Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 2700 - 2719)

  2700. So that it would be self-supporting, as it were, self-propped. The difficulty with that is that you recall at the beginning of the cross-examination that it is necessary to construct the chamber, the adits and the passage, at underground level, to go down to the Crossrail platforms, from this shaft, is it not?

   (Mr Morton) Yes.

  2701. So if you prop by constructing the floors as you go down you are then making it significantly more difficult to excavate and construct the underground parts of the station, are you not?

   (Mr Morton) I think what you would probably do is you would leave the final staircase out until you needed it.

  2702. I assume, Mr Morton, you are like any engineer, in that ultimately you can always find a solution to something. If you do put the floors in and leave the staircase out you are making that underground construction a great deal more difficult, are you not, because you have to have your digger down at the bottom, getting the stuff into the middle and then get it up a relatively small central hatchway?

   (Mr Morton) But if you take your clients' proposals you have to erect those floors and that staircase within that shaft at some time. Presumably that would be done, I imagine, as you go down—I do not know if it will be or not. But you still have the same thing to do in a different way.

  2703. I think, Mr Morton, you may have missed the point, with respect. You obviously have to put in the floors and the stairs otherwise it is not much use as an emergency shaft, but under our proposal you do that at the end when you had constructed the adits downstairs. Under your proposal, in order to maintain structural stability, you would have to put those in as you were constructing the shaft.

   (Mr Morton) As I have said, you would leave the central staircase up.

  2704. Just to come back to the point, that would involve a difficult—not impossible—operation for excavating underground and then getting out the spoil.

   (Mr Morton) I do not think that is again necessarily so. This is an engineering matter and what you are doing is you have to put the floors in anyway and if you do not put any floors in as you go down you have to come back up and put in those floors. You have exactly the same situation; you have a great deal of work to do to achieve that.

  2705. I will try one last time. It is not the same situation because under our proposal you do all the excavation and the construction from the whole width of the shaft. Under your proposal you put the full work of the floors in in order to brace the shaft.

   (Mr Morton) Yes.

  2706. Thank you. Can we just look at what plant and material you need for all three options, and can we have up the plan that shows the construction plant that you need? Can we go through the elements on this that one would need, first of all for constructing by either method? This is our construction proposal with number 38 removed. There is no issue that you would need a crane on the site, is there? That should be document 37.

   (Mr Morton) Before you go on, could I go back one step to a question you just asked me about the use of secant piles and the difficulties of doing that. I see in the Mott MacDonald report that with the rectangular proposal, which they obviously thought was a possibility, they actually have secant piles shown.

  2707. Mr Morton, have you read the Mott MacDonald report?

   (Mr Morton) Yes, I have.

  2708. Do you remember it says, perfectly clearly at 6.22, "Construction of a rectangular pile shaft is not considered feasible for safety"?

   (Mr Morton) It is constructionally feasible.

  2709. Are you proposing a rectangular pile shaft?

   (Mr Morton) No, but I am proposing to have a secant pile shaft, and they have shown it on their drawings.

  2710. Can we revert back to the plant on this site, and what I hope you now have is P37. There is no dispute that there has to be a crane on the site.

   (Mr Morton) There does.

  2711. Equally, there has to be space for a delivery lorry to bring stuff on.

   (Mr Morton) Yes.

  2712. There has to be space to get the spoil off the site.

   (Mr Morton) Unless you put it straight into the lorries.

  2713. You have to get it off the site somehow or other.

   (Mr Morton) Yes.

  2714. You can put it straight into a hopper, as is shown here on the red hatching above the lorry.

   (Mr Morton) Certainly you could but it is certainly not unusual to load it directly onto the lorry.

  2715. There would not be in any benefit in space terms in loading it straight into the lorry, would there, because the hopper is above the lorry.

   (Mr Morton) All right.

  2716. I am not sure why it is necessary to argue about that. So you have to have that space. Then it is necessary, moving around the site, just taking the stuff for the construction of the shaft, to have space for the lorry that is taking the spoil, but you also need space for a lorry that is bringing in deliveries, do you not?

   (Mr Morton) Yes, you do.

  2717. You then need to have some space, red hatched here, for what is called materials lay down. You have to have some space to put things that you are going to need in the construction of the shaft.

   (Mr Morton) Yes.

  2718. Green here, you have to have some space for welfare and stores, do you not? We are trying to make the best use of the site so we have welfare above and stores below?

   (Mr Morton) I am suggesting both can go into the building if the building is left on site.

  2719. First of all, you have to find somewhere on a site for those two uses, do you not?

   (Mr Morton) Yes.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007