Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 260 - 279)

  260. British Land strongly supports the Petition of the Corporation, as I have already said, and has of course lodged its own Petition. British Land will be calling three witnesses: Adrian Penfold, Head of Planning and Environment at British Land; Mr Tim Spencer of SDG and Mr Tim Chapman of Ove Arup. Mr Penfold will be giving planning policy evidence to supplement that of Mr Rees. Mr Chapman will be telling you about a viable alternative solution for the capacity at Liverpool Street Station, but it is Mr Spencer of SDG who will be taking the case on capacity even further than I have done at the moment. He will be expanding on the point that even on the Promoter's own figures the solution proposed by him fails very badly. He will wish to go further; he will seek to persuade you, sir, that the total figures have been quite seriously underestimated.

  261. I will take us to the example of the number of 14,500 Crossrail passengers in the morning peak alighting deep underground at Livergate. Mr Spencer will challenge the correctness of that figure and suggest that the number will be far greater, and the split will not be in the proportion 5,300 to Liverpool Street and 9,200 to Moorgate. Therefore, Mr Spencer will be taking on the evidence to be given by Mr Weiss. If you accept Mr Spencer's evidence, putting it crudely, there will be about (these are very rough figures) 20,000 Crossrail passengers alighting at Livergate of whom roughly two-thirds will head for ticket hall B and one-third for Moorgate. Instead of 5,300 Crossrail passengers passing point M into ticket hall B there will be, if Mr Spencer is right, 13,000 odd passengers doing so. Most of those Crossrail passengers will be heading straight for the underground ticket hall B gates. Apart from the huge increase in congestion in the ticket hall, more gates will be required to accommodate them than can, on any possible basis, be squeezed into the existing space.

  262. Sir, that is still not the end of the story. Shall I just add one thing that is not in the text, please? If Mr Spencer is right, the pressure on the gates will not just be from Crossrail passengers; if CLRL have underestimated Crossrail passenger numbers it stands to reason that the numbers of passengers alighting from the Central Line and subsurface lines will have been underestimated too. What is more, if the Livergate split between Moorgate and Liverpool Street Station has been misjudged for Crossrail, it is not clear to me, at any rate, why it would not also have been misjudged for the Metropolitan Line, for there the alighting passenger has a choice just as the Livergate alighting passenger has.

  263. For this, sir, if you would look at your tables, it is Table 11 again on page 5, what you see is, under the heading "Arrival mode", there are identified, amongst others, the subsurface lines and Crossrail. The subsurface lines have in common with Crossrail that they serve both Liverpool Street and Moorgate; the Central Line serves only Liverpool Street, the Northern Line serves only Moorgate, but the subsurface lines and Crossrail serve both Liverpool Street and Moorgate.

  264. So if you look at line 3, the subsurface line figures, you see a projected split there on Crossrail's figures, of 12,600 for Liverpool Street and 8,000 for Moorgate. For reasons that I do not understand, at Crossrail it is suggested the split will be the other way round: 5,300 for Crossrail, 9,200 for Moorgate. My point here is a different point. It is a simple point, really, that if at line 5 the figures for Crossrail should be more passengers alighting—

  265. Kelvin Hopkins: I am sorry to interrupt your flow, at this point. Is there not a possibility that, if Liverpool Street becomes an impossible scrum, passengers to the Liverpool Street catchment area might actually travel to Moorgate and walk back? The split might be a little more shifted towards Moorgate for that reason. Not a good reason, and I accept there might be more numbers, but there will be people who will be deterred from using Liverpool Street and therefore go on to Moorgate and even walk from Crossrail through the tunnel to the Moorgate end rather than the Liverpool Street end.

  266. Mr Laurence: Of course, if you effectively force people—if I have understood your question rightly—to choose another means of exiting the station because the one they want to use is not conveniently available without having to suffer unacceptable congestion, then they do, in that sense, have a choice. You will be hearing from our witnesses why they say that is not the kind of choice that ought to be foisted on passengers.

