Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 1740 - 1759)

  1740. For example, an expensive element of doing this might be the escalators up to street level shown half way up ticket hall B on the left.
  (Mr Chapman) Not very. An escalator I believe is about just over £1 million. It is an element of cost. It might be £5 million.

  1741. The escalators are beyond the gateline, are they not?
  (Mr Chapman) Correct.

  1742. The assessments of capacity that SDG have been looking at relate, as Mr Spencer made clear yesterday, to gateline calculations.
  (Mr Chapman) Mr Spencer has made many calculations some of which relate to the gateline. Overall, he is talking about the capacity of the station, not the capacity of the gateline.

  1743. We have seen where the pedroute showed issues. It may or may not be necessary to have escalators there.
  (Mr Chapman) The flows are substantially more, an extra 9,200 people coming off Crossrail wanting to go to street. That is an escalator full purely from Crossrail in the year it opens, not allowing for future growth. Connectivity between ticket hall B and the street is a major element of concern in terms of capacity of the station.

  1744. You disowned giving evidence on capacity right at the beginning because you did not want to go into the figures. I am not going to pick up capacity issues with you. The Committee has had the evidence from SDG on capacity so you will forgive me if I park that question and say it is a matter for submission based on the evidence. The escalators are one element. There may be a number of variations to the remodelling of the structure of the ticket hall on the right hand side, may there not?
  (Mr Chapman) Correct.

  1745. I do not think there is any issue between us. Those are vaults under the street, under the Post Office shafts, and they are empty?
  (Mr Chapman) I do not know if they are empty. I have never seen them.

  1746. If works were to be done to ticket hall B, whenever they were done they would cause disruption at least in part to the passengers coming through the ticket hall.
  (Mr Chapman) That solution does not require a lot of disruption because a lot of the work can be done behind walls that are currently walls.

  1747. The only effect Crossrail at the moment has on ticket hall B is when the breakthrough of the wall comes at point M.
  (Mr Chapman) The effect of Crossrail is to funnel—

  1748. I am talking about construction works. The only physical works that impinge on ticket hall B at the moment are coming through at point M.
  (Mr Chapman) Yes. Crossrail powers will stop at point M because it is not part of the power sought for Crossrail.

  1749. I am looking at the question about whether future works are necessarily going to be more expensive and more disruptive if they are done at the same time or in the future. Works to option six are effectively going to be the same whether or not they are done as part of the Crossrail works or whether they are reserved to see whether they are needed at some stage in the future. The disruption will be the same whether they are done with Crossrail or later. They can be done, as you suggest, behind walls. There is no reason why the cost should be any different. They are independent works of Crossrail.
  (Mr Chapman) Not quite. I understand where you are coming from but in terms of the residents of the area two major phases of construction in the area they would view as two major phases of disruption in the area.

  1750. I suggest the extent of disruption is not going to be major in that sense. We are dealing with works to the ticket hall possibly, though not necessarily creating a separate entrance up to street level. That does not need to be included. The extent of disruption does not have to be that great.
  (Mr Chapman) At the moment, without knowing what is proposed, how it would be done and what the issues are, I suspect you might be right but I do not know. There is a lot of work to be done over the Post Office shafts.

Re-examined by Mr Laurence

  1751. Mr Laurence: You have said several times that you have not had the benefit of seeing any plans that enable you to comment comprehensively on option six.

  (Mr Chapman) That is correct. We wanted to show something of how we felt it would work, just to make sure it would work, and help the Committee, but it is our guess of what is required.

  1752. If the Promoters, no doubt reluctantly, made the assumption that the kind of demand which Mr Spencer has spoken about and which has motivated you in preparing option one was something that they should have underlying the preparation of plans for option six, how long would it take them to prepare some plans that would enable you to comment more comprehensively than you have been able to do?
  (Mr Chapman) It depends how much information is already in their possession. If they have already started talking to the Post Office to get proper, accurate plans of the shafts, it may be relatively rapid.

  1753. If they have not? Still just a matter of weeks, presumably?
  (Mr Chapman) I have done buildings over the Post Office railway before and they are well equipped normally to provide information so I would hope the information could be gained quite quickly.

  1754. If necessary, through the Committee, a steer was given to the Promoters to get on with the preparation of plans that gave some flesh to the option six idea, is that something which would enable you to prepare a more detailed appraisal of option six than you have so far been able to do?
  (Mr Chapman) Absolutely, yes.

  1755. As a result of Mr Elvin's cross-examination this afternoon, it seemed to me he was trying to persuade you that on reflection you should abandon option one because of the disruption in Eldon Street and so on. On reflection, are you prepared to abandon option one at this stage?
  (Mr Chapman) Mr Elvin very perceptively identified some of the major issues but they are issues that we have been through, understand and have discussed with CLRL's consultants, so I did not learn anything new.

  1756. In so far as the Secretary of State's proposed undertaking, ex hypothesi, involves the abandonment now of option one, what comment have you on the proposed undertaking?
  (Mr Chapman) Personally, I would only abandon option one or even Mr Elvin's option two if I knew that option six worked, if option six is proven to work and to provide the capacity that might happen. There are advantages to option one, I fully acknowledge, but I would only abandon an option that I know will work if I knew the other option would work.

  1757. Sir, are you going to say something about when we are coming back?

  1758. Sir Peter Soulsby: Yes, at 10 on Tuesday, with the expectation that we will be hearing your closing submissions.

  1759. Mr Laurence: On this case?


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007