Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 7040 - 7059)

  7040. At that stage, was the Crossrail route being safeguarded?
  (Mr Methold) I would imagine it was, yes.

  7041. Thank you very much. That is all I wanted to ask by way of re-examination.

  7042. Chairman: Mr Methold, there are one or two things. You referred, when you were taking about noise reduction, to the Thames link and Jubilee line extension about the hardware and that you could not understand why it had not been included as it was 100per cent available. Can you elaborate a little bit on that?
  (Mr Methold) Can you repeat that?

  7043. Chairman: You were talking about the hardware put together for the building of the Jubilee line extension and the Thames Link, all the noise reduction standards, that the hardware which had been prepared for the construction was fully available.
  (Mr Methold) I think my reference to the hardware was in relation to whether a preferred design of a L90-5 could be achieved by the Crossrail project.

  7044. Chairman: Can you elaborate on that a little bit because if there is something available it might be helpful to the Committee and that is why I am interested?

  A.(Mr Methold) Absolutely. What we have had to do to understand whether an L90-5 was achievable for Crossrail was to understand what Crossrail had assumed would be the level of reduction inside the ventilation shaft as part of their environmental statement work. They gave a fairly detailed report giving us the predicted noise levels that they had from their ventilation shafts but nothing about what was inside the shafts. Some internet searching on our behalf revealed a report which gave us the sound power levels and the assumed level of attenuation inside the ventilation shafts. From that point we were then able to work out the additional attenuation that was required. To step back slightly, there are two types of mitigation that can be applied to ventilation shafts. One we call an "in-line attenuator". Essentially it is placed in front of the coaxial fan, the fans that are blowing the air through the shaft. It is made with an absorbent material and it lets the air flow through it but at the same time it absorbs the noise, in very simple terms. We know that the Promoter assumed an attenuator that is three metres long, which is a reasonably hefty unit. We have found that they do not need to have any more than an extra metre and a half on top of that to achieve L90-5 across all of their ventilation shafts. That is not an enormous extra amount of—

  7045. Sticking with that, you also referred in questioning to the costs that might be attributed to doing that in these sections. You gave a figure, less labour costs, of about £100,000. Is that just pie in the sky? Do you have any analysis?
  (Mr Methold) I do have analysis. We contacted the supplier that we know Crossrail used to generate their noise source terms and their attenuation performance, the very same supplier, and we had costs from them on a per square metre basis. I am hoping that is consistent with the budget that the Promoter has in place.

  7046. Could you prepare a note on that and get back to the Committee, but only in respect of that which we just discussed there, not for the whole of the Crossrail project?
  (Mr Methold) Certainly. Just to add to that, the reason we looked a the cost analysis on the

  vent shafts only was because the Promoter was making the point that it was the main reason

  they could not accommodate the Thameslink 2000 L90-5 design criterion.

  7047. On the question on scientific evidence which Mr Taylor put to you on at least three occasions, I never heard an answer. Albeit you said at one point that there have been complaints at a oneper cent increase and that indicated that there was a problem, you never really answered his question as to whether there was any scientific evidence of fact that it did have that effect.
  (Mr Methold) In so far as it was a logged complaint at the local authority from a resident.

  7048. I understand where you are going, but his question to you was: Has there been any evidence which showed conclusively that that was a fact or not or was it still a matter that was conjecture and which has not been established yet?
  (Mr Methold) Certainly there is a noise assessment done by specialist acoustic consultants in that case and a report was produced which indicated that that complainant was likely to be experiencing L90+1.

  7049. You would hold that as fact?
  (Mr Methold) I would, yes. That was a report

  7050. Could you supply the Committee with a copy of that?
  (Mr Methold) Certainly.

  Chairman: Thank you.

  The witness withdrew

  Mr Rupert Thornely-Taylor, Recalled

  Examined by Mr Taylor

  7051. Mr Thornely-Taylor is well known to the Committee. I will not introduce him again. What is the objective of the National Planning Policy so far as development that has the potential to cause noise is concerned?
  (Mr Thornely-Taylor) It is contained in paragraph 10 of PPG24 which we have already looked at. In a nutshell, it is that there should not be an unacceptable degree of disturbance.

  7052. What does the National Planning Policy say in regard to reducing existing ambient noise levels?
  (Mr Thornely-Taylor) PPG24 has no section devoted to reducing existing ambient noise levels.

