Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 13080 - 13099)

  13080. Elsewhere, there is some good evidence of good practice, in particular, in light rail and that is partly because it is actually easier to provide good access in a newly built, closed system and most often it is actually the legacy of existing infrastructure which I spoke about a bit earlier that causes the problems. That is kind of nicely demonstrated if you take the Sheffield Supertram, for example. That was almost a totally accessible system with the exception of the link to the mainline station. The mainline station was existing infrastructure, so when the Sheffield Supertram was built, you could not get from the Supertram stop to the mainline station if you needed secondary access. That has only now been implemented ten years, give or take, after the opening of the Supertram. That demonstrates the problems that you get when you compete against existing infrastructure. If you look at Crossrail, effectively the central part of Crossrail is a new build, so achieving access there is reasonably straightforward and cost-effective.

  13081. The DDA has certainly focused attention on accessibility and things are now improving, as I say, but one of the things is that the current appraisal system for transport projects tends to militate against good practice because projects have to jump the value-for-money hurdle first and the value of disabled access is not effectively accounted for in that value-for-money hurdle. I think it is a positive thing that Crossrail has managed to move past that hurdle and with the decision to address access issues at the four extra stations, it has effectively jumped the hurdle, if you like.

  13082. Crossrail has actually taken a proactive approach to the issue of inclusion in general. It is being integrated into the design at the appropriate stages, so straightforward layout and step-free access are being addressed now and other issues will be addressed as the design matures. Broadly, there are four types of station. Firstly, you have new build, such as Farringdon and that provides 100 per cent step-free access and will be 100 per cent accessible in other respects, except where this is impossible, as in the example of the connections to the Thameslink platforms because of the uncertainty around Thameslink 2000. Secondly, there are rebuilds, such as Ealing Broadway which provides 100 per cent step-free access. Thirdly, there are upgrades, like Southall, where step-free access is going to be provided as far as possible. Then, fourthly, there are places where only platform extensions will be done, and that is at places like Burnham and Manor Park.

  13083. The diagram which you can see on the screen shows where step-free access is currently available at the locations where Crossrail is going to fall.[12] Just to explain it, a filled green blob indicates 100 per cent step-free access at that location, so you can get to all the platforms, a half green blob indicates 50 per cent step-free access at that location, and in most cases what that means is that you can get to one side of the station, but when you come home you are a bit stuffed and you cannot get back the other side. An empty red blob means that there is no step-free access at that station to any of the platforms, so very few of the locations that you are looking at on the map, as you can see, are accessible to people with reduced mobility who actually need step-free access.


  13084. If we look at the next diagram, you can see the effect that Crossrail is going to have on the ability of people who need step-free access to get to and from these locations.[13] There are still a few locations where Crossrail does not provide step-free access, but we believe that the negative effect on people with reduced mobility will be fairly small because of the proximity of Crossrail stations where step-free access is being provided. Many of the stations where it is being provided are interchanges with other transport modes, such as the bus terminals at Ilford and Romford. Other locations provide better ticketing facilities, other better facilities, more staff assistance and that is extremely important, particularly for disabled people, but in general for people with reduced mobility. Generally these stations, because of their larger size and greater importance to the network, are better stations to use and many people prefer to use them, and you can tell that from the footfall figures that we have for those locations.


  13085. Mr Mould: Before you move on, I would like Mr Berryman just briefly to explain to the Committee, first of all, as part of the review that is mentioned in the information paper which I referred to in opening, have we looked at the case for making provision for step-free access at the remaining stations which are shown in red on the diagram in front of us?
  (Mr Berryman) Yes, we have and I think, as you explained in your opening, the criteria which we have used are the number of passengers, the difficulty and complexity of making step-free access available and the proximity to other stations where step-free access is available, and it is on those bases that the choice has been made about which stations should be treated.

  13086. So, in a nutshell, the Promoter's position is that in those cases the benefits really of upgrading to step-free access would be pretty limited?
  (Mr Berryman) Yes. If I can give you an example, Maryland Station, which would be very expensive to alter, is only 700 metres from Stratford Station, so any person who is accessing by car or cab or whatever to the station would not find it much more difficult to get to a nearby station which has full step-free access.

  13087. We ought to make it clear of course that the position you have just described relates to the stations which are shown with the red circles, but also to those, I think it is, two stations in the western section, Taplow and Langley, where there is only partial step-free access. Those are treated for those purposes as being in the same category as the red.
  (Mr Berryman) Yes, we treat these as non-accessible because frankly having access in one direction only is of limited use.

