of the problems identified in live running following implementation of CMS Release 2 in December 2004.

CMS RELEASE 3

CMS Release 3 went live on 31 October 2005. This Release enhances previously delivered releases of CMS; it consists of several improvements to the system, that significantly reduce the reliance on clerical products, supports new functionality, are easier for staff to use and ensure that appropriate support for customers is maintained.


A.  EXECUTIVE SUMMARY

1.  Introduction

  1.1  This summary business case has been prepared and updated primarily to set out the critical financial considerations as they stand at 22 March 2004 in order to secure internal DWP approval from a Gated Review and to seek agreement from HM Treasury to the business case. Previous iterations of the business case set out the history of the project, the details of the selection of software package and the planned development of the system. This background is not repeated here.

  1.2  This business case is written in the context of the creation of the Department of Work and Pensions and the Jobcentre Plus business. The Jobcentre Plus vision of service delivery, introducing a work focused element for all our customers, has had a marked effect on the original requirements and functionality of a Customer Management System (CMS). The previous business case envisaged three planning used CMS releases 1.0, 1.1 and 2.0. Due to a number of factors but predominantly cost containment this has been reduced to two releases R1.0 and R2.0.

  1.3  CMS release 1.0 was an enabler for the deployment of the Jobcentre Plus service delivery vision and as such do not in themselves generate significant savings but rather lay the foundations for future savings as the system becomes the normal interface between customers and Jobcentre Plus staff prior to the Work Focused Meeting. Release 2.0 should attract comparatively marginal costs and generate comparatively significant savings. CMS will then be superseded by CAM (Citizen Account Management) from April 2006. CAM will deploy the same electronic data capture methodology but using a Siebel software package. It is envisaged therefore that the savings introduced by moving to a CMS type "system" will continue even though CMS per se may no longer be the actual system deployed. Such savings are therefore scored in this business case and are not repeated in the CAM business case.

  1.4  There will also be significant benefits derived from CMS in terms of delivering an efficient, consistent and better service to customers, and in delivering an electronic communications service, consistent with the Government's modernisation agenda, in a particularly visible area of contact with large numbers of the public. It would be difficult to ascribe a monetary value to these benefits ahead of the system actually being deployed and observed in live conditions. It is planned therefore to revisit the benefits realisation plan once R1.0 is up and working and has had chance to settle down. A similar approach will be adopted for R2.0.

  1.5  CMS is the necessary IT system which will enable Jobcentre Plus to arrange and accommodate the extra 2,200,000 work focused meetings required each year to meet the new policy of work focused meetings for all customers claiming benefit.

  1.6  The deployment of CMS enables DWP to make progress towards meeting PSA targets and takes the Department significantly closer to meeting the aims of e-Government.

2.  Background to the Business Case

  2.1  The changes to requirements needed to meet the Jobcentre Plus vision have been considered and the assumptions surrounding business processes have been re-visited and tested. In addition, savings in previous business cases were dependant on the re-platforming of ISCS/JSA, which has been cancelled. These factors have lead to some significant changes to the financial data previously presented.

  2.2  This business case uses the most recent financial data available and incorporates the contractual situation as envisaged at 22 March 2004. Discounted Cash Flow schedules are attached at annex 1 to 3 that covers three possible scenarios relating to the costing of CMS.

  2.3  These three scenarios cover CMS costs and savings from 2000-01 to 2012-13 because the original project commenced in 2000 but the current contractual arrangements are based around a series of fixed price packages plus some ongoing "system fixes" which may still be contained within a long term service contract beginning in 2003-04 covering the following 10 years. The actual contractual arrangements are those which deliver best value for money:

    (i)  Annex 1—shows the total costs with the pre April 2002 costs being incorporated but without the re-platforming of ISCS/JSA;

    (ii)  Annex 2—excludes costs incurred prior to April 2002; the proposition being that these should be regarded as sunk costs since the new Agency led to a totally different work focussed specification of requirements; and

    (iii)  Annex 3—reflects the latest financials as at March 2004.

14 November 2005. These annexes have been taken out as they contain details of the commercial contacts with the suppliers of the software, the IT implementation costs and the IT live running contracts.

