Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 1640 - 1659)

  1640. Stay with that point and, always making the assumption that we may not in the event be entitled to make, that the Committee will accept our evidence on demand, what is it that needs to be done now rather than be left to another day?
  (Mr Chapman) To the best of my knowledge there are two options that are considered feasible in a station which we have called option one and option six. In both official and unofficial discussions with people working for the Promoters no-one has seriously suggested another option as viable and solving the key issues that need to be addressed. Therefore, the critical thing, I believe, now is that a decision is reached, accepting the point that SDG's figures are shown to be correct, or something in that area, that if people accept that the current ticket hall B is inadequate to cope with the possible increase in demand something needs to be done. Both option one and option six are viable. Option one becomes precluded if the current scheme is continued. Could we go please to figure 1?[18]18 If the Promoters' scheme is built and someone decides to bolt on a ticket hall on Eldon Street corner there are two problems. First of all the point here before going north is too deep so the ticket hall will actually end up right over in Broadgate and discharging people not necessarily where they want to go. The amount that the Eldon Street corner is discharging people where they want to go in the area and the ticket hall that comes in here from this depth is such that it would serve Broadgate and points through Broadgate but would not serve the area quite so well. The second point is that there are mandatory regulations for how far you can have a new passage journey from an escalator run-off. You can tell, if I go back into the point M type of argument here to try and create a passageway going north, that there is going to be conflict with passengers coming up the escalators not quite sure where they want to go so that would be another problem. The Promoters' current scheme precludes option one being built.


  1641. If the Promoters' current scheme is built a decision could not later be made to incorporate option one even if by then the view had been taken that that was far and away the best scheme?
  (Mr Chapman) You would have to come off the passageway under this building in some strange way to come back over here to avoid conflicting at the bottom of the escalators. It is a very Heath Robinson-ish scheme that comes under the buildings and under Broadgate Circus and heads over in that direction. It would not work nearly as well as the current scheme or the proposed option one.

  1642. We have just learned, Mr Chapman, that the Promoters' counsel is intending to give a series of undertakings of which the second is, and I will read it out and maybe a copy could be given to you to read as I am going along. The second proposed undertaking is that the Secretary of State will also require the nominated undertaker to construct the Crossrail works at and around Liverpool Street Station so as not to preclude or render impracticable the expansion of ticket hall capacity at a later date without disruption to the completed Crossrail works. What that means, if I can put it to you in my lay language, is that what the Secretary of State is proposing to do is give an undertaking to look at options other than your option one at some future time should that prove to be desirable and it is implicit in the paragraph two undertaking that the Secretary of State is rejecting at this stage your option one and saying to the Committee that what he will be prepared to do is look at other options in the future if that becomes necessary. Is that something that would be satisfactory to those whom you represent?
  (Mr Chapman) I have spoken about this to British Land quite a lot and to the Corporation and they are not fixated on any particular scheme. They just want to have sufficient capacity at Liverpool Street. If the current scheme is maintained I believe the only option that could be built following from that is option six. I cannot conceive of another option on any information that is available to me apart from option six that would fit in with that. There is one way round that. If they built option one escalator here and the second set of escalators here to come under the Metropolitan Line and then came shallow along here, then they could bolt on a scheme that could be done up here later. If they followed the option one escalator route that achieves the objective and then the ticket hall could be done at a later stage but that would involve massive disruption a second time to this part of the City of London which I understand from the Corporation they would not welcome.

  1643. Is it something you would recommend as an engineer?
  (Mr Chapman) The reason why option one is relatively cheap—and I know it is an awful lot of money—compared to what is happening elsewhere in London for a similar level of capacity is that it is done at the same time. All the street works would be done at the same time, the box is open at the same time, the cut and cover box is put in at the same time. There is extra work involved in all this and it is going to cost more but if you do it at the same time it will be substantially cheaper than doing it later on as well as substantially less disruptive.

  1644. Kelvin Hopkins: Could I just confirm whether other possibilities were considered at the sketch stage but were rejected as being impossible or were not sensible and that option one is really the only one that is sensible in engineering terms?

  1645. Sir Peter Soulsby: Option one and option six. We were told this morning that there were options in between.

  1646. Mr Laurence: Option six is not yet at the stage where it can properly be appraised and it is that which I am now going to ask Mr Chapman to deal with.

  1647. Sir Peter Soulsby: That would be very helpful because he did present it to us and did acknowledge at the time that it was not well worked out but there are other aspects of it that I hope you will explore with him now.