  267. Sir, you raise your question just at the point that I was saying that my point for present purposes was not to question the split as such at line 3 on the subsurface lines between 12,600 and 8,000 but just to point out that if, in due course, you hear and, subsequently, accept evidence that the overall numbers will be greater than those identified for Crossrail in line 5, then the same reasoning could, on the face of it, appear for the other place where passengers have a choice of where they get off, that is to say passengers on the Metropolitan Line or the Circle Line, the so-called subsurface lines, whose numbers are given at line 3 in Table 11.

  268. I am now able to bring the threads together before Mr Cameron calls our first witness, and I do so in this way: we suggest that there are, in the face of all this, two critical questions for the Committee. The first of them can be framed like this: can this Committee allow the Crossrail project to be taken forward to detailed design and construction on the basis of the Promoter's predictions of passenger demand, bearing in mind that even if these are wholly correct the ticket hall is placed under unacceptable strain from the outset? To that question we invite you to give an unequivocal negative answer.

  269. The second question is this: what is it that this Committee should direct the Promoter to do if it accepts our evidence on passenger demand at Liverpool Street Station? This is difficult because the Promoter has failed to complete essential preliminary work in order to identify the best option for providing a proper eastern ticket hall at Liverpool Street Station. The Corporation and British Land, who support them, consider that there are realistically only two options which are feasible. One of these has already been identified by Ove Arup on behalf of British Land, and I would like to ask you to look briefly at your little clip of diagrams to see what that alternative option involves.

  270. Skip the first three documents which you have already seen, skip Figure 1 and Figure 2 and go to Figure 3. This is an Ove Arup document under the heading: "Crossrail at Liverpool Street Station: suggested alternative layout". Over the page, at Figure 4, you see the same scheme with a section along Eldon Street with Crossrail Scheme dashed. Mr Tim Chapman will obviously be able to explain all this to you in greater detail in due course. What this scheme shows, sir, in very broad outline, is an additional method of exiting Livergate, showing passengers emerging into the corner of Blomfield Street and Eldon Street just near the number 102, Figure 3. You have still got a connecting passageway between the exit from the second of the two escalators but the escalators and the tunnels which I mentioned earlier are differently aligned because, under this scheme, it becomes necessary to reach shallow level sooner than it is necessary to do under the Promoter's scheme.

  271. For present purposes, all I need invite you to do is to note that there is an alternative that Ove Arup has been working hard on for the last three or four months, I think. Let us call that option the British Land Company option (or the BLC option, for short). CLRL themselves have been looking at it in detail and have even made suggestions for its improvement. That is the option Mr Tim Chapman of Ove Arup believes, on the present evidence, stands the best chance of solving the capacity problem at Liverpool Street Station. You will hear from him, however, that he remains entirely open-minded about the possibility of identifying a better option.

  272. There is, in theory, a number of other possible options but, in practice, Ove Arup believe, only one. That other option would have to involve a very substantial enlargement of ticket hall B. There may well prove to be practical constraints which rule it out. Let us call that massively enlarged ticket hall option the METH option. CLRL told us in late December that by early January they hoped to have carried out "an assessment of other options for providing additional ticket hall provision". (I am quoting from a letter from Mr Ben Wilson of CLRL to Mr Chapman, dated 22 December 2005, under cover of which he provided, in draft form, a detailed critique of the Ove Arup option.)

  273. Somewhat to our surprise, we recently learned that work on the assessment of such other options has been halted. Of the alternative options up to now discussed, Mr Chapman believes that only the METH option is a runner. However, as he will tell you, he also thinks it will take a few more months from now for CLRL to reach the point where as much work has been done on the METH option as has been done on the BLC option to enable them to be realistically compared. So it is not a question of getting to the detailed design stage, obviously, on either of these options, but it is a question of doing enough work on the options to be able to compare them realistically. At that stage, when the extra work has been done, a few months from now, your Committee ought to be in a position to make a judgment which option to choose, if necessary after hearing further evidence in the absence of agreement between Petitioner and Promoter, as to which is best.

