Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 9440 - 9459)

  9440. Conclusion?
  (Dr Bowers) In conclusion, therefore, on these points, for the Borough to be persuaded that the GOMMMS conclusion is robust in engineering terms, there is some further information that is needed. Firstly, it needs to be clearly demonstrated that the alignment considered through Woodseer Street, and by that I mean the alignment in a final comparison, is one that is optimised both in railway operational terms and also in terms of the interfaces with the existing structures, so that would be an iteration beyond Option 2, as we see it at the moment. Secondly, in the event that such an optimised alignment still required the tunnels to pass closer to Bishop Square than the base case, the precise implications for the project need to be clarified. Thirdly, if the variation in geological risk of depth is considered to be a dominant factor in the choice of alignment, the extent to which this risk is worse and the mitigation needed is greater for a Woodseer Street alignment needs to be clearly demonstrated.

  9441. Now you hand the baton over, as it were, to Mr Turner who will now deal with the noise aspects of the same GOMMMS analysis. Mr Turner, you first of all just give a short description of the timing of the documentation which has been provided by Crossrail.
  (Mr Turner) Yes, as Mr Whalley has said, we first got some information about the comparative study in the middle of May and then last Thursday we received some information which included details of the likely construction programme and importantly an indication of the sort of noise sources that were then likely to be needed in the construction of a new shaft at Hanbury Street. My evidence is just to concentrate on one element of this comparative study under the heading `Environment', and perhaps I could have the next slide please.[12] That is an extract from the comparative study showing the assessment that was done regarding the relative noise and vibration impact for the Hanbury Option compared to the Woodseer Option 2.

  9442. We are looking at an extract from the Promoter's GOMMMS analysis. Is that right?

  (Mr Turner) That is correct, yes. It can be seen that under the `Comments' section, there are broadly two comments against Hanbury and two against Woodseer. The first sentence against each option is in fact identical, saying that the construction effects on residential properties will be much greater than for operational noise and vibration. I would argue that actually that is not the relevant point because it is the same for both option and, therefore, we can put that to one side. The second comment is that for Hanbury the noise and vibration impacts on the Bishops Square development have been mitigated in its design based upon the base case alignment, and that is the principle that Dr Bowers was talking about just now, whereas at Woodseer there is an increased risk of impact from noise and vibration at the Bishops Square development, in particular, during construction. Therefore, the scoring, which can be seen in the last column, shows Woodseer as more adverse compared to Hanbury and a justification of the points I have just outlined which of course, regarding Bishops Square, was covered by Dr Bowers. Importantly, as anticipated by Mr Whalley, there was no consideration that appears to have been given in its assessment to the relative noise impact during the construction phase of the shaft on those properties located nearby. The next slide is a photograph looking towards the Hanbury Street shaft probably in a westerly direction and the light brown building is where the site is.[13] The buildings to the left, the three-storey ones with the blue heading, are the commercial properties with residential properties above. The next slide shows a simple set of lines showing distances from the new worksite with the revised proposal at 25, 50 and 100 metres from the boundary of the site.[14] It can be seen that within 25 metres the line cuts through several of the properties nearby.

  9443. Let us just be clear of what the key is. How do we identify residential property?

  (Mr Turner) Residential properties are broadly those in the yellowish colour, but, because of the limitations of the technology, it misses the fact that immediately to the south of Hanbury Street there are in fact residential properties there and in fact I have been in one of those flats and looked over what would be the Hanbury Street site.

  9444. What is the relationship between those flats and the construction site?
  (Mr Turner) It is effectively down below their window, where the site would be working. If we move to the next slide, that is a picture of the corner of the Woodseer site, I think, looking towards the north-west.[15] Then the next slide is the equivalent diagram showing the Woodseer site boundary and the 25, 50 and 100 metres distance.[16] There you can see that within 25 metres, for example, it looks as if there are possibly three properties in Woodseer Street itself which fall within that distance, but certainly further away from the site than those properties we were talking about just now in Hanbury Street. Therefore, at first blush, just simply looking at the distance of the properties to the sites, it looks as if Woodseer Street would be the preferable option. The point is that we have not received the proper impact assessment with the associated noise calculations to be able to form a detailed view of the relative impact.

