Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 13220 - 13239)

  13220. It sounds obvious, but is the railway at the bottom?

   (Mr Berryman) Yes. The Post Office would require us to provide a connection from this shaft, so that they can still get out into the open air without going through the ticket hall. In practice, that means that we have to build a layer underneath the existing vaults. That is quite a complex area. Above, there is the McDonald's store and the piazza outside the station, and we would need to underpin all that whilst we were doing the work, so it is rather more complicated than we initially thought. It is quite difficult doing this kind of work on a small site and constrained by the London Underground operational area. I feel bound to say that London Underground, as you would expect, are a very safety conscious organisation—as we all are. Their particular concern is the safety of passengers. That means that the way you can work in ticket office halls is naturally somewhat constrained and this makes life quite difficult for the people doing the work. Since the 30-year PPP contract has come into place, that difficulty of access has become even more difficult than it was before. The point about this lot is that it is a mass brickwork structure. I would not argue that it is not possible to do the works set out here—it certainly is possible—but I would suggest that the risks involved in that are greater than we would be happy to take on in such a sensitive location.

  13221. Shall we go to 5A, slide 12.[15]

  (Mr Berryman) This is an option which takes escalators up from the concourse level directly to the street. To achieve this, the vaults have to be removed and the gateline is positioned further forward than it was in the previous slide. These escalators are currently non-compliant with this document and we would have to get a derogation from that in order to install them. It is probably not impossible to get such a derogation—and I do not think we would be overly worried about that—but we still have this problem of what to do with these vaults and how to deal with the additional level of tunnelling required underneath. There are also significant issues involved with moving the station facilities, the booking offices and machines and so on, away from that area.

  13222. In terms of disruption, while the work was going on, how do you feel about having the new escalators going in on the west side of the ticket hall and the work going into the Post Office vaults on the east side?
  (Mr Berryman) This will make it even more difficult. As I said a moment ago, London Underground, as you would expect, have very exacting standards for passenger safety and for allowing throughput of passengers while work is going on. Complying with those standards, I think it is common ground amongst all engineers who have had to do it, is not easy and doing this kind of thing does not make it any easier.

  13223. Then option 5b, which is the one with escalators out of Network Rail.[16]

  (Mr Berryman) This is the same as option 4 but with additional escalators provided from the British Rail concourse up to the existing exit from Liverpool Street Station. This is simpler and much cheaper to do than the previous option we looked at and provides some additional circulation. We have not modelled the Network Rail concourse. There would need to be the removal of one leg of the staircase. Network Rail are not hugely enthusiastic about this because they suggest this would attract more passengers to an area of the concourse that they do not want you to use, but that is the next option. The point here is that it has all the same risks as option 4 in requiring the removal of the vaults and so on.

  13224. Then option 7A, exhibit 14.[17]

  (Mr Berryman) This uses the existing area, which is currently a sub-station, in the forecourt of Liverpool Street. I understand that this was previously part of the ticketing concourse arrangements for Broad Street Station when that existed, but it has been in use for many years as a sub-station. We think there is an opportunity here to return some of the structure but in our cost estimates we have assumed that the roof and basement slabs and much of the walls would need renewal. Clearly on the side where the escalators would go, we would need to build a new wall and a new shape of wall. All the work could be done from street level. However, it would need to be phased to follow construction of the passageway underneath, otherwise there would be no room for pedestrians to walk along the road. There is a building adjacent, which we can see indicated by the dotted line. As far as we are able to ascertain there is no physical connection between the two buildings. 100 Liverpool Street does not rely on the sub-station for support, so it would not require any underpinning. There is a canopy, I believe.

  13225. Would you put up exhibit 7, which is the street level, we can see that a bit better.[18]

  (Mr Berryman) That shows the escalators coming up from below and the structure we are talking about is roughly here. There is a canopy over the top of the entrance to 100 Liverpool Street which would need to be temporarily taken down. That should not be a particular issue and it would be reinstated obviously afterwards.

  13226. Can we talk about what we would do with the kit that is in the sub-station.
  (Mr Berryman) If we can go back to the previous slide, 14, in the area at the moment are effectively two sub-stations.[19] There is a general power station which provides power for the station and there is a traction sub-station which provides the DC power for the traction of the underground. I understand that the lives of both of these are drawing peacefully towards their close; that is to say they will need renewal in the next few years. We would propose to put the traction sub-station in what is currently an equipment room belonging to London Underground which is in a disused tunnel. We are intending, in any event, irrespective of this, to provide a new sub-station to provide power for the station. That would be in the Bloomfield Street shaft which, from memory, you saw on the visit.


  13227. Is the equipment room going anyway?
  (Mr Berryman) That goes anyway. The shape of the equipment room is there.

  13228. I think it is called CER.
  (Mr Berryman) It is, indeed: the communications and equipment room. It will be necessary to relocate the plant and equipment that is in that room in any event. I spoke about the risks in option 4. Here there are some opportunities. We may be able to use some of the existing structure; we should be able to take advantage of the fact that the equipment needs renewal. That tips the balance really quite strongly in favour of this option.

  13229. To summarise all that, Mr Berryman, what is your engineering advice to the Secretary of State as to the preferred options?
  (Mr Berryman) My advice is that, if we have to build an additional substantially increased ticket hall, this is a better option than going for option 4. As Mr Anderson will give evidence shortly, I still require some convincing that additional capacity is needed in any event, but, if it is, this would be a much better option than option 4. The other advantage of this of course—and to be fair this applies to option 4 as well—is that this can be done at any time. If at a later period, say in 20 or 30 years time, it is realised that the traffic numbers are getting out of control, this can be added at that stage without undue difficulty. It does not interrupt the flow of passengers into the Crossrail station or anything of that sort.