  274. Sir, there is a terribly important rider to all this. The BLC option, the one Mr Chapman currently thinks will best serve the needs of commuters, will be precluded if the existing Crossrail scheme is implemented. That is because the position and angle of the tunnels and escalators of the existing Crossrail scheme and of the BLC option are different. There are tunnels and escalators for both schemes but they are aligned differently. So if the arguments of the Corporation and British Land on capacity are accepted, it is not an option for the Promoter to say that provision for extra capacity at Liverpool Street can be bolted on to the existing scheme by way of a subsequent scheme. The decision which is the best option must be taken as soon as possible, we would suggest by the end of April at the latest, in conjunction with the Corporation and British Land, and that the Promoter must then be required to set in train the necessary procedures for amending the Bill, providing a supplementary Environmental Statement, etc, if necessary after the Committee has ruled which is the best option.

  275. Sir, I do not want to suggest that we anticipate that there will necessarily be disagreement between the parties on the subject, because if we succeed in persuading you that our capacity case is right there is absolutely no reason to think that the Promoter will not voluntarily get under way again with the assessment of alternative solutions to the problem, which we were told, on his behalf, on 22 December, was then under way and which it was hoped would be completed by early January. If this Committee hears our case on capacity and decides that it is sound and that something has got to be done, we apprehend that Mr Elvin, on behalf of the Promoter, will be saying: "Of course we will carry on looking at alternative options, the massively enlarged ticket hall option in particular, perhaps, but it will take us so long to do it and what we would then hope, in conjunction with the Corporation and British Land, is to reach agreement as to which of the two options is the best option to take forward, if necessary by amending the Bill and producing an Environmental Statement, and so on and so forth".

  276. There are, potentially, lots of issues that will have to be resolved in relation to the choice of the two options. If the massively enlarged ticket hall option, for example, is the one that the Promoter, in the end, thinks is the best there is the position of National Rail and London Underground to consider because, as far as I am aware, they have not been brought into this debate very much at all up to now, and issues of that sort will no doubt have to be looked at. That is why I foreshadow, as a possibility, that if we are successful on the first part of our case it may be that we will end up disagreeing with the Promoter as to which of the two options is the best option. It is not purely a matter of engineering; it is cost and all the rest of it that will have to be considered. If that happens, we may have to ask you, sir, to adjudicate on that, but you certainly cannot adjudicate on it now.

  277. My last two paragraphs, sir. Mr Darling, on 13 December 2005 made another £100 million available for further development of Crossrail. In his statement on that day he indicated that the additional money would allow CLRL, working with the Department and Transport for London, to do the necessary research and planning before Crossrail can enter the next phase of development. I do not mean to be too flippant here; there will be money to pay my learned friends and something left over to identify the best option for "additional ticket hall provision", in the words of Mr Ben Wilson. But that option ought to have been identified long ago. Your Petitioners, of course, appreciate the efforts that have belatedly been made to identify options for a suitable Liverpool Street eastern ticket hall, but urge your Committee on no account to allow that latter issue to be kicked into the long, or any, grass. We respectfully argue that provision for a properly designed Liverpool Street eastern ticket hall must form part of the Bill, and the Bill must be suitably amended to achieve this unless the Promoter, of course, can satisfy us that the best option is to enlarge the ticket hall and that that can be done without amending the Bill, which will obviously be delightful but we remain to be persuaded.

  278. I should add this by way of further emphasis as to why these Petitions have been lodged: your Petitioners want the best possible Crossrail Bill in order to achieve the project's stated objectives. It makes no sense whatever for the main entrance and exit from the Crossrail station which serves the heart of the world's leading international finance and business centre to be created by funnelling passengers into an existing crowded ticket hall. Now is the time to do something about it.

  279. I note that it is 12.45 or thereabouts. I am in your hands. We could get started with Mr Rees; Mr Cameron is here to call him and I know Mr Rees is in the room. Is that what you would like to do?


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007