Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 6960 - 6979)

  6960. So you have presented no written documentation to the Promoter on that. The first the Promoter heard of your views on that was when you gave evidence-in-chief some moments ago. Is that correct?
  (Mr Methold) I think my slide makes it clear that I have done a cost analysis.

  6961. So there has been no discussion about the evidence that you have given on costs with the Promoter?
  (Mr Methold) No.

  6962. That puts me in a slightly difficult position in respect of cross-examination, but I will do my best anyway. You mentioned that there were some limitations to the exercise that you had undertaken. I think you said that you had not examined the implications for the air flow within vents and whether that would be sufficient for the mitigation of noise—
  (Mr Methold) That is outside my speciality.

  6963. So there is the potential, is there not, for additional costs to be imposed to deal with that sort of issue?
  (Mr Methold) There is potential but I think that with the magnitude of additional mitigation that I have come up with in these vent shafts, actually it is unlikely that it would be an issue. I have a specialist in this area who works in the organisation who has been looking at this and without getting too technical there are various issues, such as back pressure that he is more than familiar with, that he is fairly confident that we have not erred in favour of the Petitioner, so to speak.

  6964. One last aspect in relation to the plus five/minus five debate, if I can call it that: you have received a copy, I believe, of the draft information paper that has been prepared. That is set out in P75 at page 118. I wanted to draw your attention to paragraph 2.12 of that document, which we see on page 120.[59] It indicates that: "While the degree of attenuation required is site dependent, not least because of different levels of background noise at different sites, the nominated undertaker will be required to use reasonable endeavours when designing the shafts to reduce the noise below the assessment criterion where it is practicable to do so." You understand what is being proposed there is, essentially, that the plus five figure is not a target and that where it is possible to have levels where the difference is significantly below plus five, reasonable endeavours will be used to achieve that. Do you understand that aspect?

  (Mr Methold) I do understand that aspect. I am concerned about the phrase "reasonable endeavours".

  6965. Indeed, we know, do we not, from your own evidence in LBH47, where you have identified 16 out of the 26 vent shafts already would achieve differences below your minus five criterion level.[60] Yes?

  (Mr Methold) Correct.

  6966. That indicates that the Promoter is already adopting the approach set out in the draft IP.
  (Mr Methold) I think it shows that the Promoter—and this was actually stated at the meeting we had recently—has really just used the Environmental Statement to identify whether their design standard of L90+5 can be achieved. I do not think there is any commitment at all to reducing below that. I am concerned about the use of "reasonable endeavours" and what that actually means in practice. My view is that you can use reasonable endeavours and still only have to meet L90+5, but this is a draft information paper and I would like to explore that further.

  6967. That is why it is in draft, so that we can continue discussions and, hopefully, achieve a measure of agreement in the future. Let us move on to deal with your point about background noise levels, if I may, briefly. Am I right in thinking that the background ambient noise levels change over time?
  (Mr Methold) Yes, they do.

  6968. So it would be right, would it, to carry out measurements of background in the future prior to the design process starting in order to take into account those sorts of changes?
  (Mr Methold) Absolutely expected, yes.

  6969. So the right approach to the design process for fixed installations, in relation to Crossrail, would be to establish at an appropriate time in the future what the background noise levels are in each location.
  (Mr Methold) Correct.

  6970. The draft IP that has been produced indicates, does it not, at paragraph 2.14, page 120 again: "The nominated undertaker will be required to determine the relevant LA90 levels to be jointly established with the relevant local authorities."[61] Now, if that is the approach that is adopted that meets your concerns about the identification of the appropriate background level.

  (Mr Methold) It meets my concerns at the design stage; it does not meet my concerns about the information that has been presented in the Environmental Statement, which is still based upon this modal value of background noise level. As I said in my evidence, I believe that is has serious and significant impacts which the Environmental Statement has a duty to report at this stage or to present to the decision-maker.

  6971. So you are saying there will be circumstances where the plus five criterion cannot be met?
  (Mr Methold) I believe there is, yes. Well, where the plus five criterion would not be met according to the Promoter's calculated levels at present without further mitigation applied.

  6972. So with further mitigation plus five levels can be met in all locations.
  (Mr Methold) It may well be but we do not know that. The Environmental Statement does not tell us that.

  6973. If the plus five level is adopted as the level of significance (and I do not disagree with that), on that assumption that would mean there would be no significant impacts arising from fixed cost installations.
  (Mr Methold) With a mystery level of mitigation incorporated.

  6974. Let us deal with Thameslink 2000. That project does not involve any new tunnelling.
  (Mr Methold) It does not.

  6975. It does not involve the creation of any new vent shafts that are ventilated by fan, as I understand it. Is that correct?
  (Mr Methold) As far as I understand, yes.

  6976. It does not involve the provision of new maintenance depots.
  (Mr Methold) No, it does not.

  6977. It does not involve the provision of new stations.
  (Mr Methold) I do not think so, no.

  6978. It would be right, given those differences, to recall that the fixed installations involved in the Thameslink 2000 project are of a different kind to those provided in relation to Crossrail.
  (Mr Methold) I think that what we have to be very clear about is that Thameslink have, essentially, justified L90-5 on acoustical grounds. They have agreed this with the local authorities, they have done their own review of the guidance that I have taken you through today and they have concluded that L90-5 is an appropriate acoustical target to meet. That is important. That is why I have a problem with the Promoter suggesting that they need to go into something else than ventilation shafts because it conflicts with the whole premise that the acoustical target should be moved.

  6979. Did the promoter of Thameslink 2000 form that view in relation to all forms of fixed installations, or did they form a view in relation to—
  (Mr Methold) I do not know. I was not party to those discussions, I am afraid.


59   Crossrail Ref: P75, draft Information Paper, Noise from Fixed Installations (HAVGLB-14704-120). Back

60   Committee Ref: A81, Achievability of Alternative Design Aim (HAVGLB-14705-047). Back

61   Crossrail Ref: P75, draft Information Paper, Noise from Fixed Installations (HAVGLB-14704-120). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007