Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 10240 - 10259)

  10240. Mr Liddell-Grainger: Who is taking this on? Mr Elvin?

  10241. Mr Elvin: Sir, on the consultation issues, we do not accept all the criticisms that have been made and I am going to explain why at 2.30. Can I deal with a couple of limited points at this point just so the Committee knows where we are coming from. So far as consultations are concerned, there was not only one consultation round, there were a number. Could I ask Mr Fry to put up Information Paper F2 page 2, please, just to remind the Committee it is a long time since I referred to the information which I gave in opening on 17 January.[11] You can see there that in terms of consultation there was a public awareness campaign in September 2003, which is item 3a. There was a major consultation round, the first consultation round, for 12 weeks, in the latter part of 2003. There was a supplementary public awareness exercise later. There was then a second major consultation round for another 12 weeks in 2004. Finally, there was an information round which accompanied the Bill Deposit to give information about the scheme as it finally emerged at the time of the Bill Deposit and Environmental Statement.


  10242. Can I say this? The issue with regard to the old Truman's Brewery, I make no bones about it, it was insensitive given the nature of the community. But I am going to explain why—and it is not a good excuse because it was insensitive, as I accept. The problem was that in terms of obtaining proper accessibility it was the only available site at the time, and it was moved when an alternative site became available—it was moved to the Brady Centre for subsequent consultation. It was force of circumstances but I nonetheless acknowledge the lack of sensitivity involved in that. Can I also make it clear that information was given at both consultation rounds one and two that Hanbury Street would be used for tunnelling as well as ventilation and intervention? By way of illustration now—and I will deal with this more fully later—can I have put on the scanner the information panels that were displayed and which were also available in A4 format, and they were also available in Bengali.[12] This is the 2003 version and you will see in the text at the right hand side the last two paragraphs make it perfectly clear that this is to be a launch and retrieval point for tunnel boring machines used during tunnel construction. So we do not accept that information was somehow concealed about the true nature of the then Hanbury Street shaft and the purpose for it. Of course, the position changed in April of this year when the tunnelling strategy was changed and letters went out to Petitioners on 22 May, but a public statement was made in Parliament, a statement was made, I think—I cannot remember whether it by was me or somebody else—to the Committee and a new version of the Information Paper on Hanbury Street and on the tunnelling strategy was published in the last week of April and made available from that date. So in terms of the role of Hanbury Street and then in terms of the change we do not accept that there was not transparency or notice.


  10243. I am not going to deal with other matters at this stage on consultation; I will make our position clear this afternoon.

  10244. So far as the CRE is concerned and the Equality Impact Assessment, as I indicated to the Committee yesterday there has been a correspondence with Mr Trevor Phillips. This is only the first letter and there are others. Mr Trevor Phillips now knows that an initial assessment has been carried out, that another assessment is underway and if the Committee wishes to see the full range of correspondence I am quite happy to provide it. But there are later letters than this, this is the first letter from Mr Phillips that we had in correspondence.

  10245. In terms of the other issues, those are matters that have already been covered in evidence, both on Day 38 with Tower Hamlets; and why an intervention shaft is needed has already been covered by Mr Berryman. On questions such as the alignment and the need therefore for an intervention shaft at all and the Woodseer Street option, evidence has already been presented on Days 38 and 39. I do not propose to add anything else unless the Committee would like me to clarify any further matters?

  10246. Mr Lidddell-Grainger: Just one matter of clarification, Mr Elvin. Who appointed the Crossrail referee?

  10247. Mr Elvin: Appointed by the Secretary of State for Transport.

  10248. Mr Lidddell-Grainger: And paid by the Department?

  10249. Mr Elvin: It comes out of project funds.

  10250. Mr Lidddell-Grainger: So it is actually paid by Crossrail but it is honoured by the Department.

  10251. Mr Elvin: It is paid by public funds and made available to Crossrail.

  10252. Mr Lidddell-Grainger: Mr Akker, do you have anything else that you would like to add?

  10253. Mr Akker: No, sir, I think it has been fully dealt with.

  10254. Mr Lidddell-Grainger: I am very grateful. Thank you for your evidence, it was extremely well put.

  10255. Since we have no other evidence I therefore call the Committee to order and we will now re-sit at 2.30.

  After a short adjournment

  10256. Mr Liddell-Grainger: I call the Committee to order. Mr Elvin.

  10257. Mr Elvin: I have various pieces of housekeeping and I then propose to call a witness and, in part, myself, just to present some material on the consultation to assist the Committee in its considerations.

  10258. Can I first, for the purpose of the record, record that a statement has been made by the Minister, Mr Twigg, this morning to announce that changes have been made in the scheme with regard to the main Crossrail depot, and what Mr Twigg said to Parliament this morning was that the government is aware of the concerns that have been expressed by the London Borough of Havering and others in that borough about the impacts of the proposed Crossrail train depot at Romford. Cross London Rail Links have been working for many months to reduce those impacts and at the same time to identify whether there is a viable alternative depot strategy that would remove the facilities at Romford altogether. Following a fundamental review of the depot strategy and in the light of changes in the occupation and expected future use of existing depots, CLRL has concluded that it is possible for Crossrail to operate entirely from the existing rail depots at Old Oak Common in West London and Ilford in East London. As a result Crossrail would not need to continue with any of the proposed facilities at Romford or to make use of the sidings at West Drayton in the London Borough of Hillingdon. The revised depot strategy will reduce the overall environmental impacts of the Crossrail project by removing the need for the construction of new facilities in Romford. CLRL estimate that the cost of the revised strategy will be up to £80m lower than that of the Romford scheme. The revised strategy will require the acquisition of a small amount of open land at Old Oak Common to allow for improved rail access. The land lost will be replaced by an equivalent amount from an adjacent brownfield site. In order to implement the revised strategy the Bill will need to be amended; the government will promote an additional provision in due course, including a detailed Environmental Statement, which will be subject to the agreement of the Select Committee. Those affected by the additional provision will be able to petition Parliament. As part of the revised strategy it is proposed to move EWS Limited from Old Oak Common to North Pole—that is North Pole and not the North Pole! -which is to become vacant in 2007. It is also proposed to move Bombardier Transportation Limited from or within Ilford Depot. CLRL will continue to work closely with these organisations to try to minimise the impacts upon them. CLRL will in due course write to existing Petitioners affected by this announcement and undertake information rounds in the relevant areas to explain the details of the revised depot strategy and the implications for the local area.

  10259. Therefore, whether or not of course Romford now wish to appear in two weeks' time is a matter which will need to be considered.


11   Crossrail Information Paper F2 Pre-Bill Consultation Process, Consultation Activities http://billdocuments.crossrail.co.uk (LINEWD-IPF2-002). Back

12   Crossrail Information Panel: Hanbury Street Shaft Crossrail Proposals (SCN-20060614-011). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007