  9445. There is one thing about Woodseer Street while we have the slide up. Can you just tell us, and the Committee may know this already, its current use? Do you know anything about its projected plan in the future?

  (Mr Turner) I understand its current use is that there is little business on it and there is some car parking that is used. It is certainly part of the car park for the brewery and I understand there is some planning consent on that, and Mr Whalley could probably give you more details. If we could go back to slide 12, we have already spoken about the properties immediately to the south of the site.[17] With the original Hybrid Bill scheme, those properties were identified as having such a severe noise impact during the construction phase that they would be eligible for temporary rehousing during the construction phase element. I do not know for certain yet, but I would not be surprised if they would also be eligible for similar treatment with the new scheme simply because they are so close to the site, whereas, if we could go back to slide 14, there are properties that close to the site and I would be surprised if any properties there would be similarly eligible.[18] Therefore, it seems from that cursory assessment, and do bear in mind that we do not have the details, that it is quite possible that once the noise and vibration impacts during the construction phase are properly taken into account, the Woodseer site could be clearly the preferred alternative on this aspect, whereas at the moment in the analysis presented by the Promoter, they have Hanbury Street as the proposed option.

  Cross-examined by Mr Elvin

  9446. Mr Elvin: I think I will stick for the moment, if the other two will forgive me, with Mr Turner and the comparative position of Hanbury Street and Woodseer Street and just draw attention to a couple of features. Can we please go back to slide 12.[19] Hanbury Street, Mr Turner, so far as residential properties in close proximity is concerned, although it is not shown on this plan as orange, there are the upper storeys and the shops at Princelet Street you were drawing attention to, the ones with the blue fascia which we saw on the photograph.

  (Mr Turner) Yes.

  9447. Other than those, all the other residential properties in close proximity to Hanbury Street are shielded by other properties, are they not? For example, in the revised scheme Britannia House does not come down and it will remain as a substantial barrier to noise affecting those to the west along Hanbury Street and Princelet Street?
  (Mr Turner) That is quite correct, yes.

  9448. Similarly, in Princelet Street, other than those who back directly on to the site, those on the opposite side of Princelet Street will have the houses which do back on to the site again as a barrier?
  (Mr Turner) That is right, yes.

  9449. Secondly, so far as the temporary rehousing is concerned, of course that was in the scheme when Britannia House was going to be demolished, was it not?
  (Mr Turner) Indeed, that is in the Hybrid Bill scheme.

  9450. And you would accept that a significant element of change in the new proposals is that Britannia House does not have to go and it remains there? It is no longer a noise source in itself through demolition and it remains a substantial barrier protecting a lot of the residential properties in Hanbury Street and Princelet Street?
  (Mr Turner) I cannot disagree with that. I think simply the point you are making is that we do not know yet know and, when we have got a proper assessment, then we can form a view.

  9451. I am just drawing your attention to what the comparative position might be. Then the only other properties that remain without any direct barrier are those in the flats across the road, are they not? That is a block of flats.
  (Mr Turner) That is right, yes.

  9452. Members of the Committee will have seen that on their site visit.
  (Mr Turner) Sure.

  9453. Can we just look for comparative purposes at Woodseer Street and can we look at photograph 13 which is the next exhibit.[20] In terms of the main residential properties, this in fact is looking the wrong way, is it not?

  (Mr Turner) It is, yes.

  9454. The main residential properties are on Spital Street and the back of the photographer is to the gardens of the flats on Spital Street, so if we look at the next plan, which is 14, we have here Woodseer Street and we have here in close proximity a series of blocks of flats which will directly overlook the Woodseer Street site.[21]

  (Mr Turner) Yes.

  9455. Indeed in terms of comparative proximity and numbers of flats, there are far more here than you would have overlooking the Hanbury Street site.
  (Mr Turner) Well, in terms of the total count, the difficulty is that we do not have the information. The point you are making about the effect of localised barriers is perfectly valid and would be taken into account in the calculations. On a simple property count and distance, Woodseer Street is the favoured option, but the detailed points you are making are quite right. What we are asking is that we have that information so that we can form a proper view. I think dismissing it at this stage is premature.