  1648. Mr Laurence: This is particularly one of the matters that you yourself indicated that you wanted to address, sir. You are at paragraph 29. Would you remind yourself of the text and tell the Committee what your conclusions are on this issue?
  (Mr Chapman) Given the need to substantially increase capacity at this station, which I have had a chance of working on with Mr Spencer for several months now, and I have gone through his figures and I have a lot of confidence in them, and given the need to expand the ticket hall to provide the extra flows that Mr Spencer described, that has led to two options to meet the design objectives. The option that we see as having the best advantages overall is the one that reaches the surface at the junction of Eldon Street and Blomfield Street, option one, because it gets people from platform to street as quickly as possible. There is another option which we acknowledge as entirely valid, which is CLRL's preferred option, to massively expand ticket hall B and so-called option six. I would caution slightly that although it appears to be feasible from the preliminary work that we have done, and I have seen no drawings they have produced, we have a couple of options and we believe, as I said before, that we can get the ticket hall to work well. Just to refresh memories can I have figure 6 please?[19]19 As I said before, figure 6 is the Promoters' scheme; it is not our scheme. We have seen no plans for this and so we wanted to make sure that it would work. I do not know if the Promoters have got figures showing what they would do. There are three elements. The first one is expanding the entrance through here and the idea for this was inspired by the Crossrail previous scheme which was abandoned in 2004/2005 because it used some of the pavement space here for the escalator stem. That avoids that problem and, as I said before, we really believe it would work although, as I said before, we have not modelled it to see if it works. The second is that what we achieved was fairly straight lines like you get on the modern Jubilee Line extension station or at the new King's Cross. You achieve 27 gates going across in a way that works well and gives you full run-off on either side around the pillars and the third element of it is increasing vertical separation from the ticket hall here to street where they want to go to, not just pumping them into the already hard-worked Network Rail concourse.


  1649. If the Committee take the view that the demand capacity case that we have put forward is broadly correct and it requires something to be done, you have already said that your view is that it would be best to do it at the beginning as part of the project. How do we get to the point where, in the event that there is a disagreement between the Petitioners and the Promoters as to what is the better of these two solutions, something is done within a reasonable short timescale?
  (Mr Chapman) Option one has been looked at in quite a lot of detail by us and by Mott MacDonald on behalf of the Promoters and I think there is a reasonably strong understanding of the issues and I fully agree with the Promoters that it will cost in the region of £80 million extra so there is extra work required on that to give you slightly more reassurance on that factor of 100 per cent on cost. In terms of option six, there are quite a number of issues which need to be explored.

  1650. Without going into those issues again, because I think you have dealt with them, your evidence is that if there is a will that could be done in how long?
  (Mr Chapman) I believe that with proper resourcing and a proper will two months would be reasonable although I acknowledge that Crossrail are very busy on a number of other points so far. This to me seems a fairly fundamental issue. There are five central area stations and this appears from all the evidence that I have heard to be the most critical one. Solving this station so that people are happy and it works is critical to the scheme.

  1651. I am not asking you something you have written down an answer to and I may not get the answer I want. I do not know if we can rely on the Promoters to co-operate fully with us in trying to examine properly option six if the Committee indicates to them that something has to be done about the capacity problem at Liverpool Street Station. We have to hear from Mr Elvin in due course what exactly the Promoters' attitude will be if we are successful on what I call issue one. Could Ove Arup if need arose and it was provided with proper information, do the work necessary properly to appraise option six absent co-operation from CLRL?
  (Mr Chapman) It could do the work but we would need co-operation from CLRL and the Post Office Railway and there are a lot of issues that the Promoter of the scheme should be in on. I think it would be very difficult to do it in isolation if the Promoter was not willing to co-operate or help. Think that is pretty fundamental. For instance, the Post Office Railway would not necessarily talk to a third party, I would imagine. I would have trouble conceiving of a situation where a third party would have the level of authority to negotiate with Network Rail who own the building above. This area here is actually under a Grade II listed building owned by Network Rail and currently occupied by McDonald's and it is, of course, Post Office Railway shafts, so it would be difficult to find the right solution. That is where the Committee's help and the Promoters' help would be necessary.

  1652. If you look at your last page do you see if there is anything else that you want to say before I sit down?
  (Mr Chapman) I think I have made the point.

