Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 2600 - 2619)

  2600. Thank you. Just so that we can have this clear before we move on to consider your evidence, can you briefly summarise the Promoter's position as to the demolition and construction works at number 38?

   (Mr Morton) Surprisingly, the Promoters have only looked at one situation, which is the retention of the façade of the building. I am quite amazed at that because certainly if a project like this was put before us, as a company of engineers, we would look at all aspects of it (a) to provide the best economic solution to the solution that had arisen and (b) to properly advise our clients as to the alternatives that might be available to them. The report that I have draws a conclusion that the only way of dealing with the site is the demolition of the building because they put up an enormous scaffold around the building itself and then say, "We have not got enough room to construct the shaft because we have not got anywhere to put things on the site, this enormous scaffold that is retaining the façade is in the way".

  2601. I know that you have considered the Promoter's position. Can you please say what your response is in general terms to the Promoter's position?

   (Mr Morton) What I have tried to do is to look at this as a project that came to us. The way I see it at the moment as far as the Promoters are concerned is they have not been properly advised as to the possibilities for the use of this site. I think it should be further investigated down the path I have taken which is to put forward three alternative proposals which can be looked at individually and assessed and decisions made.

  2602. Thank you. We are up to about paragraph 13 in your note. Can I ask you to outline what the position is as far as those three options you mentioned are concerned?[17]

  (Mr Morton) The first option would avoid the need for any alteration to number 38 at all. The second and third would enable the building to be left substantially intact. All would involve only very minor changes to the Promoter's proposals being based largely upon changes to the construction methods. None of the methods I propose are unusual or would be unduly onerous or expensive. They are intelligent but straightforward solutions to enable Crossrail to be built as planned without demolishing 38 Charterhouse Street. They would provide sufficient working space on the Fox and Knot Street site and not require the works to be carried out other than in a wholly safe manner.

  2603. I am going to ask you to explain what is involved in the first option that you put forward and in particular in relation to the construction techniques involved.

   (Mr Morton) I think probably rather than read this I ought to explain to you and perhaps I can get you to visually understand what is involved. We are digging a big round hole and in digging that hole as you dig it, you have to hold its sides in. There is a system of doing this by putting piles around the periphery of the hole. Initially you put pairs of piles—I am sorry, are you looking for something?

  2604. Mr Binley: Yes. I would find it easier if I saw the options in front of me, quite frankly. I am sorry, Chairman, but I am finding this slightly difficult.

  2605. Mr Honey: There is one drawing which will help illustrate and that is at tab 7. Before describing what is shown here, can you just describe what the Promoter is promoting by way of construction techniques?

   (Mr Morton) There are several ways of constructing a big hole like this. The Promoter is proposing to construct this by effectively digging a ring around the area where they are going to need to construct the walls, in other words a circular ring, which is over width about a metre wider than the actual hole itself. They place concrete blocks at that sort of depth in segments all around the outside. They possibly put another row of these segment blocks around on top of those and, having got to that position, they put concrete around the periphery so it gives the wall at the top some stability and excavate underneath these segments to put further blocks underneath and go down that way. So you are building underneath what you have already constructed the whole time. The risks associated with that are that you loosen the earth behind the wall and thus you have to carry out grouting which is the pouring in of a cement-based mixture to solidify the ground around the outside of the hole. This has a risk of settlement on adjoining building associated with it because the ground almost certainly will consolidate during this period, but of course properly done the risks are quite small. They go on down with this system until they get the 22 metres down, which is about 75 feet. At the bottom of that they spray concrete on to the further digging that is taking place to hold the earth up beneath this secant pile system. They rely on that as the structural means of retaining the earth and they then construct from that the entrances to the adits that take the people down on to the railway track.

  2606. You have an alternative proposal which is illustrated on the screen at the moment.

   (Mr Morton) Yes.

  2607. Please can you explain what is involved in your alternative proposal?

   (Mr Morton) If you look at the plan you will see there are a series of piles, a series of tubes that are shown around the periphery, which is what is called a secant pile system. Initially you pile every second pile, you leave a gap between them. You then come along and put another pile down between them and on the inside face you build a block wall to consolidate the whole structure. You drive those piles down to the requirement that you have and excavate from inside the waste materials that you do not want any more. That would probably be done by having a small digger dropped into the hole doing the excavation and removing the earth. Again, when you get to the bottom you will have a different form of construction which would almost certainly be a sprayed concrete system.