  9456. Mr Turner, I understand your point and there will be a further Environmental Statement. I am simply trying to draw out why in fact one might already begin to form at least a preliminary view based on some of these characteristics. Of course we have got some dwellings there, but of course the buildings in the Woodseer Street site will have to come down and there will be no significant noise barrier along the lines of Britannia House to protect the residents here or here, and the residents in the flats here cannot really have any acoustic barrier treatment because they are at a much greater height because it is a multiple block of flats overlooking Woodseer Street.
  (Mr Turner) There would be less opportunity to shield the upper storeys, I would agree, but the standard mitigation being proposed for all worksites includes fencing of various heights and I would imagine that the plan would be for a five-metre fence at least.

  Indeed, but what we lack on Woodseer Street is anything akin to Britannia House providing significant shielding, so these dwellings here will have to rely simply on the five-metre acoustic shielding or whatever else is determined at the time as being necessary.
  (Mr Turner) They do not have a Britannia House to protect them, yes, that is correct.

  9457. Thank you. Can I then just turn please to Dr Bowers. I just want to deal with the possibility of revising the alignment and can we look at exhibit 8, please.[22] Could you zoom in a little bit so that we can have the end of Whitechapel to Liverpool Street but just a little bit more visible detail. As I understand the situation, it was thought that there may be some scope for further iterations of this alignment to allow the track to go slightly further to the north to produce a tighter curve and possibly miss Bishops Square.

  (Dr Bowers) That was not the suggestion. The observation was firstly associated with this section of the curve west of Whitechapel. That section of the curve is of the order of 600 or 700 metres radius, depending on which tunnel you look at, which is a rather greater radius than the minimum desirable, which clearly one wishes to stay within. If one were to tighten that curve—and I exaggerate because it is necessary on this scale—one would reach a point somewhere more in this direction and could then go back into a curve the other way. Again, I exaggerate the difference in angle but it would pass through the shaft, say, more towards that orientation and that would have an effect down here. Putting it in numerical terms, the differences are small but we are only looking at a few metres over here in plan.

  9458. I will ask Mr Berryman just to give a view on this. The Committee knows our concern and I will get Mr Berryman to explain the position. Our concern—and as Mr Berryman will explain, there has been considerable consideration given to alternative alignments—is that the curve here gets tighter. Are you aware that the curve going into Liverpool Street is already substandard and that any further tightening of that curve will be unacceptable?
  (Dr Bowers) Yes, the curve in this area is, I believe, around 300 metres radius minimum which is, as you say, substandard and we would not be anticipating any change that made that worse.

  9459. The risk here of course is if that curve is tightened by any change in alignment it has unacceptable effects at the western end of Liverpool Street, does it not?
  (Dr Bowers) Indeed, which is exactly why we would not seek any tightening of that curve.


12   Committee Ref: A110, View of Woodseer Street (TOWHLB-21805B-011). Back

13   Committee Ref: A110, Crossrail-Impact of Proposed Worksites in the Spitalfields Area (Hanbury Street Worksite) (TOWHLB-21805B-012). Back

14   Committee Ref: A110, View of Woodseer Street (TOWHLB-21805B-013). Back

15   Committee Ref: A110, Crossrail-Impact of Proposed Worksites in the Spitalfields Area (Woodseer Street Worksite) (TOWHLB-21805B-014). Back

16   Committee Ref: A110, Crossrail-Impact of Proposed Worksites in the Spitalfields Area (Hanbury Street Worksite) (TOWHLB-21805B-012). Back

17   Committee Ref: A110, Crossrail-Impact of Proposed Worksites in the Spitalfields Area (Woodseer Street Worksite) (TOWHLB-21805B-014). Back

18   Committee Ref: A110, Crossrail-Impact of Proposed Worksites in the Spitalfields Area (Hanbury Street Worksite) (TOWHLB-21805B-012). Back

19   Committee Ref: A110, View of Woodseer Street (TOWHLB-21805B-013). Back

20   Committee Ref: A110, Crossrail-Impact of Proposed Worksites in the Spitalfields Area (Woodseer Street Worksite) (TOWHLB-21805B-014). Back

21   Committee Ref: A110, Crossrail Central Tunnels-Woodseer Street Shaft Alignment Option 2 (TOWHLB-21805B-008). Back

22   Committee Ref: A110, Crossrail-Impact of Proposed Worksites in the Spitalfields Area (Hanbury Street Worksite) (TOWHLB-21805B-012). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007