  1653. Mr Laurence: In that case, fine.
  (Mr Chapman) Thank you.

  1654. Sir Peter Soulsby: Mr Chapman, before I invite Mr Elvin to cross-examine, can I ask you about this option 6. I think the Committee has understood it is one that is not as well developed as option 1. To ask you what you do know about the obstructions in that area and whether that is part of the exploration you have been able to make so far, particularly what you know about the obstructions that would be necessary to enable the widening of the passage as it joins the existing ticket hall and what you know about the obstructions of the large section which would have to come out on the eastern side?
  (Mr Chapman) Dealing with points first, the flare of point M I believe is reasonably free of obstructions in the macro sense, although every street in London is not completely free of services. When we did the site investigation through the middle of London for Crossrail, with the best will and doing our utmost, we hit a number of buried services because it was incredibly difficult to find streets that were not full of services. There would be a few more service diversions but a lot of them run in a north-south direction anyway. Changing this shape slightly will probably affect a few more but not an awful lot more. In crude terms, that is probably of the order of a million pounds' worth of work, maybe, it might be less than that because you already have a retaining wall coming along here. It is a little bit of extra work required to do it. I know in the Environmental Statement Crossrail are very concerned about reinstating bus access in the north-south way as quickly as possible, and a bit of extra work would not help that. In crude terms, that is probably quite a small amount of money to address in the scheme of things. I understand that the Promoters are considering that issue already as quite an easy way of trying to resolve some of the problems at the top of the escalators.

  1655. Mr Elvin: If it helps the Committee there is no dispute with Mr Chapman on that point.
  (Mr Chapman) That is a relatively quick and cheap win for the scheme overall. The second issue, which releases the large amount of gates here, is being able to build over the Post Office shafts here. Currently there is a ticket hall at the northern end of this red lump. When you come off Liverpool Street concourse, following the line of my pen, if you come here, this is where you buy your tickets. My concern is between this line here and this line here are the foundations of a listed building. I was not sure how much space is there so without full access and permission to go and talk to people, we have been buying tickets there surreptitiously trying to see the ticket hall at the back. We believe it is about three metres distance and then the door at the far side of the ticket hall which leads me to believe this space here under the listed building is probably free. One of my biggest concerns is trying to undermine a listed building. Like I say, from not having proper data but doing our best to collect it in an objective way, we believe this space here can be free. Coming south of the listed building, coming south of the MacDonald's line into Liverpool Street itself, there are these shafts which rise in the pavement and come out under the pavement in front. In extremis, if there is a structure here which cannot be sensibly excluded from the site, one could excavate the street here directly and access them. Possibly the Promoters will have better information on this than we do. Without getting access to that zone, going into proper London Underground facilities, we do not know that.

  1656. Sir Peter Soulsby: I think we realise you have not explored beyond the accessible in that area. We do have, in A23, the gate point we were referred to earlier on. It happens that also shows the outlines of some of the structures you have been referring to, I think?
  (Mr Chapman) That is correct, yes.

  1657. Sir Peter Soulsby: Could you, if you are able, give us an interpretation of those bits of the structure there?
  (Mr Chapman) Okay. Again, using the main screen and my laser, these are shafts which connect down to the Post Office Railway. I will show you in a few seconds how those inter-relate. These structures here I infer are pavement vaults from the listed Network Rail building which is to the north of where MacDonald's is. I would infer, I do not know, that this space here is free air at basement level, ticket hall level. I have walked along here, I know this wall well, I am ashamed to say, rather too well for comfort! This wall is an ordinary solid wall. Passengers have free access—speaking as a passenger with my Oyster card—to walk along this wall as much as they want to. Fortunately it is one of the few bits of the station that is free, there are few people loitering in this area. This is a wall at basement level; this is an old vault wall at basement level and is probably the front of the vaults that were from the building. This space here I suspect might be soil or whatever else, I honestly do not know. I suspect this is free, I expect this is free, I know this is free, this must be free because it previously connected the Post Office shafts to the old station level, this area here I believe is the current LUL facilities. I believe most of this space could be expanded to free up the 27 point gateline. I would hazard one bit of caution which is that all of this work to create the long gateline, there needs to be work for circulation now, there is no point having enough capacity to get people through here, through the gateline and then coming to a very constrained space. It is vitally important we get people to street level and currently I believe there are only two or three escalators to serve the whole of Network Rail coming off the Network Rail concourse to street, one up one down roughly here. I am not sure, I think there are two on the very eastern side of the station, two and two, I am not sure. Currently, if we discharge everybody to this zone, there needs to be a means of getting them to street level.

  1658. Sir Peter Soulsby: Right. Mr Elvin?

  1659. Mr Elvin: Mr Chapman, I am not going to ask you the names of other walls you have befriended in the last few days. I am glad you are on good terms with this wall. You have to laugh sometimes, Mr Chapman! Can I understand this, Mr Chapman, I think there is a good deal of common ground between us, particularly as to aspects of option 6. Your position is quite straight forward, your clients, the petitioners whom you represent, are not wedded to one option or another, what they want is an appropriate increase in capacity?
  (Mr Chapman) Absolutely correct.


18   Committee Ref: A20, Current Crossrail Proposals (SCN-20060126-004). Back

19   Committee Ref: A20, Current Crossrail Layout/Upgrade Existing Ticket Hall (LONDLB-EXH03-008). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007