  2608. Comparing the need for working space on the site between the two methods, which would be better?

   (Mr Morton) The secant pile system needs a rather wider area for its construction overall because you have the block work lining it. I am not aware of the thickness of the segment system but there is a difference. Marginally the shaft would be of somewhat larger diameter.

  2609. How about working space needed on the site in terms of the storage of materials and so on?

   (Mr Morton) In due course I would have to refer to the proposals to retain the façade because that significantly affects the construction overall related to storage on the site. In my view this system would not require any more storage space than the segment system. With the segment system it is suggested storage space on site for the segments that are going to be immediately used and in the case of the piling system you would not have those segments but you would have tubes and reinforcement on the site ready to go down into the various piles.

  2610. To your knowledge, is this system for building shafts related to rail works being used elsewhere?

   (Mr Morton) Yes indeed. Scanmoor tell me they are working on such a shaft and putting forward proposals in Shepherd's Bush.

  2611. Having regard to the options you are putting forward in order to avoid the complete demolition of this building, what is your first option?

   (Mr Morton) The first option is to move the shaft some two metres. That is something of a guess, but something of that order in the direction of Fox and Knot Street. This means that it impinges on Fox and Knot Street rather more. One of the arguments put up against this is possible services in Fox and Knot Street but the comparatively quick investigation that Scanmoor did suggests that there is a sewerage line on the far side of Fox and Knot Street, although there does not seem to be anything of significance on our site side.

  2612. Are there any barriers to moving the shaft some little distance towards Fox and Knot Street?

   (Mr Morton) Not that I am aware of.

  2613. Will it have any effect on any other buildings in terms of increasing the need for acquisition?

   (Mr Morton) No, it certainly will not.

  2614. I understand that using this system there is also a second option. Can you please explain what that is?

   (Mr Morton) The second option is as shown on the drawing. That uses piles flattening out one side of the ring in the way that is shown on the drawing. If that is done, it is my opinion that we could get away without even taking down our enclosing wall to the building at 38.

  2615. I understand that there is a third option where, even if you accept absolutely everything that the Promoter is proposing, you do not believe it is necessary to demolish the building. Can you please explain what would be involved in those circumstances?

   (Mr Morton) In working on historic buildings, one is always looking for a solution. You are prepared to go to any lengths to design a solution to save that building. What I have done here is say to myself, "Okay, the chips are down. We cannot do anything else. We have to accept some loss of this building. What can we do about that?" I looked at the photographs.

  2616. The photographs are to be found in your tab six. Is it the last photograph in there?

   (Mr Morton) Yes.

  2617. Please explain by reference to that photograph.

   (Mr Morton) If you look at that photograph, you will see at first floor level there are two windows. Alongside those windows in the retained part of the building there is a brick pier. You can simply remove that section of the building to the right of that pier. It is a structural line across the building. It has beams across the floor at the upper levels. You could take that section out and rebuild it afterwards. The only difficulties, if they are difficulties, are the slight complications of replicating the cornice and pilasters on the front elevation. Exactly the same situation applies on the elevation on the other street. If you simply take that off, it would give you an extra three metres of building site area to work in. It seems to me to be a much better alternative to total demolition of the whole building.

  2618. Has Crossrail, the Promoter here, considered anything similar to that at all?

   (Mr Morton) They have indeed, in their report.

  2619. The drawing is tab five, the last drawing. Can you explain first what this drawing is and where it comes from?

   (Mr Morton) This is related not to trying to save the whole building but to restraining the two long walls at their ends so that work could be carried out to build the shaft without taking the ends of those walls down. The odd thing is that what has been proposed—please understand this is totally related to facade retention—is only taking out the wall in the ground floor. Then they comment on that that it is not really practical because you still have the building above you and you cannot get at it. They have looked in a sort of way at one of these proposals but then dismissed it.


17   Committee Ref: A35, Alternative construction plans for Fox and Knott Street (SCN-20060207-015 to 021). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007