Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 4540 - 4559)

  4540. Chairman: Just before we start, Mr Taylor, this was not a personal attack on your credibility; we greatly enjoy your advice whenever we get the opportunity.

  (Mr Thornley-Taylor): Thank you, sir; I took it as a compliment!

  4541. Mr Mould: Mr Thornley-Taylor, we have here the draft undertaking on noise and vibration, which has been provided to the CBI. I am not going to ask you to read it out, but what I would like you to do very briefly is to explain the process which is encapsulated within this undertaking in relation to controlling and mitigating the impact of airborne noise on construction sites on sensitive receptors such as, in this case, the CBI located within Centre Point.
  (Mr Thornley-Taylor): It is a two-pronged approach which devotes, on the one hand, effort towards controlling noise from the site through a process which I will explain in a minute, and on the other hand towards assessing the effect that that noise would have on premises which are acknowledged to be sensitive, as this one is, taking into account the noise levels predicted, assessing the sensitivity in the uses of the building and the structure of the building and working out whether any additional noise insulation measures are needed—for example secondary glazing may be needed—and then preparing a noise and vibration mitigation package which will ensure that through the construction process the uses of the building which have been identified as sensitive are not harmed by intrusive noise from a construction site. The other prong that I mentioned is the statutory process set out in section 61 of the Control of Pollution Act, where the contractor is required by the Secretary of State to go through a process of applying for prior consent for the works, in which he has to set out the plant and machinery he is going to use, the method of working, duration, the locations and it is not uncommon for that to include predicted noise levels. The local authority then either consents to the application as it has been made, or consents to it with conditions, and that consent having been given it is an offence to exceed or breach the requirements of the consent. So it becomes quite clear what future noise levels are going to be because if they are exceeded enforcement action is taken and the contractor has to stop doing what he was doing that was creating the exceedence. And that coupled with the package of measures which are implemented for what is known as the receiver, the building of the premises affected by the noise, ensures that throughout the construction process the noise effect is acceptable.

  4542. One other question: can you give the Committee an example of this approach to the control and mitigation of airborne noise apparently working successfully in practice?
  (Mr Thornley-Taylor): The one that sticks in my mind was when Canary Wharf Jubilee Line Extension Station was constructed, a very large copper damn was created with sheet piles around the outside to excavate deep into the former dock beside the buildings which formed part of phase one of Canary Wharf, the original cluster of buildings around the Tower. I remember actually being called down there because the contractor was exceeding the noise levels in his Section 61 consent. Immediate action was taken to make him stop doing what he was doing, which was trying to insert sheet piles using an inappropriate method, and it was immediately brought back down below the consented levels. But that is an example of the enforcement process, and, having used the enforcement process, the noise conditions inside the building were such as to enable normal use throughout the construction project.

  4543. Mr Mould: Thank you very much.

  4544. Mr Harwood: No questions.

  4545. Chairman: Are you content?

  4546. Mr Harwood: Having a noise and vibration package is part of matters which we have agreed and Mr Thornley-Taylor has not given any evidence specifically on Centre Point impacts and I do not propose to invite him to go into that territory.

  4547. Chairman: Thank you again, Mr Thornley-Taylor.

  The witness withdrew

  4548. Mr Mould: Sir, in relation to access, we have shown the Committee the suite of assurances that we now have given to the CBI in relation to their concerns on access. You have heard what Mr Anderson said about them, and I propose to do no more really than to say that in our submission those give proper and adequate comfort at this stage in the process. Of course, there will be a good deal more work to be done through the detailed design stage, as we move forward, but at this stage in the process they provide proper and adequate comfort and security to the CBI too in relation to the matters that they have raised before the Committee.

  4549. I do draw attention to the fact that in relation to that point you have not been told that there is any serious concern with the traffic management phasing process that we have proposed in relation to the works at Tottenham Court Road on the part of the CBI and nor have they put forward to you a particular point of access that they say they would wish to see being provided in order to meet their concerns. It is in that context that the suite of assurances we have given provides the comfort that we say is justified.

  4550. In relation to noise and vibration, I need say no more than you have heard what Mr Thornley-Taylor has just said in relation to that. The points he has made are encapsulated in the undertaking that we have given to the CBI, which you have seen in the Promoter's papers in relation to this petition.

