Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 2620 - 2639)

  2620. Have they considered what you are putting forward as this third option at all?

   (Mr Morton) No, they have not.

  2621. There is evidence in relation to the facade retention you mentioned earlier and the need for buttressing mentioned by the Promoter when you were to retain the façade. Can you please explain whether there would be any need for external buttressing in any of your three options?

   (Mr Morton) The building as it stands is restrained by the floors of the building. It stands there perfectly foursquare. It is a solid structure. It is not going to go anywhere. If you take out the end wall as I have suggested, removing the three metres, it will probably be necessary to put some ties across to restrain the open ends of those walls but, apart from that, no other work would be required to the building to restrain it.

  2622. What if any use would the retained, existing building be capable of on the work site there?

   (Mr Morton) It could be used for the facilities one needs on site, the health and safety situation and the contractors' huts inside the building. It is interesting that Crossrail's engineer suggests, in talking about the retention of the facades, that the interior of the building has no value for their working abilities on the site.

  2623. As far as your options are concerned, what if any of the problems that you would face with facade retention would be encountered with your three options?

   (Mr Morton) The problems simply are not there. You have the building; it is a solid structure. You have considerable advantages because you do not have the loss of the large amount of the overall contractual site that occurs because of the facade retention scaffold. Could I refer to tab five?

  2624. It is the second page at 5B. Can you explain what this drawing is and what it shows?

   (Mr Morton) This is the construction site. It is based around the facade retention proposals. You can see to the left hand side of the site and to the bottom the facade retention areas that are necessary to restrain the walls. This proposal shows a situation where they are going to put a steel frame across these areas with access underneath it for lorries or storage materials. You can see it takes up an enormous space on the site. If you do not need those facade retention structures, you gain a great deal of space all round. You can see on that plan as well the area where segments of the precast concrete would be stored at the top of the drawing and then various fuel tanks, generators et cetera that are obviously a necessary part of this form of construction. I see it may be put forward that access around the site is going to be difficult but of course it will be quite possible to put these items that need to be stored on a scaffold or steel framework at first floor level, as you see on many construction sites. You could end up with a fairly clear area of ground on which you could work.

  2625. Can you identify on this plan for the Committee please the location of the tower crane that is proposed?

   (Mr Morton) Yes. The tower crane is shown on that drawing in the centre of the retained building. It is marked in blue.

  2626. At tab seven we can see your proposals which include organisation of the site. Can you please talk us through this drawing in terms of organisation and what working space would be available?

   (Mr Morton) You can see quite clearly on Charterhouse Street the space that is now available, where you do not have the retention proposals. You do not need to bring the lorries into the site at the end of that sloping area shown to the right. You can bring them in half-way down that boundary so you would gain space behind the lorries in open ground for storage of segments for other site huts or materials that you need to bring to site. You also gain space on the bottom of the drawing where you can see again there is the width of the pavement for further storage inside the site boundaries. I discussed with Scanmoor the arrangements for the crane. I cannot really repeat their comments but the thought was that it was crazy to put a crane in the middle of a building that had a steel framework all round it and anything you had to lift you had to lift over the top of that building. It would be much better and much more convenient to put the crane in the sort of position that is shown on this plan.

  2627. As the borough understands it, the Promoter has concerns about limited working space there may be on site and health and safety issues which could arise from that. Could you please explain what, under your three proposals, would be available in broad terms for working space and whether it would be sufficient to give rise to any significant risks?

   (Mr Morton) You can see from this plan that you have a bare site which has a big hole at one end of it. You have the remains of that site, apart from the floor plan of that building, which can have the ancillary facilities inside it. Believe me, site huts are quite a problem. Toilet facilities and whatever could be put inside the building and it could be used as an adequate site office during the construction period, altogether a much better arrangement. You significantly reduce the health and safety risk associated with the construction. You are not endangering the building. You do not have the danger of the facades falling down. Okay, you require some protective measures and a risk assessment needs to be carried out so that the risks can be avoided. Any project is possible as long as a proper risk assessment is carried out. The risk assessment indicates the sort of risks that are associated with the construction and then you put forward proposals to avoid those risks. That is the normal way of doing it. I believe that the risks associated with each of the three proposals I have put forward are far fewer than they would be if we try and retain the facades, although it is perfectly possible to retain the facades.

  2628. Having regard to what the Promoter proposed to do, which is to level the site essentially and knock everything down, taking into account all relevant factors, do you think the risks proposed by your options are acceptable or not?

   (Mr Morton) Absolutely acceptable.

  2629. In respect of the time that the proposals would take to realise, what effect on the time taken for construction would your proposed options have?

   (Mr Morton) There would be a significant reduction in the time required for carrying out this construction.

  2630. That is as against what?

   (Mr Morton) As against the proposals for erecting a massive structure to retain our building before you can carry out any work or construct the shaft.

  2631. As against what the Promoter is proposing to do, which is not facade retention, would this significantly add to the period taken for construction or not?

   (Mr Morton) Not at all. The building is there; you do not have to demolish it. With the health and safety risks in demolition nowadays, there is a significant time associated with taking it down and getting that material off the site.

  2632. Could you say briefly what, in your opinion, the likely cost implications are of your proposals both as against complete demolition and some form of facade retention?

   (Mr Morton) In the report by the engineers for Crossrail, they have a list of costs associated with their proposals. Most of those costs simply disappear. There must be an enormous cost saving in adopting these proposals and a consequent time saving as well.

  2633. As against what the Promoter is proposing to do in terms of demolishing the building, what are the cost implications of your proposal, in broad terms?

   (Mr Morton) There is a significant cost attached to demolishing a building with the health and safety requirements that are now in place. It is a dangerous business and will require time and care to demolish the building.

  2634. Overall, are the reasons the Promoter puts forward for wishing to demolish the building in terms of time, money and safety concerns at all when compared to your options?

   (Mr Morton) No, clearly not.

  2635. What is your overall professional opinion in advising this Committee as to what ought to happen on this site?

   (Mr Morton) I believe that Crossrail's engineers have not looked properly at the proposal to build this shaft on this site. There are clearly other options. It seemed to me when I received the original information on this project just 10 days ago that somebody had fairly arbitrarily drawn a ring on that site, keeping it off Fox and Knot Street and said, "That is the only place it can be." I do not believe that this is a well thought out position for the shaft. I do not believe that it has been properly thought out.

  2636. Is there any other evidence that you want to give to the Committee today?
  (Mr Morton) No.


Cross-examined by Ms Lieven

  2637. When were you instructed by Islington?

  (Mr Morton) Two weeks ago.

  2638. We have not seen any report from you or any plans from you at all until this morning at 9.30, have we?

  (Mr Morton) I am sorry; that is not my involvement. As far as I am concerned, a meeting was held with Crossrail engineers where we did have a document but I understand that was not sent.

  2639. It is not a criticism of you, Mr Morton. It is just to try and explain where I am at now. We had no written document from you or plan of your proposals until 9.30 this morning. Is that your understanding of the position as well as mine?

   (Mr Morton) That may be so but I did not have anything from Crossrail with regard to the retention scheme until Friday morning last week, which has meant I have had to work over the weekend to put this all back together again.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007