Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 8960 - 8979)

  8960. We therefore continue to remain very concerned in a number of areas, and these areas are shared with our inspecting architect Julian Harrap, who is a very experienced and well respected conservation specialist. I think you may have before you a letter which confirms an email which he or one of his staff sent highlighting the practice's concerns about the impact of the Crossrail tunnelling. He draws to mind the fact that the church falls within the zone of zero to 0.01 mm of possible movement when the tunnelling is taken. That might not seem like an awful lot, but the movement is likely to be absorbed on all sides by the building fabric. That could lead to cracking within the mortar joints, or fracture of the stonework, due to the nature of the differential movement experienced by the whole building, as if the building were moving across itself.

  8961. The existing structure is particularly prone to movement due to the nature of its medieval construction. That is the thing which concerns us most. The masonry walls consist of random rubble which is not brought to courses. It is constructed on shallow or minimal foundations. As yet, we are not convinced we know the nature of the foundations that exist beneath the building, especially beneath the tower, which, as has been alluded to, houses our very grand bells. The bells are very, very heavy, as is a lot of the concrete work at the top of the tower, and—although this is hearsay and you may not want to hear it—people are amazed that the tower is able to cope with that particular weight at the top, given that there is no clarity about the nature of the foundations at the bottom.

  8962. Underpinning the foundations—which might be seen as a way of protection—our architect advises us would be an expensive task and may not anyway solve the problems experience by differential movements across the whole building. Movement in the north-west corner of the 15th Century church tower has already been detected. If you were to walk up the tower's spiral staircase, you would see those little bits of kind of tell-tale glass cemented to the wall, which would suggest that there has been movement. Our architect has told us that this has been due to gradual ground movement over the last 200 years.

  8963. Hockley and Dawson, specialists in conservation work and our structural engineers, have stated that the configuration of the branching tunnels is likely to make this particular movement we are already experiencing much worse. Recent conservation work on the tower, which has taken place over this last winter, has highlighted that the general condition of the stonework forming the walls is poor. The stone used is a mixture of soft Reigate and Kentish ragstone which is particularly soft by nature and is currently scaling. If you walk around the bottom of the tower, you can see bits of the scaling that has dropped off and flaked to the ground. I and the church are therefore very concerned about the impact of the tunnelling process on what seems to me to be a unique and really quite delicate historic building.

  8964. We have had some discussion earlier about the location of the plague pits which are located somewhere in the vicinity of the churchyard. Our architects are particularly concerned at the impact of that on the building, in that of course it makes the subsoil of a very uncertain nature because we do not quite know what exists beneath it. There is a concern about the impact of that upon the nature of the ground beneath—in fact, the whole churchyard, as you might expect, is full of bodies.

  8965. We are also concerned about who would pay for the surveyors and any agreed remedial works. Our structural engineer has stated that the church could appoint an independent tunnelling expert who would be best at advising us at the likely impact of the tunnelling and be able to monitor the effect of the tunnelling upon our building. This would be an expense which I put to you the church would find it very difficult to have to bear. Our reason for coming to you this morning is to reiterate that, whilst we recognise the importance of the Crossrail development and we do value the impact that will make upon our community and upon the whole of the East End, we ask again whether the route of the tunnelling could be amended to take account of the risk of damage to what is a priceless historic and unique Grade I listed building.

  8966. Whilst we are aware that there is always a cost implication to such a move, given the possible consequences, we think it is a question well worth asking and, from your point of view, well worth considering. We have never really had a clear and convincing answer as to why that would not be a possible solution. If it does transpire that that is not possible, we should like to think that the church might be afforded the opportunity to engage independent experts to monitor the impact of the tunnelling on this unique building for a reasonable period of time, the cost of which we believe ought rightly to be borne by the Crossrail developers.

  8967. The current proposals seem to use to be quite short term and place a heavy burden of cost and responsibility upon the church community that we would find it difficult to support. At the very least, we would wish to see the building treated as though, from the Promoter's point of view, it were in category 3, especially given the very real nature and danger of lasting damage to one of the only medieval buildings surviving in East London.

  8968. This may seem a bit like a David versus Goliath action, but we believe our requests are reasonable in the circumstances. I hope that members of the Committee would view them sympathetically and thank you for allowing me to speak to you. I will hand over now to Stephen Richards.

  8969. Mr Richards: I am the Agent for the Petitioner. I would like to address some specific points that have arisen from the Promoter's response to our Petition, if I may.

  8970. The overriding concern of the Petitioner is the wellbeing of this church. He sees the wellbeing of the church and its fabric as being best guarded by a diversion of the route of Crossrail away from the church, even by a degree or two, in order to minimise potential disruption.