  4551. In relation to settlement, there are two points. First of all, the concern expressed by Mr Handy that the buildings at Centre Point require some reassessment in order to see whether or not the risk categorisation that has been attributed to them thus far sufficiently recognises their sensitivity to settlement. That is dealt with through the process which is set out in our policy, and I have drawn attention to the relevant paragraphs in information paper D12 which deal with that. In essence, there is an ongoing process of detailed assessment through what we call our Stage 3 process. I have pointed to the paragraphs which address that. That will enable the concerns that Mr Handy has put forward to be taken into account as that process continues.

  4552. In relation to the concern about ongoing and recurring expenditure on repairs—you will recall that he made that point in his evidence to you—again, I would simply draw your attention to information paper D12, section 6: "The Promoter will require the nominated undertaker to reimburse property owners for the reasonable cost they incur in remedying material physical damage arising from ground settlement caused by the authorised works..." provided that a number of considerations are satisfied.[34] Plainly, in an appropriate case, that will embrace recurring expenditure, if that expenditure can be shown to be reasonable.

  4553. That deals with settlement. There is no particular point raised in relation to dust.

  4554. It remains just to deal with Mr Harwood's points in opening about controlling impacts by reference to the environmental statement and compensation. In relation to the former point, sir, I simply remind you of what was said by Mr Anderson in response to the Smithfield traders' petition. I have given you the references in relation to that, dealing with the question of compliance with environmental controls, including those within the Bill, those that apply from general legislation, and those that arise under the Environmental Minimum Requirements regime. We have drawn attention today to the key paragraphs in information paper D2 which indicate the Promoter's intention to carry out the project so that its impact is as assessed in the Environmental Statement, and the concomitant statement that the controls contained in the Bill and the general legislation which, along with the undertaking given by the Secretary of State, will ensure impacts which have been assessed will not be exceeded so as to depart from the Environmental Statement assumptions, save in certain specified circumstances.[35] That, in practice, achieves the result that Mr Harwood says is necessary here to give comfort to those affected by the scheme. How that is achieved in practice in any given case, of course, is a matter for consideration through the detailed design.


  4555. Sir, the final point is compensation, and I am very reluctant to go into that to any extent because you have heard form Mr Elvin in relation to that and you have seen the information paper. If I can give you the references in relation to the closing submissions on day 14 in response to the Smithfield traders, Mr Dingemans and Mr Elvin's submissions. Mr Elvin dealt in detail with the justification for applying what we call the National Compensation Code of Crossrail. Paragraphs 4041 through to 4047.[36] They pick up in particular concerns which have been expressed by these and other Petitioners about the limitations of the code in compensating for the environmental impacts of works from time to time during the construction phase. They also point out that, if access is obstructive as a result of works, the effect of that would, in the absence of the powers given by the Bill, be to give a right of action in common law, then the fact that that obstruction is temporary as opposed to permanent does not prevent the affected landowner from claiming compensation under the code if he can show that his land has been devalued as a result. There is, if you will, that residual comfort to somebody in the position of the CBI who are concerned that they may suffer from an obstruction of their access from time to time. That is something which, whatever its other limitations, the Compensation Code does provide for if the circumstances justify it.


  4556. My final point is that there is certainly no justification for extending the Compensation Code so that it provides a compensation remedy for loss of profits or loss of revenue per se. The Compensation Code has been in place since the first railways were built in the 1830s and 1840s. Whatever else it may or may not have done and however the vagaries of it exclusiveness or inclusiveness, it has never provided for recovery of items of that kind. We would respectfully submit there is no justification for a change of that radical nature being made, as proposed by the CBI.

  4557. Unless there is anything else, those are my submissions.

  4558. Mr Harwood: Thank you, Mr Chairman.

  4559. When Mr Mould was cross-examining Sir Digby Jones on the benefits of the scheme and leading on to the scale of works at Tottenham Court Road he seemed to be, essentially, suggesting you cannot make an omelette without breaking eggs. Well, Mr Chairman, in this particular case we would like the omelette but we are just concerned whether we might be one of the eggs or we might be some broken crockery. It is a matter or protecting, as is the main function of this Committee, interests which are impacted on by the Crossrail scheme. The CBI is in an unusual position in respect of Crossrail, in that its office use at Centre Point has to provide VIP meetings and operate a conference centre there; the Crossrail works will take place, at times, on all sides of the building over a period of five years—there will be work sites around the building for the majority of that time—and whilst part of the Centre Point building will be acquired none of the CBI's legal interest will be.


34   Crossrail Information Paper D12-Ground Settlement, http://billdocuments.crossrail.co.uk/ Back

35   Crossrail Information Paper D2 Control of Environmental Impacts, http://billdocuments.crossrail.co.uk/ Back

36   Smithfield Market Tenants' Association oral evidence, 1 March 2006. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007