Select Committee on Constitutional Affairs Committee Minutes of Evidence


Supplementary memorandum submitted by the Ministry of Justice

  When I appeared before your Committee on 9 October, I agreed to write providing additional information on the cost of the National Offender Management Service (NOMS), the C-NOMIS programme, and the number of prison staff who are members of the Prison Officers' Association. Subsequently, your Clerk also asked for further information on the delay in responding to the consultation on `Quashing Convictions', the policy area covered by Clause 26 of the Criminal Justice and Immigration Bill. I also wished to write in order to clarify a point in relation to the funding of new prison places.

QUASHING CONVICTIONS

  On the "Quashing Convictions" consultation, I explained to the Committee on 9 October that the delay post-28 June was caused by my decision on taking up office to reconsider Clause 26 in the light of the comments made in response to the Consultation Paper. Clearly, there would have been little point in publishing a Government response at that stage, because the policy was under review. In principle, it would have been possible to publish a response before I assumed office, but the view was taken that consultees should be able to see the terms of the Bill provision giving effect to the policy (as it then was); and this was not available until very shortly before the Bill was published.

COST OF NOMS

  In relation to the cost of NOMS, David Howarth asked (at question 88 in the transcript) "What assessment has been made of the costs and benefits of the NOMS layer?" NOMS has a total Resource budget for 2007-08 of £4,646 million. This includes £160 million for Administration Costs (including those of HMPS) which represents 3.4% of the total. Administration budgets cover the costs of all central government administration other than the costs of direct frontline service provision or support activities that are directly associated with frontline service delivery. All other expenditure is classified as programme expenditure.

  The National Offender Management Service encompasses HM Prison Service, the National Probation Service, the Youth Justice Board and NOMS centre. The NOMS centre is not an additional layer. It brought together units from the Correctional Services Directorate of the Home Office and teams from HM Prison Service and the National Probation Directorate. This was an amalgamation of "back office functions" and activities that required management to cut across prison and probation, such as public protection; as well as issues such as population management, which cut across both public and private prisons. Subsequently the National Probation Directorate became fully integrated into NOMS.

  NOMS will be will be publishing a Revised Strategic Business Case for the NOMS Reform Programme to update the one previously published. On Commissioning, the Regulatory Impact Assessment for the Offender Management Bill assessed the performance and cost benefits from increasing commissioners' freedoms to buy from the best providers as potentially up to £288 million (on a discounted costs basis) over the next 25 years. Together with the introduction of offender management, the creation of a purchaser provider model is a core enabling measure designed to deliver an additional reduction in crime through a further 5% reduction in re-offending.

C-NOMIS

  I also committed to write in relation to the costs of the C-NOMIS programme. At the time of the original full business case (2005) the project lifetime costs (2005-20) were estimated as £234 million, excluding depreciation and the cost of capital.

  The current reviews suggest that these initial costs were underestimated and understated in the original business case, particularly in relation to:

    —  the lack of contingency to mitigate risks;

    —  the original costs being appropriate for the implementation of a tailored "off the shelf" product rather than the heavily rewritten product that evolved;

    —  the cost estimates not adequately factoring in the costs associated with ongoing changes arising from legislation and any new operational service instructions or policy changes that would be likely to come into place during the project's lifetime. These gave rise to many changes to the requirements leading to significant increase in costs;

    —  the project having a very optimistic timetable for deployment across the Prison and Probation services, with insufficient contingencies for delays; and

    —  the business case basing the projected costs on the assumption that VAT was reclaimable for the project as then described. This assumption was found not to be correct on the basis of advice from HM Revenue and Customs.

  Continuing with the Programme as previously scoped and designed has been shown to be unaffordable. The revised Programme emerging from the rapid review will maintain the commitment to ensure that offender managers have access to the key information from records held within both prisons and probation and will replace unstable, at-risk IT systems across both services. Current estimates for a revised programme are projecting a lifetime cost (before depreciation and cost of capital) in the range of £450-500 million.