  13088. Mr Binley: Perhaps I could just ask a question in relation to that. It does seem to me that, whilst it might be easier to deal with Stratford Station than Maryland, if the journey to somebody's home is more difficult from that station, then there is an impact and I just wonder if any work has been done on that. I am not suggesting it should have been, but it is a question that I think we ought to ask.
  (Mr Berryman) No specific work has been done on that point other than a general appreciation of the direction from which people come to access the station, the bus routes that go to that station, the disposition of the main roads in the area and, as Ms Maynard said, one of the other criteria that has been considered is the incidence of other transport modes which are going to that station. For example, Romford and Ilford, which have quite powerful bus services, are themselves being provided with step-free access and that is an important consideration in selecting which stations to take forward.

  13089. Mr Mould: I think, Ms Maynard, you were making that point, as I understood you, in your commentary to this slide a minute ago.
  (Ms Maynard) Yes.

  13090. Can I turn to you before we move on and pick up a point which Mr Binley raised when I was introducing the information paper in opening. It was the point, if you recall, as to what arrangements were proposed in relation to those stations where step-free access is not available, and what the information paper says is that dignified, alternative arrangements will be employed. Can you just give an indication of what in practice that might entail?
  (Ms Maynard) Yes, at the moment the practice on the national rail network is to provide alternative accessible transport to the station that someone wants to travel from. Sorry, if they want to travel from a station which does not have step-free access, they get alternative accessible transport to the nearest accessible station from which they can then travel, and obviously it is difficult to get to 2016 and see whether there will be any more innovative solutions by then, but certainly the provision of a taxi to the nearest accessible station would be quite common.

  13091. Thank you. Please continue with your presentation.
  (Ms Maynard) I just wanted to give some examples of some of the issues that we have come across in Crossrail. Two examples of major infrastructure upgrades will give you an idea of the way that Crossrail has approached access provision. One of these is a successful example and the other is actually an unsuccessful example. If you take Tottenham Court Road, Crossrail has worked with LUL to provide a station with fully accessible ticket halls with accessible links to the Central and Northern Lines from street to platforms and with interchange between all three lines, so that was a plus point. However, if you take Paddington, in fact Mr Mould showed the interchanges at Paddington and if you were quick to spot it, you would have noticed that the step-free access from Crossrail to the Bakerloo Line is not currently proposed to be available and it is going to have to wait until modernisation of the Bakerloo Line releases space to insert a lift underground, and that is the problem. You saw that on a visit, I believe, if you were there and if you remember.
  (Mr Berryman) I did point that out to members of the Committee.

  13092. Mr Binley: I am getting to the stage when I do not remember if I was there!
  (Ms Maynard) It is very hard to look at something which does not yet exist. So that is an example of a slightly less than successful attempt at providing access, but hopefully in due course when something else happens it will trigger the provision of access. If you take building improvements, at Paddington again alteration of the LU station building has allowed a step-free link between Crossrail and the Circle and District Lines. Then if you take the platform improvements where the platforms are improved, not only will extensions be built in gauge, which was mentioned in the information paper, but tactile paving will be provided to the whole of the platform which, as you know, is very important to people with visual impairments. This is an example of the creative approach that Crossrail has taken to the issue because it is easy to put the tactile paving on the extension, but putting the tactile paving in in a way which is not disruptive on the main part of the platform, I can tell you having worked at Network Rail, is not a straightforward issue. Crossrail has found an innovative solution with hard-wearing plastic studs which are very quick and cheap to install.

  13093. Mr Mould: We have brought some samples, I think.

  13094. Mr Binley: Free samples?

  13095. Mr Mould: If it would be helpful, we can certainly just give you an indication of them. (Same handed). Perhaps, Mr Berryman, you can explain what we are looking at.
  (Mr Berryman) They are very simple to install. I understand it is an Australian invention, which always seems a contradiction in terms, I think! What you do is you cut a longitudinal saw-cut with a diamond saw in the platform and then just bash them in. They are straightforward things to fit.