  13230. Finally, may I point out that this is not a cost-driven decision but we have done some cost work. I do not think we need to go into it in any detail at all, but, from the engineering point of view, can you explain your assessment of the relationship between risk and cost on these options.
  (Mr Berryman) I would like to make a point generally about design, because it does not just apply to the risk and cost, it applies to the interface between the physical design and the modelling of what is going on. You will notice that some of the drawings which have been used for modelling are marginally and slightly different from the layout drawings you have here. That is because the modelling process is iterative and we are at one stage of the iteration. The result of the modelling would probably be to change marginally some of these layouts. The same thing applies with the costs and risks. At the moment, we have estimated the costs—that is the concrete and the digging of piles and so on—and we have added flat percentages to all of the options to arrive at cost figures. Clearly that is not good practice. Normally we would do what is called a quantified risk assessment, where we make a full assessment of the additional costs that might arise and what the chances are of those arising. We have not been able to do that in the time. Indeed, we would not want to do it just yet because we would need to do a bit more design work before we could do that sensibly. By inspection or by experience, one knows that some things will turn out to be inherently more risky than others. Putting in an additional level, a basement, underneath a set of Victorian brick walls, immediately falls into that category.

  13231. Could I point out that 002 is a cost summary: across the top are the options and right at the bottom are the figures.[20] At line 5, the contingency, despite what you have just said, you have applied the same contingency to each option.

  (Mr Berryman) We have applied a percentage, yes.

  13232. It is right, is it not, that if one did option 3B and option 7 together, cumulatively—so you did increase the gateline—and, whether now or in the future, built option 7A, the £30 million would go up, would it not?
  (Mr Berryman) Indeed, it would. I would like to draw attention to two points on this chart. First of all, the raw construction costs for doing option 4, the things which tip the balance are £8 million for re-provision of the sub-stations which are in the existing space. As I said a moment ago, there is an opportunity there that may not arise and those costs may go away. If you did that, the cots for this one would go down significantly because the contingency and risk is a percentage which is added to everything. Reducing the figure by £8 million has a much bigger effect on this one and perhaps brings it down by closer to £10 million.

  13233. Ms Lieven: Thank you very much, Mr Berryman.

  Cross-examined by Mr Laurence

  13234. Mr Laurence: Good morning, Mr Berryman. I do not believe we have met each other, although you are obviously very well familiar to everybody else in this room. I have a few questions for you, because what is happening today might not necessarily have been foreseen six months ago, at a time when the evidence that was being put forward on behalf of the Promoter suggested that there was nothing that needed to be done. We need to go through a little carefully to see how we have got to a position where we are now having round two of what is turning into an epic exchange of views between the respective parties. With respect to Mr Lieven, it is not only British Land for whom I appear, as you will appreciate, but also the Corporation of London. Are you an engineer by training, Mr Berryman?
  (Mr Berryman) I am.

  13235. You are here to tell us, as you have just done, that about the options for enhancing ticket hall capacity at Liverpool Street as a result of Crossrail.
  (Mr Berryman) That is correct.

  13236. Mr Anderson's function will be to tell the Committee about predicted passenger flows and matters related to that.
  (Mr Berryman) That is correct.

  13237. Yours is to tell the Committee which option caters best for those predicted passenger flows, is it not?
  (Mr Berryman) That is part of my function. It is also to inform the Secretary of State which is the optimum, in terms of risk and general impact, on the rest of the scheme.

  13238. I accept that. With that qualification, this has led you to explain why option 3B is in your view sufficient, on one view of those flows, whereas if another view were to be taken, a view the Committee might take, a more extensive option is going to be needed.
  (Mr Berryman) If the Committee took that view, that would be the case. Mr Anderson, of course, will be giving evidence on that point shortly.

  13239. You recognise, do you not, that the Committee needs to make its mind up about these matters now in case anything needs to be done which requires an amendment to the Bill.
  (Mr Berryman) Yes, that is correct.


15   Crossrail Ref: P104, Liverpool Street Station-Option 5A-Test 2, Ticket Hall Level-Additional Escalators (24 Gate lines) (LONDLB-20504A-012). Back

16   Crossrail Ref: P104, Liverpool Street Station-Option 5B-National Rail Concourse-Photomontage of Additional 2 Escalators added to Existing 2-way bank (LONDLB-20504A-013). Back

17   Crossrail Ref: P104, Liverpool Street Station-Option 7A-Test 2, Substation Ticket Hall Options-Western Escalators (24 Gate lines) Ticket Hall Level (LONDLB-20504A-014). Back

18   Crossrail Ref P104, Liverpool Street Station-Option 7A Substation Ticket Hall Options-Western Escalators Street Level Plan (LONDLB-20504A-007). Back

19   Crossrail Ref: P104, Liverpool Street Station-Option 7A-Test 2, Substation Ticket Hall Options-Western Escalators (24 Gate lines) Ticket Hall Level (LONDLB-20504A-014). Back

20   Crossrail Ref: P104, Liverpool Street Station: Cost Summary Comparison of Ticket Hall options (LONDLB-20504A-002). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007