Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 2800 - 2819)

  2800. What is shown as the boundary on this drawing for the worksite layout on Fox and Knot Street?

   (Mr Morton) It certainly appears that my technician has drawn it on our drawing, which is tab seven, correctly.

  2801. Did he produce this drawing in 5A?

   (Mr Morton) That was produced by Crossrail's engineers presumably.

  2802. So now that you have been able to compare the two, is there any need to change your plan at tab seven at all?

   (Mr Morton) No, there is not.

  2803. You were asked a series of questions about site constraints and maybe if we keep the drawing at 5A open, can you say please what, if any, clash there would be between your options and the site constraints identified by Crossrail to you in cross-examination?

   (Mr Morton) If you look at plan 5A, clearly the storage of the rings and the—

  2804. Forgive me: I put the question wrongly. I am going to go on to materials in a moment but you were asked first about the site constraints like location of buildings, and the location of the emergency access I think arose at this point. Having regard to those things what, if any, clash is there between those site constraints and your options?

   (Mr Morton) There is none at all as far as I can see.

  2805. Just after lunch you were asked a number of questions about piling and what that would involve. Can you say practically what, if any, real hurdles are presented by a secant pile approach here?

   (Mr Morton) I do not think there are any significant problems other than the fact that the thickness of the shaft wall is going to be greater. You have all the engineering problems at the base of the shaft that are the same as for the segment system. You have got to link that in with the exits at the base. You have got to construct your floors. It is a different way of doing it but I do not see any particularly onerous problems associated with it.

  2806. Comparing the two in terms of the Promoter's proposals, segment against secant pile approach, is your approach significantly more expensive or time-consuming so as to make this other than an option?

   (Mr Morton) I do not believe it is any more expensive but also you have to look at the fact that it is accepted that the segment system can generate settlement of adjoining buildings and thus it can generate settlement of the building we are trying to hold up. I accept that there is within the Crossrail general documents provision for measuring settlement and when the settlement gets to more than 10 millimetres warning bells start to ring, but if you can avoid that situation by using the secant pile system it seems logical to do it.

  2807. You were asked some questions about arranging the site and a drawing was produced which I think has the reference P38. It is the second one of the two that were stapled together. Do you have that?

   (Mr Morton) Yes, I do.

  2808. You told us in your evidence in chief that you would be able to use the building if it was retained in storage. Looking at this drawing, what elements could be transferred to within the building to free up further space?

   (Mr Morton) Certainly office facilities could be accommodated within the building. Toilet facilities could be accommodated within the building and generally any other accommodation that is required on the site for people to use.

  2809. What, if any, space could be used for storage of certain items?

   (Mr Morton) It would be possible to use the ground floor internally for storing items but, of course, unless you are going to take the gable wall out there is not going to be easy access to that ground floor.

  2810. Keeping that plan open can I ask you to go back to the one at 5A and compare the areas of the site proposed, particularly at the apex end between what we have at 5A and what has just been put in today? What extra space would be available if the hoardings were as shown on the proper Crossrail plan?

   (Mr Morton) What comes out of that question is that you look at the plan given to us today, which showed the green storage area at first floor, and you look at the storage shown on 5A and you see that there is significantly more on the plan given to us today than there was on the drawing 5A which was produced some while back.

  2811. Looking at the hoarding line, which I think is shown in red on both drawings, particularly at the apex, can you see any difference between the two?

   (Mr Morton) The line is different, is it not? It is a diagonal line which on one drawing is a fairly flat diagonal and on the other drawing is much more acute.

  2812. So, having regard to the position of the building, for example, what extra space would be available if the hoarding was put where it was originally proposed on 5A?

   (Mr Morton) There is rather more space to be able to think of putting the crane in that corner.

  2813. Do you think you would be able to accommodate the crane on the site if it were to be as originally proposed at 5A?

   (Mr Morton) I do indeed. Indeed, Scanmoor felt that that was a very sensible place to put the crane. They absolutely dismissed the idea of putting it in the position shown on drawing 5A.

  2814. You were asked about option three and what was involved in taking down the end three metres. Can you please compare the difference between total demolition of the building and taking down the three metres in terms of the risks and the time and the cost involved?

   (Mr Morton) It is a comparatively easy matter to scaffold up that small section of the building and literally having it taken down by hand. One would be much happier doing that. There is the likelihood of, if you like, a hammer demolition of the whole building which is undoubtedly the way the way it would go if you were going to demolish the whole of the structure.

  2815. So if you were simply trying to allocate enough space to do the works which would you recommend: taking down just the end of the building or knocking the whole thing down?

   (Mr Morton) Oh, taking down the end without a doubt.

  2816. There is one question I wanted to ask for the sake of clarification. You were asked a question about your option one and the need for underpinning number 38. Can you please clarify whether any underpinning would be required to number 38 if you were using secant piling in option one?

   (Mr Morton) There would not be.

  2817. The Committee asked you a question in relation to the length of the building that could be taken down in option three, three metres, and what that would leave of the building. Could you say roughly perhaps, if we have a look at the drawing on the screen at the moment, what proportion of the length of the building would be left intact compared with what would be taken down?

   (Mr Morton) It must be 80 per cent, 85 per cent perhaps that would be retained.

  2818. Thank you very much. Sir, I have no further questions for Mr Morton so that ends our evidence in relation to this first of the two matters that we have. I understand the Promoter proposes to call no evidence in relation to this issue. There was a debate earlier about whether a note should go in. What I would like to propose the Committee to consider is that we go on to close this issue today while it is fresh in our minds. Sir, you said you would consider whether a note would be allowed in. What I would propose is that if a note is allowed in and it raises any issues we can deal with those later by submissions but the best thing is simply to press on, have closings today while it is fresh and then have this issue resolved. Sir, that is what I would propose.

  2819. Ms Lieven: Sir, can I say I would be most unhappy about closing this issue today. These are very technical issues and we only received Mr Morton's plan after 9.30 this morning and that was the first time he had put options to us. I have done my best to put the problems to him in cross-examination but surely the position that the Committee is in is that it has to weigh what the problems and the pros and cons of this are but it really cannot do that until it has seen a note as to our view of the options. It is unrealistic to suggest that I in cross-examination can genuinely put all the engineering problems with the proper weight. As you yourself said, although it could have been Sir Peter, when chairing an earlier session, it is not my function to give evidence, it is my function to ask questions and the Committee needs to see the evidence in the form of a note. I would suggest given that Mr Honey is returning in the very near future, at least I assume it will be in the very near future as we are moving down the line, to deal with the rest of Islington's case, the best way forward is for Crossrail to put in a note and I can undertake to do that by tomorrow morning so that you have got our position on the engineering difficulties and when Islington come back we can close on the entirety of Islington's petition in one go. After all, the Committee has indicated it is not going to make decisions on these matters until right at the end of the process, so the fact that it is not fresh in your mind, as my learned friend puts it, really is not here nor there, what is important is that on the record is the clearest possible exposition of both sides' case so that when the Committee does come at the end of the day, whenever that may be, to appraise all these petitions it has got the full statements from both sides.

   (Mr Morton) Can I just say a word because I am rather irritated by what counsel is saying. We had a meeting with Crossrail, with the particular station manager there, I think it was Thursday last week, about 10 days ago, when I went through all our proposals in a note, they knew what we were proposing and they talked to me about it, there were questions across the floor. This is not the first they knew of it.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007