PERCENTAGE OF STAFF IN THE POA

  I was also asked to provide details of the number of members of the Prison Officers' Association (POA) across establishments. We do not have, nor are the POA obliged to provide us with, details of the number of staff who are members of the POA. We are therefore unable to calculate the percentage of members in each establishment. The attached tables should, however, provide some useful information. The first indicates the number of staff who took part in the recent industrial action at each establishment. This includes both POA and non-POA members. The second indicates the numbers of staff of different grades who took action and the percentage against the Staff in Post figure for those grades as at the end of July 2007.

FUNDING FOR PRISON BUILDING CAPACITY PROGRAMME

  Finally, I would also like to clarify the answer I gave to question 54. The question asked was "Do you have any more money from the Treasury to deal with this [prison building]?" I replied:

    "This afternoon sufficient money is to be announced to meet all the current plans. We will wait and see what Lord Carter proposes. Had Lord Carter's review been concluded and decisions made on it in advance of the CSR then decisions flowing from that could have been taken into account within the CSR, but that is not the case and so we will have to do it in reverse direction".

  The reply I gave is technically correct, in that we have plans in place to build the original 8,000 prison places that were announced, plus the first 500 of the additional 1,500 places that were announced this summer. Of these, at least 5,000 of the original 8,000 places plus the 500 places are due to be delivered within the current spending review period, and the remaining 3,000 of the original 8,000 places are expected to be delivered in the next CSR.

  The plans, and funding, for the remaining 1,000 places (of the additional 1,500) will not be agreed until after Lord Carter has completed his report.

  This means that of the full 9,500 places that have been announced, and were referred to in Q.53 by the Committee, there is funding for 5,500 within the current CSR; funding to be allocated for 3,000 places in the next CSR—where HM Treasury has acknowledged the amounts; leaving 1,000 places where the plans and funding will be agreed after Lord Carter reports on his current review.

Rt Hon Jack Straw MP

Secretary of State for Justice and Lord Chancellor

November 2007

TABLE SHOWING NUMBER OF STAFF WHO TOOK STRIKE ACTION ON 29 AUGUST 2007 (by establishment)