3.  Business Case Objectives

  3.1  The objectives are to present the latest financial information and set out the continued justification for the CMS project, gain gated approval to roll out R1.0 nationally and continued HMT approval to release the appropriate Welfare Modernisation Funds to fund the changes proposed by this project.

  3.2  14 November 2005—all figures in £'s millions.



2002-3
2003-04
2004-05
2005-06
2006-07
2007-08
Then five years at
Total
Costs:

Project
8.7
5.7
7.0
3.15
0.0
0.0
0.0
24.6
IT
17.9
95.96
57.76
7.8
16.13
9.235
7.0
260
Implementation
0
3.5
9.6
9.5
7.4
7.9
7.9
77.4
Total
26.6
105.2
74.4
40.4
23.5
17.14
14.9
361.989
Savings:
DEL
0
0
0
18.125
25.375
31.0
31.0
229.5
AME
0
0
0
17.439
30.061
30.513
30.513
230.578
Total
0
0
0
35.564
55.436
61.5
61.5
460.078
Net Cashflow1
-26.6
-105.2
-74.374
-4.849
31.9
44.375
46.388
98.089
Net Present Value of Savings over 10 years up to 2012-13 is
£40.135 million

4.Benefits and Savings


  4.1  These have been calculated on the basis of release 1.0 being available in September 2003 and Release 2.0 in November 2004.

  4.2  DEL savings are calculated to be £31 million per year. AME savings are calculated to be £30.5 million per year.

    (i)  The take up of savings assumes no savings will be taken in 2004-05 even though Release 2 will be deployed from November 04.

    (ii)  55% of steady state savings will be taken in 2005-06, 85% in 2006-07 and 100% in 2007-08.

    (iii)  This take up pattern recognises that an entirely new way of processing customer data is being used and will take some time to bed in.

  4.3  This profile has been agreed with the project and the business and is consistent with the Integrated Modernisation Business Case and the assumptions around a continuous rollout of Jobcentre Plus.

5.  Costs

  5.1  The IT costs reflect a cost of £260 million maximum plus related finance charges.

  5.2  Project costs, IT costs and Implementation costs up to 2012-13 are estimated at £24.6 million. Contact centres form the infrastructure for the delivery of the customer focused business processes supported by CMS. The costs are not included in the DCF schedules as they form part of the Integrated Modernisation Business Case and specifically the Jobcentre Plus Implementation Business Case. They are therefore not funded through the CMS project. Total undiscounted costs of CMS are £362 million.

6.  Financial implications

  6.1  The three scenarios outlined in section 2.3 above show a net present value of savings from CMS for each as being;

    (i)  The base case (Annex 1)  £XX.

    (ii)  Excluding pre April 2002 costs (Annex 2)  £XX.

    (iii)  Current cost indications prior to revisiting the benefits realisation plan (Annex 3)  £XX.

  6.2  A discount factor of 3.5% has been used in line with current policy and guidance. However the previous iterations of the Business case were based on the then Treasury rate of 6%. If we apply the old rate on the base case, the final Net present Value would decrease to £8.8 million, still positive but clearly showing a worse return on the investment.

  6.3  The Internal rate of Return for the base case is 6.83% based on the revised base case.

7  Contractual arrangements

  7.1  The arrangements set out below are still subject to final contractual signing between EDS, IBM and DWP but are based on verbally accepted proposals as at this date.

  7.2  CMS will be developed by IBM but delivered and supported by EDS via a series of fixed price packaged contracts.

  7.3  The fixed price packaged contracts are interlinked and include explicit deliverable products or key milestones against which progress is being tracked, monitored and reported to the appropriate governance arrangements. An appropriate sum or sums will be retained should the specific deliverables or key milestone targets not be met. There is the intention, via the commercials, to formalise the rectification risks as belonging to IBM

  7.4  More detailed particulars of the work packages and the payment conditions relating to them are set out in section G below.

