Select Committee on Work and Pensions Minutes of Evidence


Annex 4

CMS RELEASE 3 WORK PROGRAMME

DOCUMENT CONTROL

Key personnel


Title
CMS Release 3 Full Business Case

Author
Elaine McLaughlin
Status
Draft
Document Reference
S004


Summary

  This business case summarises the critical financial considerations relating to Release 3 of the Customer Management System, covering both functional and performance related requirements.

Version history


Version
Date
Summary of changes
Changes marked

0.0a
01/03/05
Draft version following on from re-worked Outlined Business Case
0.0b
14/06/05
Updated following review
0.0c
21/06/05
Updated following review
1.0
24/06/05
Baselined version
1.0a
19/09/05
Rework of Benefits, from Benefits realisation Plan.


Distribution


Name
Area

Lesley PlankCMS Project Manager
Ismail HafejiISD Finance
Coleen DayPDD
Brian KearsleySenior User
Bob HarrisCSD
Gavin MarsdenJobcentre Plus Finance
Sue VentonLPPD
Kerry HartleyHBSD
Key Stakeholder List


References


Doc reference
Document title

v1.0Release 3 Proposal Paper
S002 v1.0Outline Business Case
S001 v0.0cProject Brief
v3.13Project Plan
V2.1Risk Log



ABBREVIATIONS


CMSCustomer Management System
SIPSystem Improvement Programme
FCOFirst Contact Officer
BPBenefit Processing
FAFinancial Assessor
PAPersonal Adviser
LALocal Authority
WATChWorking Age Transformation and Change
HBSDHousing Benefit Strategy Division
PDDProgramme Delivery Division
CSDCore Systems Division
ISDInformation Systems Directorate
BPRPBenefits Processing Replacement Programme

1.  INTRODUCTION

  1.1  This Full Business Case builds on the Outline Business Case from April 2005, in order to secure internal DWP approval from a Gated Review for the implementation of CMS Release 3 and associated performance related releases and to seek continued agreement to the Business Case.

  1.2  Contributions in respect of the assumptions included in this Business Case have been made by Jobcentre Plus Implementation, BPRP Project, and Jobcentre Plus/ISD Finance teams.

  1.3  CMS Release 1.0 was an enabler for the deployment of the Jobcentre Plus service delivery vision and as such did not in itself generate significant savings but rather laid the foundations for future savings, as the system becomes the normal interface between customers and Jobcentre Plus staff. Release 2.0 attracted comparatively marginal costs and generated comparatively significant savings, as detailed in the CMS Full Business Case and Benefits Realisation Paper.

  1.4  Benefits Realisation for CMS Release 2 will be managed by the Business. CMS Release 3 is not associated with Release 2 and has its own costs and savings as detailed in this document. Benefits Realisation for R3 will be managed by LPPD and documented jointly by them and the project. A contribution to the funding for the R3 work-study is incorporated in this Business Case.

  1.5  Customer Management System first went Live in July 2003 as a live trial, with national rollout starting in October that year. In December 2004 Release 2 went live and the project formally closed in April 2005. In the live environment CMS is managed by LSMD, in line with other legacy systems. As at 10 June 2005 there are 24 Contact Centres, with 371 linked offices and approximately 18,000 registered users.

  1.6  CMS is currently supported by a number of Desk Aids, DWP and LA Questionnaires that are completed clerically. Some of these were introduced to accommodate additional business requirements, raised after CMS was developed, and some of the LA requirements were not included in the original scope. Although a number of items on the Desk Aids have been removed as a consequence of the implementation of Release 2 on 13 December 2004, a significant number remain.

  1.7  Following the project closure announcement at a Project Steering Committee Meeting in Autumn 2004, the Field requested that a subsequent release of CMS be considered. A submission was made to the Field Performance Management Group (FPMG) on 15-16 December 2004 to consider whether funding should be made available for a further release of CMS, based on a reduction of the Desk Aids and clerical forms.

  1.8  A workshop was held at the end of November 2004 with the Business and the resulting paper documenting the scope and savings for release 3 proposals, was put to FPMG in December. At that December meeting tentative agreement on Release 3 was given, with a request for a further workshop to firm up the proposed scope.

