Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 9622 - 9639)

Ordered: that Counsel and Parties be called in.

  9622. Mr Liddell-Grainger: As usual, I inform the Committee that it is my intention to suspend at a convenient time, some time or thereabouts at 11.45 so that everybody can have the opportunity of a comfort break. As there are so many cases to hear today, I will now explain exactly how we will proceed.

  9623. The Committee wants to hear every Petitioner's case. However, as you know, the Committee will not listen to the same evidence being made more than once. We understand that many people here do have similar concerns. We would ask you to listen carefully to the case being made to you and other responders by the Promoters and try not to repeat, if possible, anything that has been said. If you agree with the case that is being made, you can tell us which points you support, that is absolutely acceptable, and you do not then need to repeat the argument. Some of the issues which are revolving around Hanbury Street and Whitechapel have already been raised by the London Borough of Tower Hamlets in last week's committee and have already been taken into account from what was said last week. Equally, we encourage, dare I say it, counsel for the Promoters to refrain also from repeating counterarguments, where possible. I remind everybody that any witness brought forward by the Promoters may be cross-examined by each and every Petitioner, should they wish to, after they have made their case, but we understand it would be helpful to hear the first two cases and then we will ask counsel to respond. We will then call each additional Petitioner to make their case after the first two. Mr Elvin?

  9624. Mr Elvin: Sir, the first two Petitioners, and I am not entirely sure which order they are being presented, are the Spitalfields Society and Dr Pedretti.

  9625. Mr Liddell-Grainger: I think we are going to take Dr Pedretti first.

  9626. Mr Elvin: Sir, I am going to give an introduction which will just go over some of the main issues the Committee will be hearing from Petitioners today. This will cover not only issues raised by Dr Pedretti and the Spitalfields Society, but some of the more general issues that are raised because I do not propose then to repeat myself, taking my guidance from what you have just said.

  9627. As the Committee has already noted, the Petitioners this week follow on to some extent from the issues raised by Tower Hamlets last week and there is a degree of overlap, particularly on the issue of the Hanbury Street shaft. Sir, since a large number of the Petitioners are raising similar issues and there is considerable overlap, I will go through the main issues, although Petitioners should note that I am not dealing with each and every issue in their Petitions, just the very broad issues which are in common.

  9628. Those issues appear to us to include issues relating to a station at Whitechapel, secondly what is now proposed as a ventilation and intervention shaft at Hanbury Street, construction impacts on individuals and on the community, the alignment of the tunnels and the impacts in terms of noise and settlement, especially on the many Listed buildings in the Spitalfields area, and compensation issues.

  9629. If Mr Fry could please put up plan A2 from the Environmental Statement, volume 4A, and zoom in please on Hanbury Street, that is the main area under consideration.[1] Of course the Committee are very familiar with this, having had a site visit and seen the documents on a number of occasions. Whitechapel of course is to the east of this plan. We have also provided for the Committee, and I will have paper copies distributed, a plan which is GEN-0101 which shows you the location of most of the Petitioners' properties in the area.[2] It is a bit difficult to read on the screen, so I have asked for A3 copies to be provided, but what this will do is give you the Petition numbers, and some of the Petitioners have properties which are off the plan, but the intention is to give you an idea of where the Petitioners are living so that you can cross-reference to Petition numbers.



  9630. I remind the Committee, and really say this more for the benefit of the Petitioners than the Committee, that concerns about the various types of impact have been assessed at considerable length, particularly those relating to noise, vibration, construction, lorries, settlement and heritage issues. They have been assessed in various parts of the Environmental Statement, not only the main Environmental Statement, but the first Supplementary Environmental Statement deals with Hanbury Street and the first Environmental Statement relating to AP1 deals with the revised proposals for Whitechapel Station.

  9631. As the Committee also knows, in addition to the various volumes of the Environmental Statement and the technical reports on matters such as noise and settlement, there have been available to the public for some time not only those matters, but the IPs, the information papers, and each Petitioner has received an individual Petition response document which the Committee also has.

  9632. I will deal firstly then briefly with the issues around Whitechapel Station. As you know, sir, the current proposals were revised in the first AP and described in chapter 4 of AP1. Perhaps Mr Fry can put up the illustrative drawing which the Committee has already seen of the proposed Fulbourne Street ticket hall.[3] The justification and the benefits will be explained briefly by Mr Anderson when I call him. The Committee will recall that in the Tower Hamlets evidence, Mr Whalley, the officer from Tower Hamlets who gave evidence to the Committee last week, spoke strongly in support of the Crossrail station here and of the enlargement of Whitechapel Station and said that it was fundamental to Tower Hamlets' support for Crossrail. The reference to that is the transcript for Day 38, paragraphs 9471 and 9482. Indeed Tower Hamlets' position is that they want the station, as the Committee may recall, with even greater street presence than proposed and they were arguing for the demolition of McDonald's to allow an even greater access to the station. The importance of the station is underlined by the Mayor's London Plan which targets Whitechapel as an opportunity area. These are areas in association with regeneration areas in the London Plan. It is areas targeted for the regeneration of jobs and homes, the promotion of social inclusion, increased accessibility and it is all tied to improvements in accessibility and public transport, such as the East London Line and Crossrail. The key issues which justify a station at Whitechapel are the assistance of regeneration in Whitechapel, which fits in with the Mayor's Strategy in the London Plan and the fact that the station acts as a major interchange, as the Committee knows, between a number of different rail lines, the Tube, the East London Line and Crossrail itself.