  7053. What does the National Planning Policy say with regard to meeting the guidelines for community noise levels set out in the document published by the WHO?
  (Mr Thornely-Taylor) The only place you find reference to the WHO material in PPG24 is where it explains how it derives its system for categorising new residential development according to its noise exposure category. That is all.

  7054. We have seen from PPG24, paragraph 10 (page 72 in document A75) the reference to: "Much of the development which is necessary for the creation of jobs and the construction and improvement of essential infrastructure will generate noise. The planning system should not place unjustifiable obstacles in the way of such development."[75] If a design target is set by reference to the absolute levels set out in the guidelines for the Crossrail fixed installations, what do you say about practicability of design to that sort of target?

  (Mr Thornely-Taylor) One has to take a different view by day and by night. By day in some locations it would be a major engineering obstacle to achieve the levels and would place an unjustifiable obstacle in the way of development. In other ways, at night time the WHO levels are nothing like good enough because they use the whole eight-hour night period as the averaging time and since the fans we are talking about may run for only a few minutes in a night, you could in fact have a fan making a noise well up into the 50s and still not exceed the WHO figure of 45. From that point of view, they are very unhelpful. I really think they are a bit of a red herring in the present circumstances because the WHO document is all about transportation noise sources and nowhere in the document do they address noise from fixed plant. It is by extension that people such as Mr Methold seek to apply them to fixed plant. They were never intended for that purpose.

  7055. In the context of National Planning Policy indication that the development should not cause an unacceptable degree of disturbance, how do you see a design criterion of background plus 5 dB in BS4142?
  (Mr Thornely-Taylor) It fully complies with the requirements of PPG24 and it certainly achieves the objective of not causing an unacceptable degree of disturbance and it is implementable and practicable and shown to work well on previous projects.

  7056. You heard the point that was made earlier on this morning that if the plus 5 criterion is adopted, the nominated undertaker will simply design to that so as just to meet that level. In the light of the paragraph to which I drew Mr Methold's attention in the draft IP, paragraph 2.12, what do you have to say to the Committee about that suggestion?[76]

  (Mr Thornely-Taylor) Most certainly that will not happen because, as we saw in the draft IP, paragraph 2.12: "While a degree of attenuation required is site dependant, not least because of different levels of background noise at different sites, the nominated undertaker will be required to use reasonable endeavours when designing the shafts to reduce the noise below the assessment criterion where it is practicable to do so." And, as Mr Methold has said, Crossrail have provided information to Havering which shows that there are many cases where it is entirely practicable to do that and many of the shafts will improve on the Crossrail policy and it certainly will not be an upper limit which a contractor will just achieve at every single site. It will be a limit that we need to meet at the severe engineering constraints at a few of the most difficult sites.

  7057. Chairman: Mr Taylor, we have to do our duty. We will return in 20 minutes.

The Committee suspended from 2.59 pm to 3.12 pm for a division in the House

  7058. Mr Taylor: Mr Thornely-Taylor, what scientific evidence is there that a minus 5 dB criterion would result in material benefit to the amenity of those who might otherwise be affected by noise from fixed installations compared to a plus 5 dB criterion?

  (Mr Thornely-Taylor) On this particular topic I already mentioned the fact that most noise targets are about transportation noise for which there is information about the relationship between the number of people, a noise and the levels, but for fixed plant we do not have that kind of scientific evidence. In general, one can say if noise levels are sufficiently satisfactory to avoid an unacceptable effect, then there is no advantage in going below a noise level.

  7059. If the plus 5 dB design criterion is adopted, what can you tell the Committee about the prospects of meeting that criterion in terms of the mitigation that is available?
  (Mr Thornely-Taylor) It does present some severe engineering challenges. The Committee did receive a slightly over-favourable impression from Mr Methold's evidence. The noise levels we are talking about are low and after incorporation of the fan noise attenuators that were referred to, the dominant noise source is just aerodynamic noise of the air coming out of the louvres of the ventilation shaft. Mr Methold talked about bolting another metre of attenuator on but you cannot bolt an attenuator on the outside of the louvres of a vent shaft and that is the kind of thing which is the reason why there are engineering difficulties, which admittedly can be reduced at a cost somewhere along the line, but they are the top-line concern that we must take into account when considering this policy.


75   Crossrail Ref: P75, Planning Policy Guidance 24: Planning and Noise, Development Control, Noisy Development (HAVGLB-14704-072). Back

76   Crossrail Ref: P75, draft Information Paper, Noise from Fixed Installations (HAVGLB-14704-120). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007