  1.9  A further workshop with all relevant stakeholders was held at the beginning of January 2005, where the requirements and predicted savings proposed as the scope for Release 3 were confirmed. These were presented to FPMG on 19 January 2005, and authorisation for the funding of CMS Release 3 was given.

  1.10  As several of the improvements in the agreed scope benefit the Local Authorities, Housing Benefit Strategy Division have agreed to provide some funding towards this release.

  1.11  A number of performance improvement activities have been identified and will be developed, tested and implemented in conjunction with the Release 3 programme. These include the refresh of the CMS software stack such that it will remain supported by product vendors until at least September 2007. These conclude the scope of the Release 2 work programme, and as such will be funded from CMS R2.

2.  STRATEGIC CASE

  2.1  The continued rollout of CMS through Jobcentre Plus Implementation enables DWP to make progress towards meeting PSA targets and takes the Department significantly closer to meeting the aims of e-Government.

  2.2  Release 3 of CMS supports the DWP delivery plan for 20-03-06 by contributing towards the following objectives:

    Objective II: promote work as the best form of welfare for people of working age, while protecting the position of those in greatest need.

    Objective V: modernise welfare delivery so as to improve the accessibility, accuracy and value for money of services to customers, including employers.

  2.3  Also supporting the strategic needs of the business by contributing to the DWP Efficiency Programme.

  2.4  Inbound and Outbound call processes will be significantly improved by:

    —    eliminating the need for completion of the DWP and LA Questionnaires;

    —    consequent reduction in the size of Desk Aids; and

    —    the provision of an automated notes facility. This will enable more efficient tracking of customer cases through the CMS process, and in particular will remove the administrative overhead of reliance on form CMS1 by all sites. Also removes the need for users to complete CMS1(LA).

  2.5  This programme of work will implement and build on the performance improvements as identified through System Improvement Programme (SIP).

  2.6  Further details on project objectives, scope and success criteria can be found in the Project Brief, which is derived from the Release 3 Proposals Paper.

  2.7  The majority of Key Stakeholders are represented at the Project Steering Committee Meetings. The PSC membership comprises:


Brian KearsleyChair—Deputy Field Director
Bob HarrisPerformance Issues (ISD)
Lesley PlankProject Manager
Sandra HockleyADDM Northampton
Martin BrownContact Centre
Hilary GovierISM
Brian GarnerIBM
Joe RowbothamEDS
Gavin MarsdenJobcentre Plus Finance
Ismail HafejiFinance (ISD)
Ben AylottHBSD
Coleen DayGovernance
Lynn ClarkeOSM
Sue VentonLPPD
Ian BaileyWATDA
CMS R3 PMOSecretariat


  2.8  Additional key stakeholders are invited to Meetings for Governance Reviews, these include:


Elaine McLaughlin
WATCh/BPRP

Sue Venton (on behalf of Peter Hull)
PBDD
Sue Byers
Jobcentre Plus Implementation


  2.9  Release 3 is scheduled to go live 31 October 2005 following a number of replanning activities. It will be implemented over the go-live weekend to all existing CMS offices. There is a constraint on Release 3 that it has to be delivered by the end of November 2005 in order to realise the benefits identified with the functional release in October 2005.

  2.10  CMS Release 3 work programme has no identified dependencies, however BPRP will have a dependency on CMS and is represented as a key stakeholder.

  2.11  Risks and assumptions have been identified and assigned owners. The Risk Review Board is held every three weeks and the first was held on Thursday 10 February. The risks and assumptions are being managed in accordance with the DWP Risk Management Methodology.

3.  FINANCIAL CASE

  3.1  Following a number of workshops with the Field and suppliers the scope for CMS Release 3 was documented and agreed by all parties. It was emphasised that any additional changes to CMS will need to be fully funded by the proposer, and that the increased scope will only be possible if there was no adverse impact on delivery dates.

  3.2  To support benefits realisation from CMS R2 to R3 it has been agreed that funding for R3 work-study will be included in this Business case up to £20,000.

  3.3  On current estimates, costs up to 2005-06 are proposed at £10.5 million. A more detailed presentation of the resource estimate is provided at Annex 2. In addition to these costs additional functionality changes have been added to the scope of R3 since the Outline Business Case to negate the need for the LA questionnaire. The additional cost of making these changes is being met by the relevant sponsors and as such has a nil cost impact on the funding of £10 million being provided by the field and the £0.5 million provided by HBSD.