  9633. I turn then to the issues with Hanbury Street and the Hanbury Street shaft. As the Committee is also aware, Hanbury Street was originally a proposed site for the launch of a tunnel-boring machine. This was revised following the revision to the tunnelling strategy in April with a proposed change in the tunnelling strategy. The proposals at Hanbury Street have been scaled down to a much smaller intervention shaft for emergencies and for ventilation and the position with regards to the new Hanbury Street proposals, which will be the subject of an AP in due course, are set out in a revised information paper D8. As the Committee also knows, the intervention shaft is needed for access during emergencies, particularly by the fire brigade. The Committee is also familiar from the evidence given during the Greenwich Petitions on Arsenal Way that a one-kilometre spacing criterion is preferred by the fire brigade because of the difficulties they have in getting down the shaft and accessing the points of any emergency and getting out again safely. That guidance, I can remind the Committee, is Exhibit 21804-023.[4] The guidance which is currently given by the HSE the Committee can see there and it was produced some weeks ago, but the Committee can see that the reference to the distance is of the order of one kilometre where there are twin single-bore tunnels with adequate intermediate cross-passages which is what is proposed here.


  9634. The revision to the tunnelling strategy, as I have already mentioned, led to the revision of the proposals for Hanbury Street and the shaft and its impact will be much reduced over that originally intended. For example, as the Committee will have heard last week, Britannia House will no longer need to be demolished and the shaft itself will be much smaller. Can I ask Mr Fry to put up 21804-025.[5] This is a plan which I think the Committee saw last week. The left-hand side is the original Bill scheme and it shows the land-take needed for the original version of the Hanbury Street shaft. The Committee can see on the right-hand side the considerably reduced land-take, less than half of what was required originally, and Britannia House is outlined which will no longer be required to be demolished. These matters were drawn to residents' attention not simply by general publicity, but a letter was sent to the Petitioner residents on 22 May, which is Exhibit 21804, page 001, which is the first page of it, and it runs over five pages.[6] It was a letter written to the Petitioners living in the area which explains to them what the revised tunnelling strategy meant in terms of the Hanbury Street shaft and the Committee can see that it sets out the information, including the confirmation that the Pedley Street shaft and the additional tunnel will not be required, Britannia House will remain, no need for a conveyer, no need to store excavated material at Mile End Park, et cetera, but it did not mean the alignment would be affected; the running tunnels would remain where they were.



  9635. It also made it clear on the second page that the revised tunnelling strategy did not remove the need for the works at Hanbury Street, and it referred to the fact that an additional provision would be required, and then attached are a couple of plans and a diagram. The issue of where the shaft should be has been debated with Tower Hamlets, and I do not propose to go over that. As the Committee knows, the main alternative contender is Woodseer Street which is two streets away.

  9636. So far as the additional provision is concerned, it will have its own Environmental Statement in due course, although I will ask Mr Thornely-Taylor to give a brief view as to the comparative position in environmental, noise and vibration, impacts of the two locations. You will recall I said I would do that last week during the course of Tower Hamlet's Petition, but Mr Thornely-Taylor was not available last week.

  9637. Crossrail has taken the view that, even before the Environmental Statement has been provided, it is likely that the environmental impacts, in terms of noise and vibration, of the two locations will be broadly similar, and there are good engineering reasons for preferring Hanbury Street over Woodseer Street. As the Committee will be aware from Mr Berryman's evidence last week, there is a range of options for a Hanbury Street shaft. He described Options A, B and C going from a maximum underground intervention where there is much of the equipment placed underground and that involves more excavation, but there is then less equipment and shaft on top of the ground, which allows, if it is thought necessary, greater over-site development, to an option which puts more overground and has less construction impacts and a lesser construction period. That is all a matter which is open for discussion with the local community through Tower Hamlets, as we made clear last week. The options as to what will go on the shaft site precisely remain to be determined.

  9638. It is the case that we consider the impacts of the Hanbury Street shaft to have been exaggerated, for example, in terms of lorry movements and perceived impacts on the community over a lengthy construction period, and I just wanted to make it clear now, and this came out in Mr Berryman's evidence last week, that Crossrail's view is that the construction period for the Hanbury Street shaft should be, on the worst case, of the order of two years, not four or six or eight, but two, and that the two years is probably the maximum if you go for the maximum intervention and underground construction as opposed to the option which puts more of the equipment above ground. If you will recall, in terms of lorry movements, Mr Berryman last week said that he thought of the order of five lorry movements a day for that two-year period and less frequently than that, maybe one a day or less, after that. It is important to put those impacts in context.

  9639. On the issue of noise and vibration, Mr Thornely-Taylor will explain the position. It is clear that there are likely to be some impacts from noise and vibration during construction. That is unavoidable with any scheme of this sort. They will be fully assessed for the revised Hanbury Street shaft with AP3 and the ES which comes out with that. We have of course assessed the comparative position of Hanbury Street and Woodseer Street for the original Bill scheme with the greater impact and that is, as we dealt with last week, in the first Supplementary Environmental Statement, and Mr Thornely-Taylor will explain the position briefly.


1   Crossrail Environmental Statement Volume 4A, Whitechapel Station, Construction Works & Impacts (LINEWD-ES16-035). Back

2   Crossrail Ref: P87, Location of petitioners based in the Spitalfields area (TOWHLB-GEN01-001). Back

3   Crossrail Ref: P87, Whitechapel Station, Fulbourne Street Ticket Hall from Durward Street, (TOWHLB-21804-017). Back

4   Crossrail Ref: P87, Railway Safety Principles and Guidance, Part 2 Section A Extract, Emergency Intervention Point Requirements (TOWHLB-21804-023). Back

5   Crossrail Ref: P87, Hanbury Street Shaft, Worksite Comparison (TOWHLB-21804-025). Back

6   Crossrail Ref: P87, Correspondence from CLRL to The Spitalfields Centre, 22 May 2006 (TOWHLB-21804-001 to -002). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007