B.  STRATEGIC CONTEXT

8.  Introduction

  8.1  The Integrated Modernisation Business Case (IMBC) written to cover the deployment of the Jobcentre Plus service delivery vision, described CMS as an enabling project. Enabling projects are central to the development of Jobcentre Plus and were brought together in the IMBC to demonstrate how they support the delivery of the vision.

  8.2  CMS was described as follows; CMS is the means by which we plan to enable telephone based initial contact for our customers. This project will start delivery of its functionality from September 2003 and is linked to the planned rollout of Jobcentre Plus. CMS will collect the relevant data on each customer to populate the legacy systems, which in turn enables the work-focused interview and the electronic calculation of benefits, via ISCS/JSA. The two main benefits to Jobcentre Plus will be that information will be collected once only and be accurate, thereby saving time in future work focused meetings and the considerable clerical rework currently required. In addition, and to some degree more important than the above, it will improve customer service and introduce the concept of job broking at a much earlier stage in the client contact process.

  8.3  CMS will gather information electronically by enabling initial contact by telephone to dedicated contact centre staff. While it is technically possible to deploy the required systems and telephony to staff wherever they are based, it is clear that significant savings and efficiencies will be achieved by brigading staff together in contact centres. It is demonstrable from the experience of other similar organisations that such centres enable best practices to be shared and worst practices to be eliminated, as well as providing a standard and professional customer service.

C.  REQUIREMENTS

9.  Need for the electronic capture of data

  9.1  Research conducted at workshops with field colleagues confirmed that on average claims for benefits require more that just the initial handling process. For IS and JSA claims there are two additional handlings and for IB claims, one. Furthermore all change of circumstances notifications require additional handling. Staff at workshops confirmed that these were "normal" parameters for re-working on claims. Therefore on average all claims are re-processed and a significant amount of staff time in benefit processing offices is spent correcting errors or gathering additional information.

  9.2  Incorrectly completed forms result in benefits often being paid unjustifiably or for incorrect amounts. This contributes significantly to the £2 billion per annum lost to official and customer error. Considerable staff resources are then utilised trying to collect erroneous overpayments of benefit from those members of society least likely to be able to repay.

  9.3  Benefits payments to the most vulnerable members of society are often delayed while errors are corrected, placing these people in an unnecessarily precarious financial position. Furthermore job seekers will be more concerned about what amount of benefit they will be receiving rather than finding a new job.

  9.4  The department, recognising these issues, established the project to consider and pursue a means to resolve them in an efficient and cost effective manner. The result of this work was the creation of the CMS project.

  9.5  CMS will prevent these problems occurring in most cases because of the more efficient information gathering process driven by the scripts which use expertise derived from the latest contact centre industry standards. Furthermore Jobcentre Plus staff in contact centres will have sufficient knowledge of benefit processing to ensure that the correct information is gathered once and used properly. This will result in less staff resources being needed to correct errors and chase debts. It will also mean that the correct benefit will be paid more rapidly to those members of society who need financial assistance.

  9.6  A speedy and accurate confirmation of benefit should lead to a reduction in the number of, and difficulty of, aggressive confrontations with customers thereby enabling the Jobcentre Plus ethos of a professional office atmosphere to develop with the consequent alleviation of Health and Safety concerns. At present there is not sufficient evidence in order to place metrics on such benefit, however a very brief initial study post go live in Livingston indicated that additional savings could be garnered and a more detailed study is planned for June/July 04 once the staff using the system have become familiar with it ie in live and "normal"running.

  9.7  All Jobcentre Plus customers will be directing their effort into seeking work more quickly as they will have confirmation of the fact that they will receive benefit, and be informed of the amount, in four days at maximum and are introduced to the concept of job seeking during the course of their initial contact with us.

D.  OPTIONS

10.  The four possible methods of data collection

  10.1  Option 1. Continue with the customer completing forms that are complex and lengthy. This is the do nothing option and would not address the need to prevent/reduce the numerous errors occurring, which are leading to excessive staff time spent correcting those errors and to incorrect amounts of benefit being paid. The policy decision taken which requires all customers who claim benefit to attend a work focused meeting, obligates Jobcentre Plus to arrange and conduct 2,200,000 extra interviews each year. Without CMS the extra clerical costs that would fall on Jobcentre Plus would be in the region of 2,000 staff unit years or £30 million for the additional work focused interviews and clerical claims handling. It is estimated that the pre CMS benefit processing cost is £47.5 million that compares to a post CMS cost of £16.9 million per annum. Added to this would be the extra estates and IT costs needed to accommodate and support the extra 2,000 staff.