  8971. We do appreciate that this would involve a certain amount of cost and difficulty at this point and, were that not possible, then as a fallback we would like to address certain of the points that the Promoter has raised, particularly in relation to paragraphs 14, 15, 16, 17, and 18.[4] They deal with the risk of damage to the fabric of the church caused by tunnelling, ongoing vibration and traffic in tunnels. That is on page 4 of the Promoter's response. The Promoter has kindly offered that there will be a further stage 3 assessment to the fabric of the church in order to determine whether the risk category in which the church should be placed. We would ask the Committee that, in order to save the cost of conducting this additional assessment, and particularly given the unique and delicate nature of the building, the church be treated as if it were automatically a category 3 building. It is my understanding—and please do correct me if this is not the case—that a category 3 building is entitled to independent monitoring of the cost of the Promoter during and after tunnelling. If we are placed in a lower-risk rating than category 3, there is ongoing monitoring during tunnelling and following tunnelling, from my understanding, only to the extent that the church is able to show certain movements and that this movement has taken place within the two years of the tunnel opening for traffic following its actual opening. Once again, this is monitoring which the church cannot afford and we consider by the time the damage is discovered, were we able to afford it, then the damage may well be irreparable to this unique Listed building. In terms of that, the Promoter has offered to make good material physical damage within two years of the opening of the tunnel for traffic, which we welcome and thank the Promoter for.


  8972. One point we would like to make is that it appears that we have to identify the extent of this damage, prove this damage and the causal link with Crossrail at the church's cost. Once again, we believe this is a cost which the church is not able to sustain, and even if it were able to sustain it, we feel it would be more properly borne by Crossrail to show this. Those are the points we would like to make in relation to paragraphs 14, 15, 16, 17 and 18 in relation to damage to the church fabric.

  8973. The other points raised in the Promoter's response were in relation to paragraphs 20, 21 and 23 of the Petition. This is on page 8 and 9 of the Promoter's response and deal with the matter of disapplication of various statutory provisions for the purpose of the Bill being able to disinter bodies primarily and also disapplication of Listed building regulations.[5] We are happy with the Promoter's response to these particular paragraphs of the Petition provided that the offers they make in their response are made good in terms of ongoing monitoring of the site and, also, provided that the offers they make in relation to protective work are honoured. There are very few specific points there, but, just to summaries that, we are very grateful to the Promoter for the offers they have made thus far.


  8974. In an ideal world, we would like to see the course of the tunnels being diverted slightly away from the church to minimise risk. If this is not possible, we would like the church to be considered automatically as a category 3 building and have the protections that that would bring with it in terms of both monitoring during the tunnelling and after.

  8975. Finally, to the extent that if there are any works required to the church, we would like the Promoter to agree to underwrite those works prior to them being undertaken. At present my understanding is that it is proposed that the Promoter will simply indemnify the church for works that are undertaken. I am sure you know enough of business to understand that this brings a cash-flow difficulty to an organisation which has had difficulties raising £200,000 for the vital restoration works in raising the tower; that took some three years. In order for them to find a lot of money at short notice it would be difficult, if not impossible, for the church. That is all I have to say. Thank you very much for your time.

  8976. Chairman: You have no other witnesses, Mr Richards?

  8977. Mr Richards: I do not.

  8978. Chairman: Mr Mould, would you like to make your case?

  8979. Mr Mould: Sir, what I would like to do, if I may, is ask Mr Berryman briefly to address the point as to whether we are in—as Mr Richards put it—an ideal world where we can shift the running tunnels from their proposed location. I will deal with that in a moment, but there are one or two points there which I think I can clarify, I hope, to the satisfaction of the Petitioner and also to reassure the Committee as well. First of all, I mentioned in my brief opening that we have gone a fair way down the route of assessment in relation to this building. I mentioned that we have in documents before the Committee what we call the phase 3 first iteration settlement report in relation to this structure. I wonder if I might put that up on the screen. It is O4C009, please.[6] I will not take the Committee through this in any detail, but you will see the summary and the conclusion at the bottom of this page. It sets out the score following assessment at this stage in the process which has been attributed to this building from an engineering perspective, in relation to the sensitivity of the building structure, special or vulnerable features/finishes and predicted damage category. You will see that the total score is four. I will not go through why and how the scoring is done at this stage, but the conclusion is this:



4   Crossrail Ref: P86, Promoters Response Document-Settlement, contamination (TOWHLB-30902-004). Back

5   Crossrail Ref: P86, Promoters Response Document-Disapplication of statutory controls (TOWHLB-30902-008). Back

6   Crossrail Ref: P86, Engineering Assessment by Mott MacDonald (TOWHLB-30904C-009). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007