Establishment
AreaFull Days Half DaysTotal no of Staff
AcklingtonNorth East 1234127
AlbanySouth Central 67370
AshwellEast Midlands 50050
Askham GrangeYorkshire & Humberside 19019
AylesburySouth Central 1091110
BedfordEastern76 076
BelmarshHigh Security 1930193
BirminghamWest Midlands 2761277
BlakenhurstWest Midlands 71475
Blantyre HouseKent & Sussex 000
BlundestonEastern79 180
BrinsfordWest Midlands 1030103
BristolSouth West0 114114
BrixtonLondon78 078
Brockhill/Hewell GrangeWest Midlands 58058
Buckle HallNorth West 471259
BullingdonSouth Central 1260126
Bullwood HallEastern 48048
Camp HillSouth Central 76480
CanterburyKent & Sussex 04646
CardiffWales53 154
CastingtonNorth East 1030103
Channings WoodSouth West 87087
ChelmsfordEastern83 083
ColdingleySouth Central 03535
Cookham Wood/East
  Sutton Park
Kent & Sussex410 41
DartmoorSouth West77 077
DeerboltNorth East102 0102
DorchesterSouth West 60060
DoverKent & Sussex 82028
DownviewSouth Central 51051
Drake HallWest Midlands 49049
DurhamNorth East116 0116
Eastwood ParkSouth West 000
Edmunds HillEastern 64064
ErlestokeSouth West 101
EverthorpeYorkshire & Humberside 97097
ExeterSouth West88 189
FeatherstoneWest Midlands 221941
FelthamLondon156 0156
FordKent & Sussex 101
Foston HallEast Midlands 45045
FranklandHigh Security 2510251
Full SuttonHigh Security 2170217
GarthNorth West141 0141
GartreeEast Midlands 94296
Glen ParvaEast Midlands 53053
GloucesterSouth West 05959
Grendon/Spring HillSouth Central 38038
Guys MarshSouth West 45752
HaslarSouth Central 15015
HaveriggNorth West99 099
High DownSouth Central 1650165
High PointEastern81 081
HindleyNorth West121 0121
Hollesley BayEastern 000
HollowayLondon104 0104
Holme HouseNorth East 1760176
HullYorkshire & Humberside 1760176
HuntercombeSouth Central 67168
KennettNorth West86 086
KingstonSouth Central 000
KirkhamNorth West34 034
KirklevingtonNorth East 30030
Lancaster CastleNorth West 39039
Lancaster FarmsNorth West 1510151
Latchmere HouseLondon 000
LeedsYorkshire & Humberside 2000200
LeicesterEast Midlands 55964
LewesKent & Sussex 61465
LeyhillSouth West0 00
LincolnEast Midlands 1290129
LindholmeYorkshire & Humberside 1431144
LittleheyEastern69 069
LiverpoolNorth West 2440244
Long LartinHigh Security 1130113
Low NewtonNorth East 1050105
MaidstoneKent & Sussex 93093
ManchesterHigh Security 2913294
MoorlandYorkshire & Humberside 1980198
Morton HallEast Midlands 64165
New HallYorkshire & Humberside 1020102
North Sea CampWest Midlands 21324
NorthallertonYorkshire & Humberside 30030
NorwichEastern25 75100
NottinghamEast Midlands 1142116
OnleyEast Midlands98 199
ParkhurstSouth Central 86086
PentonvilleLondon0 161161
PortlandSouth West70 070
Prescoed/UskWales43 043
PrestonNorth West130 0130
RanbyEast Midlands136 0136
ReadingSouth Central 60060
RisleyNorth West153 4157
RochesterKent & Sussex 75075
SendSouth Central25 025
Sheppy ClusterKent & Sussex 2350235
Shepton MallettSouth West 35338
ShrewsburyWest Midlands 192948
StaffordWest Midlands 85085
StockenEast Midlands 44044
Stoke HeathWest Midlands 1360136
StyalNorth West88 088
SudburyEast Midlands 35035
SwanseaWales71 071
Swinfen HallWest Midlands 1080108
The MountEastern82 082
The VerneSouth West 47047
Thorn CrossNorth West 75075
WakefieldHigh Security 26410274
WandsworthLondon146 0146
Warren HillEastern48 1260
WaylandEastern81 081
WealstonYorkshire & Humberside 1110111
WellingboroughEast Midlands 72072
WerringtonWest Midlands 29029
WetherbyYorkshire & Humberside 93093
WhattonEast Midlands 82082
WhitemoorHigh Security 2820282
WinchesterSouth Central 811596
WoodhillHigh Security 1822184
Wormwood ScrubsLondon 1675172
WymottNorth West98 2100
Yorkshire & Humberside TSSYorkshire & Humberside 033



TABLE SHOWING BREAKDOWN OF % OF EMPLOYEES TAKING INDUSTRIAL ACTION BY GRADE

@PARA@@PARA@HMPS Grade  @PARA@Half Days  @PARA@Full Days  @PARA@Total  Staff in Post Figure@PARA@(End July 2007)@PARA@  Percentage of@PARA@staff on strike

OSG  94  1,429  1,523  7,772  20

Prison Officer  450  7,594  8,044  19,761  40

Senior Officer  84  1,307  1,391  3,917  36

Principal Officer  28  283  311  1,217  26

Other  24  202  226

@PARA@@PARA@Note:

Not all staff in post are members of the POA

Other = numerous grades and therefore a staff in post figure and % is not obtainable

@PARA@


 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2008
Prepared 26 November 2008