  10.2  Option 2. Simplify the forms being used. This would be problematic given that DWP must ensure that customers are aware of their statutory rights and obligations and the number of IT systems on which their details are stored. Proper scripting of the electronic data collection process does ensure that statutory requirements are met, customers are treated timeously and consistently, data is available for transfer between systems minimising handling and keying errors.

  10.3  Option 3. Develop a Customer Management System incorporating off the shelf package software and adopting a contact centre approach to data gathering, modernising our interface with customers, gaining the advantages of economies of scale and developing best practices.

  10.4  The software package chosen is Curam, which has been developed to process benefit payments as well as providing a scripting facility for telephonic information gathering. Whilst this benefit processing capability will not be utilised for releases 1.0 and 2.0, the fact that it could be made available, with further work, was considered as part of the IS/IT strategy.

  10.5  Option 4. Provide desktop computers in Jobcentre Plus offices allowing customers to complete forms on line that would be edited and validated in real time. This would involve considerable expense as the large number of desktop computers required would have to be vandal proof and the cost of educating our customers unfamiliar with desk top computers would not be cost effective or particularly efficient.

  10.6  Option 3 has been selected as providing the most viable solution to the problem. It also provides enabling technology, improves customer service and reduces errors.

E.  COSTS

11.  Total costs 2002-03 to 2012-13

  11.1  Total costs are estimated as;

    (i)  Project costs (internal)  £24.6 million.

    (ii)  IT costs  £260 million.

    (iii)  Implementation costs (internal)  £77.4 million.

    (iv)  Contact Centre costs[2]  £380.1 million.

  11.2  The most significant assumptions incorporated in the costs set out above are;

    (i)  The IT costs reflect the actual contractual arrangements currently in place or subject to final ratification with IBM and EDS. Financing charges have been reduced commensurate with the reduced risk arising from the fixed price nature of the initial part of the contractual arrangements.

    (ii)  That training costs will be £3.7 million, and "backfill" costs will be £3.7 million. These costs represent CMS specific training and not process (labour market or benefit knowledge) or induction for new staff which is covered by other sources including IMBC. The costs assume an average number of days training per staff member and have been validated by training experts;

    (iii)  The £X.Xm ongoing annual IT running costs cover the continued operation, maintenance and provision of the CMS service including costs to cover release 2.0.

    (iv)  That telephone charges will arise from two directions. First the incoming call will last around 15 minutes and be at a local rate for the customer. Jobcentre Plus will pay for the difference between the local and the actual rate. This has been estimated at £2 million per year. Second, the call back will last around twenty-five minutes at the expense of Jobcentre Plus, and this is estimated at £3.5 million per year.

    (v)  That volumetrics data is the most up to date forecast of new, repeat claims and change of circumstances available from Analytical Service colleagues.

12.  Costs avoided

  12.1  In addition we have avoided the costs of re-keying change of circumstances information by continuing with the "as is" process. CMS will not enable change of circumstances information to be "pushed" to legacy systems. Instead this functionality will now be developed as part of CAM. 14 November 2005—CAM was the Customer Account Management project, which was not pursued. This process will continue to be done clerically, as it is now, and therefore in the short run has a NIL cost impact. These costs equate to £22 million per annum and will be avoided when CAM is operational.

13.  Release management

  13.1   Release 1.0 went live in September 2003 and Release 2.0 is due to go live in November 2004 and the costs for both are now contained within fixed price packages. The only remaining contractual issue is around the live support costs, agreement for which has now been reached and subject to gate approval will be contractually documented.

F.  SAVINGS

14.  Total savings 2002-03 TO 2012-13

  14.1  Total savings are calculated as;

    (i)  DEL (undiscounted)  £229.5 million.