  3.4  A small team, based in LSA, is leading on design and implementation activities in addition to providing the full Project Management Support functions. The team comprises one contractor and 33 FTE DWP staff.

  3.5  The key cost drivers are:

    —    IBM IT design and development costs; and

    —    EDS IT design and development costs.

  3.6  Based on the projected savings and improvements, the Field have agreed to provide £10 million towards the work programme. As a number of the proposed changes improve the information gathering process to support claims to Housing Benefit and Council Tax Benefit, Housing Benefit Strategy Division have offered to contribute £500,000 towards the costs of the proposed release, hence the overall total cost of £10.5 million.

  3.7  Assumptions relating to Costs:

    —    There will be no additional CMS End to End Operational Charges for EDS Live running—

    —  R3 introduces some performance enhancements to the ITG service which manages transactions between CMS and PDCS/DCI;

    —  Operational costs are reduced at R3 by the introduction of changes to improve SLA transaction gathering; and

    —    There will be no additional costs or impact for Cúram. The current version of Cúram is version 4, CMS has recently upgraded to version 1.5.2. It is unlikely we will upgrade again before BPRP is introduced and Cúram have agreed to support the version we are using as part of the operational contract until 28 February 2009.

  3.8  Dependencies/Constraints/Risks/Assumptions: The following have been identified as Key Assumptions to the realisation of any benefits associated with CMS Release 3.0.

    —    That R3.0 will work as expected and the existing CMS Release 2 DWP and LA Questionnaires will no longer be required for completion by users.

    —    Users will follow existing guidance/Jobcentre Plus Standard Operating Model when using CMS Release 3.0.

    —    There will be a further 4 main and 6 PTE releases of CMS.

    —    Procedural instructions and SOM guidance will be updated prior to go live in order to maximise potential benefits ie changes to new process are compulsory.

    —    That BPRP/WATCH 2 benefit realisation plan will take into account the CMS savings already claimed, ensuring that there is a dovetail of information.

    —    That financial returns will be adjusted accordingly to prevent any overlay of CMS/BPRP/WATCH 2 claims over time.

  3.9  Benefit realisation for CMS R3 is being managed through LPPD (the Business Sponsor), with support from CMS R3 staff. A contribution to the funding for the work-study team for R3 is incorporated in this Business Case.

  3.10  A full Benefits Realisation Plan was signed off 12 September 2005, prior to the ORR Gate on the 22 September. The calculation of the savings are included in the Annexes to this document, and further detail can be found in the Benefits realisation Plan.

  3.11  The benefits are required to enable the Business to live within current budgetary constraints, rather than generate new efficiency savings.

  3.12  A summary of the R3 scope is as follows:

    On-line Notes facility, removal of both the DWP and LA questionnaires, removal of CMS 1 and CMS 1 (LA), significant reduction in the Desk Aids for both the Outbound Call and FA, removal of the unanswered questions sheet from the customer statement, National Sensitivity Case checks, updating of Risk Profiles, more efficient CMS customer tracing functionality, changes to FLLS User Administration. There are also further enhancements to the design/layout of screens. The removal of the clerical documentation detailed in this paragraph, refers to those products in place at Release 2.

  3.13  The performance improvement aspects of this work programme come under the scope of Release 2 and will be funded as such. However they are being delivered alongside Release 3 to take advantage of economies of scale.

4.  COMMERCIAL CASE

  4.1  There is a five-year Operations contract with EDS in place for CMS effective from 1 March 2004, under the IS/IT Services agreement and SOBA. A change is required to this agreement to include the provision of activities to develop, test, support and deploy the Release 3 Work Programme. The EDS proposal, assumptions book, Cost and Finance model have been agreed and submitted to the Departmental Change Control Authority.

  4.2  A new contract with IBM for R3 development under S-CAT was signed 24 March 2005. This provides commercial cover until end October 2005.

5.  CONCLUSION

  5.1  The CMS Release 3 Work Programme will support PSA targets and the Efficiency Programme and I recommend we are given the authority to continue.



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 8 February 2006