A2 BeanCobham Phase 2 Pepperhill-Cobham Improvement
|
September 2006
|
December 2008
|
Construction
|
A2/A282 Dartford Improvement
|
August 2006
|
May 2008
|
Construction
|
A11 FivewaysThetford Improvement
|
March 2013
|
March 2015
|
Development
|
M6 Carlisle to Guardsmill Extension
|
July 2006
|
December 2008
|
Construction
|
A14 Haughley New StStowmarket Improvement
|
June 2007
|
July 2008
|
Construction
|
A3 Hindhead Improvement
|
January 2007
|
August 2011
|
Construction
|
A38 Dobwalls Bypass
|
November 2006
|
September 2008
|
Construction
|
A595 ParfonLillyhall Improvement
|
January 2007
|
October 2008
|
Construction
|
A1 PeterboroughBlyth Grade Separated Junction
|
September 2006
|
October 2008
|
Construction
|
M62 Junction 6 Improvement
|
April 2007
|
November 2008
|
Construction
|
A46 NewarkWidmerpool Improvement
|
April 2012
|
September 2016
|
Development
|
A30 Bodmin Indian Queens Improvement
|
July 2005
|
July 2007
|
Construction
|
A5117/A550 Deeside Park Junctions Improvement
|
October 2006
|
October 2008
|
Construction
|
A419 Blunsdon Bypass
|
September 2006
|
December 2008
|
Construction
|
A66 Temple Sowerby and Imp at Winderwath
|
February 2006
|
October 2007
|
Construction
|
A1 Dishforth to Leeming (A1 Dishforth to Barton) Improvement
|
March 2008
|
June 2011
|
Development
|
A1 BramhamWetherby (Including Wetherby BP) Bypass
|
April 2007
|
June 2009
|
Construction
|
26 July 2007 : Column 1573W
A1 Leeming to Barton (At Dishforth to Barton) Improvement
|
March 2008
|
June 2009
|
Development
|
A47 Blofield to North Burlingham Dualling
|
April 2011
|
October 2012
|
Development
|
A66 Greta Bridge to Stephen Bank Improvement
|
March 2006
|
July 2007
|
Construction
|
A66 Carkin Moor to Scotch Corner Improvement
|
March 2006
|
July 2007
|
Construction
|
A66 Long Newton Junction improvement
|
February 2007
|
May 2008
|
Construction
|
A69 Haydon Bridge Bypass
|
January 2007
|
October 2008
|
Construction
|
M1 J19/M6 Improvement
|
February 2009
|
February 2012
|
Development
|
A14 EllingtonFen Ditton Improvement
|
January 2010
|
January 2014
|
Options
|
A57/A628 Mottram in Longdendale, Hollingworth and Tintwistle Bypass
|
August 2012
|
December 2015
|
Development
|
A45/A46 Tollbar End Improvement
|
July 2009
|
June 2012
|
Development
|
M1 Junction 6a to 10 Widening
|
March 2006
|
December 2008
|
Construction
|
M1 Junction 10 to 13 Widening
|
December 2008
|
December 2011
|
Development
|
A1/A19/A1068 Seaton Burn Junction Improvement
|
April 2011
|
April 2013
|
Options
|
A19/A184 Testos Grade Separated Junction improvement
|
November 2009
|
May 2011
|
Options
|
A505 Dunstable Northern Bypass (A5 to M1 Link)
|
July 2013
|
February 2015
|
Development
|
A421 Bedford to M1 Junction 13 Improvement
|
October 2008
|
December 2010
|
Development
|
A21 Tonbridge to Pembury Improvement
|
October 2010
|
October 2012
|
Development
|
M40 Junction 15 (Longbridge Roundabout) Improvement
|
March 2008
|
September 2010
|
Development
|
A590 High and Low Newton Bypass
|
August 2006
|
May 2008
|
Construction
|
M20 Junction 10A Improvement
|
April 2010
|
March 2012
|
Options
|
A27 Southerham to Beddingham Improvement
|
October 2006
|
June 2008
|
Construction
|
M1 J21-30 (Phase 1) Widening
|
January 2008
|
March 2011
|
Development
|
M1 J21-30 (Phase 2) Widening
|
October 2010
|
October 2014
|
Options
|
M25 J1b-3 Widening (Section 3)
|
June 2007
|
March 2009
|
Construction
|
M25 J5-7 Widening (Section 2)
|
October 2012
|
September 2014
|
Development
|
M25 J 16-23 Widening (Section 1)
|
January 2009
|
June 2012
|
Development
|
M25 J23-27 Widening (Section 5)
|
October 2012
|
June 2015
|
Development
|
M25 J27-30 Widening (Section 4)
|
January 2010
|
December 2011
|
Development
|
A21 Kippings Cross to Lamberhurst Bypass
|
May 2011
|
April 2013
|
Development
|
A23 Handcross to Warninglid Widening
|
September 2009
|
March 2012
|
Development
|
A453 Widening (M1 J24 to A52 Nottingham)
|
July 2009
|
November 2011
|
Development
|
M25 Junction 28/A12 Brook Street Junction Improvement
|
May 2007
|
February 2008
|
Construction
|
M27 J1 1-J12 Climbing Lanes
|
January 2008
|
October 2008
|
Development
|
M27J3 To J4 Widening
|
January 2008
|
March 2009
|
Development
|
M1 J30 to J31 Widening (SWYMBUS)
|
July 2011
|
June 2014
|
Options
|
26 July 2007 : Column 1574W
M1 J31 to J32 Widening (SWYMBUS)
|
January 2007
|
November 2007
|
Construction
|
M1 J32 to J 34 Widening (SWYMBUS)
|
April 2011
|
September 2013
|
Options
|
M1 J34N to J37 Widening (SWYMBUS)
|
January 2011
|
December 2014
|
Options
|
M1 J37 to J39 Widening (SWYMBUS)
|
October 2012
|
December 2015
|
Options
|
M1 J39 to J42 Widening (SWYMBUS)
|
September 2009
|
July 2013
|
Options
|
M1 J31-32 N/B Collector/ Distributor Widening 1SWYMBUS)
|
July 2014
|
March 2016
|
Options
|
M62 J25 to J27 Widening (SWYMBUS)
|
June 2009
|
June 2014
|
Options
|
M62 J27 to Jet 28 Widening (SWYMBUS)
|
June 2009
|
June 2014
|
Options
|