  13096. Mr Binley: You could not put some of these around my golf course, could you!

  13097. Mr Mould: Ms Maynard, please continue.
  (Ms Maynard) Making a journey experience seamless for people with reduced mobility does involve working with partner organisations, such as London Underground and Network Rail. As you can see from the situation at Tottenham Court Road, that is an example of partnership working. It also requires a level of investment by them. One of the issues is that it is not always clear at this stage how much partners are going to have achieved by the time that Crossrail completes, so Crossrail has to base its plans on the existing strategies that those partner organisations have. Meanwhile, it is taking a proactive approach to partnering so that where there are solutions to be had, it can happen, as it were. This is an example. Ealing Broadway Station is going to be rebuilt and if you take a look at these two photos, you can see that it is riddled with steps.[14] If we then take a look at the artist's impression of what it will be, actually perhaps Keith could describe this.[15]


  (Mr Berryman) For those of you who are familiar with Ealing Broadway Station, this is the existing building which I believe is occupied by the BBC (indicating), the existing office block we have there, and this is the existing London Underground station (indicating), and this is the new station structure that we are proposing to build (indicating). What we are proposing to do is to have a level concourse from the street level coming right through to here (indicating) with bridges distributing passengers to various lines and lifts at each point where there is a station platform which people would need to access shown in the red structure, so the Crossrail project will be providing access not only to the Crossrail platforms here and here (indicating), but also to the London Underground District and Central Line platforms, so there will be quite a significant upgrade resulting from the Crossrail project at this location.
  (Ms Maynard) Access has been quite a long time coming at Ealing Broadway, as someone I know who lives there will tell you, but it is Crossrail which is going to make a difference there and I think that is an important point to consider. If we take a look at the difference that Crossrail is going to make in London as a whole when it opens in 2016, I wanted to take a comparison with London Underground. Going back to the point I made about working with people's strategies, London Underground has a clear strategy for 2013 which is going to result in 21 per cent of journeys beginning and ending at a step-free station, but they have not yet firmed up their figure for 2016. They have two possible directions they can go in, and that is either that 50 per cent of stations are accessible, which gives 50 per cent of journeys, or 60 per cent of stations which gives 33 per cent of journeys. I know that sounds very strange, but I think that is about sharing the same pot of money around a series of different stations and, therefore, putting different stations into the mix, as it were. On Crossrail, 93 per cent of journeys will be step-free since the four additional stations have been incorporated. This tells us two things. The first is it tells us that London underground has an extremely aging infrastructure. The second thing it tells you is Crossrail will make a difference to people with reduced mobility in London in 2016. When I started, I talked about it not being all about step free access, and I want to come back to that to finish with because that is a really important issue. It is not just about wheelchair users' difficulties and step free access, except that today it kind of is because the fundamentals of the design at this point are straightforward layout and step free access, so straightforward layout in absolute new builds. That is very important, for example, for people with learning difficulties and vision impairments, but we can only do it with new builds. Step fee access is also key at this point because it can only be designed from the outset, it can be done later, but it would be extortionately expensive. Essentially in design terms, we are at the outset, so in due course, as the design matures, Crossrail is going to need to look at things like the colour of materials and those people with visual impairments. Towards the end of the project, as the provision of information, including signage, is considered, the needs of people with sensory impairments and learning difficulties are going to become particularly paramount. There are different needs at different points in the design. Crossrail has an involvement and consultation that is going to be key throughout the project to engage the right people at the right time, to provide good advice where there are no standards or accepted good practice. Obviously where there are standards Crossrail will follow the standard, and where there is accepted good practice Crossrail can do that, but in many cases, particularly with some of the issues for people with hearing impairments and people with learning difficulties, there is very little clearly accepted good practice. We will need to look at those issues then. Crossrail will be contributing to the development of good practice as long as it is operating at the cutting edge of design for disabled people in the transport environment. Lastly, access is not just about hard things, it is also about things like good management of station infrastructure. You can have the best step free access in the world and if you then put a cleaning sign in the middle of the route, it is not very helpful. Good management is important, also training is important, effective co-ordination with other operators is important and journey planning and assistance is important. As the specification for Crossrail's operation is developed this must be borne in mind

  13098. Mr Binley: Can I thank you for your comprehensive and professional presentation. We are most grateful.

  13099. Mr Mould: If there are any questions from Petitioners, then obviously my panel will answer those, and any questions which you and your colleagues may have?


12   Crossrail Ref: P103, Step free access to platforms (LINEWD-GEN12-010). Back

13   Crossrail Ref: P103, Step free access to Crossrail stopping platform (LINEWD-GEN12-011). Back

14   Crossrail Ref: P103, An Example Ealing Broadway (LINEWD-GEN12-013). Back

15   Crossrail Ref: P103, Ealing Broadway as it will be (LINEWD-GEN12-013). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007