    (ii)  AME (undiscounted)  £230.5million.

  14.2  The DEL savings represent administrative processes no longer required and savings in goods and services as a result of the new ways of working the information gathering front-end system brings. Less administrative costs will be incurred correcting errors. Currently customers are unaware of all the evidence that they are required to produce for a successful work focused meeting. CMS will provide a short checklist for the customer and therefore abortive meetings will be rare.

  14.3  The AME savings represent the savings arising from correct information being obtained during the initial telephone call and the subsequent call back. They further depend on the inclusion of risk profiling and trained operators being able to address inconsistencies or referring them to Financial Assessors for further consideration. CMS, Fraud Strategy Unit and Analytical Services Division devised a method of determining the savings. This entailed mapping the correct information against Quality Support Team and Area Benefit Review error data sets and then quantifying the result of eliminating those errors. All business owners have signed off the AME savings claimed as an accurate assessment.

  14.4  No savings were ever included in this business case relating to carrying out changes of circumstances electronically as in effect the "process" does not change. Currently we take change information from clients face-to-face or in writing and then manually key in those changes to the legacy systems. Were we to have developed an electronic system to handle change of circumstance detail, we would still be taking the change information from clients and keying it into our systems.

G.  CONTRACTUAL ARRANGEMENTS

15.  Contractual arrangements

  15.1  The details set out below have been negotiated and agreed with IBM and EDS but the live support costs are subject to final ratification by the ORR gate prior to a contract being signed.

  15.2  Release 1.0 has been developed and successfully delivered and went lie in September 2003.

  15.3  Release 2.0 has been developed and is now undergoing performance and systems testing prior to going live in November 2004.

  15.4  Hardware for testing and Cúram licences. There is a contractual commitment to pay, in part, for the necessary production hardware and the software licences. These costs are included in the total costs and the DCF schedules as a proper cost of deploying CMS.

  15.5  Live support contract from September 2003. The costs are based on the fact that some transfer of development risk into a long-term service contract has been achieved and represent value for money. 14 November 2005—two sentences of commercially confidential information deleted.

  15.6  The future release strategy is now subsumed within the IS/IT strategy and the associated commercial arrangements will build on the existing agreements in place and be aligned with priorities determined by policy changes and the needs of the Jobcentre Plus business as they evolve. Future releases will be able to build on the foundation of the contractual arrangements agreed as part of the deployment of a customer management system that utilises modern technology.

  15.7  Key Risk:

    (i)  The key risk identified is that a substantial proportion of the total cost for the commercial arrangements will have been paid prior to full implementation.

  15.8  Mitigation:

    (i)  It is the intention that the commercial arrangements for the packages to November will measure progress against plan by the project on a weekly basis, that any slippage or non-delivery of agreed products or reaching milestones will be reported to the Project Steering Committee and will result in payments being withheld.

    (ii)  The most important product is for delivery of an operational version of the R2.0 software product to the live estate in November 2004 and introduced incrementally to other contact centres as they go live. Should this not operate as required, the contractor is committed to fixing errors to an acceptable level at their own cost. The contractual negotiation sought and was successful in embedding into the contract explicit references to holding back payments and no charges incurred for fixing the R2.0 product.

16.  Next steps

  16.1  A more detailed assumptions log underpins the costs and savings information contained in this business case. This business case will now be the subject of change control with changes being impacted not only on costs and savings within this case but also impacted on other relevant business cases.

  16.2  The business case will also be updated as we confirm in more detail the benefits to be realised but as yet un-scored following the successful release of R1.0 and R2.0 functionality. These will be measured by the Jobcentre Plus work study team who are in the process of being commissioned to carry out a detailed study of both R1.0 and subsequently R2.0 in a live operational environment.

17.  Sensitivity analyses

  17.1  Annex 5 comprises six different sensitivity analyses, any one of which will not seriously undermine the business case. If, however, several of these were to be combined, the business case would need to be revisited with Treasury colleagues.



2   The costs are outwith this business case and are contained within the IMBC. They are shown for presentational purposes only in terms of the full cost of CMS as requested by HM Treasury. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 8 February 2006