Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 13560 - 13579)

  13560. In terms of Mr Berryman's view, which I think was his view, the taking of a flat figure for contingencies straight across all the different options being perhaps questionable, what do you say about that?
  (Mr Chapman) I agree. For instance, option 3B is just basically realigning a gateline and allowing a £1.6 million contingency for just optimising a gateline, that is more than the cost of actually doing the work almost. A gate costs roughly £50,000, so 25 gates cost just over £1 million, so in terms of the physical work on site, there is almost a 100 per cent allowance for the physical work allowed, so I would agree that option 3B you would expect to be a lot less because the work is much simpler. All of the other options, options 4C, 5A, 5B and 7A, all have complexities and issues which have not yet been fully explored. Option 7A also involves capping over a shaft. There is a shaft in the middle of the EdF substation which I believe is not capped yet. Mott MacDonald's report talks about having to fill in that shaft and again, if you want, I can show you the bit of the Mott MacDonald report for 7A which shows the shaft which needs to be filled.

  13561. Just for the record, what are you putting up again?[55]

  (Mr Chapman) This is an extract from Mott MacDonald's report which shows the works that Mott MacDonald have allowed for under option 7A. Here is a shaft which also needs to be filled beneath the EdF ticket hall, so, to my mind, the risk money that should be allowed for both options should be at least comparable, and I will come on to some of the issues in 7A.

  13562. We will come on to 7A in a minute. Right, 5A and 5B?
  (Mr Chapman) I think as time is short and as 5A and 5B have not been the subject of controversy, there is probably no point in raising any issues on them.

  13563. Let us move on to 7.
  (Mr Chapman) Could I have my exhibit 8 please which is page 9 in the party pack.[56] This shows the works and again it is identical to the image that Mr Berryman showed you this morning. It is the exact same figure which has been scanned by both of us. We spoke about what this zone actually is. It is an EdF power transformer room which is under the forecourt of UBS's offices at number 100 Liverpool Street. The last time I was before you I explained it was the former ticket hall for Broad Street Station and I have discovered that it actually opened on 10 October 1912, just after the extension of the railway line to Liverpool Street in July 1912, so it was four months or five months later opening. It was remarked at the time that it was the first ticket hall in London to have underground escalators. Escalators had been used in the previous year at Earl's Court, but this was the first Underground station to actually have tunnels with escalators in. In fact I believe the Broadgate Estate, which is part of British Land, have been approached by London Underground because London Underground wanted to use those escalator tunnels and the ticket hall as part of their `Cooling the Tube' proposals. London Underground are considering using similar space to flush air-conditioning water or air down to the Central Line platform tunnels at the moment. If I can move to my exhibit 10, we did a survey about a year ago within the old ticket hall, within the current EdF power transformer zone.[57] This is used for providing traction power to the Metropolitan Line and this is actually where the electrical power for the trains comes from as well as where the power for Liverpool Street Station comes from. This just gives you an image and it is some photos actually of inside the ticket hall. I have a report which has a lot more information in, but this shows you the magnitude of the equipment and the headroom available within the space. I have been interested in costs for option 7A because I am a little bit concerned that they are an underestimate of the work that might be required. If we can go to the Promoter's sheet 2 please, it gives cost estimates.[58] The second line of figures down is probably the one that I have concerned myself with. It is the construction costs for the various options. I was concerned that the cost for option 7A was low because it shows about an £11.6 million construction cost vis-a"-vis a £12.4 million construction cost for option 4C when the sort of work being carried out in both areas is sort of similar. They are being used for a disused space or a space that exists with structure alterations, but the 7A area is about 450 square metres of space compared to about 220 square metres of space for the space that has been changed on option 4C, so I was surprised that the cost of doing the work was less for doing more than twice the area. I asked the Promoter for the breakdown of the figures, but I was told that they were unable to provide the figures because they are commercially confidential, so I have not been able to validate the Promoter's figures. I did my own calculations very roughly and they do not stand up to very good scrutiny, but they just give a relative idea of the costs between the different options. I calculated that it is about £6.5 million extra on the £30 million for option 7A. I am not qualified to give cost advice, so British Land procured Cyril Sweet, a firm of quantity surveyors, also to carry out an assessment of the various options. Again they are also without the Promoter's cost breakdown information because that has not been available to us, but they have made an estimate and they have confirmed that my estimate of about £36 million for option 7A was correct, but they actually calculated less money for the other options, so the relative difference becomes bigger. They calculated a difference for 7A, and that is 7A alone, not plus 3B, so this 7A cost is 7A alone because sometimes 7A, we have been told, also includes 3B, so obviously you have to add the two figures if you are going to do both bits of work, so treating 7A alone, and ignoring the 3B part, Cyril Sweet's figures gave a difference in cost of £21.5 million between 7A and option 4C, instead of £10.8 million, as the Promoter has been suggesting.




  13564. What about Mr Berryman's point that the figure of £8 million shown in the right-hand column there against the footnote might involve a saving if the substation were to be relocated by LUL as part of their renewal works?
  (Mr Chapman) That £8 million, again as yet I have seen no evidence from anybody or even a piece of paper showing that the substation is substandard. I know Mr Berryman well and I trust his words if he tells me that is required, but as yet I have seen no evidence or even a piece of paper from anybody saying that that information has expired. The £8 million to replace it, again I do not know fully what length of the Metropolitan Line that covers, so I do not know whether the £8 million is right, too much or too little. Cyril Sweet's estimate, and again it is only an estimate, they allowed £10 million for the same amount of work, but, without knowing what the electrical equipment is, who has to pay to move it and where it goes to, it is very difficult to be more exact and to know whether it is the right figure or not.

  13565. Mr Chapman, the Committee is not going to have evidence from a chartered surveyor in relation to the amount to be paid by way of compensation if option 7 were to be taken, but have you considered whether there is any doubt whether some land of British Land would have to be taken if option 7 were to be pursued?
  (Mr Chapman) If I go back to my exhibit 1, and this is very similar to the figures I showed you last January, if you can cast your minds back all those months ago, the light blue line is the actual British Land property boundary.[59] The actual canopy as proposed by Crossrail, or it is not a canopy at the moment, but the entrance escalators are in the pavement here on British Land's land and in an area that is not currently used for LUL facilities, so there will be a purchase of land. Also I believe there are concerns about compensation for UBS and UBS's access which the Promoter acknowledges would be very severely affected by this, as will the operation of their building because their front door is here and I think it is acknowledged by all parties that this area here, the lid would have to be broken out, so there would be a major worksite right up against it, partially underneath their building, although I agree with Mr Berryman that it is unlikely that the building actually bears on the ticket hall, so I doubt if there is an issue with a need to underpin the building, but that would need to be discovered later on. The main issue is that UBS would have a very, very severely degraded entrance and other facilities at the front of their building for quite a considerable period of time while the work was being carried out. I do not know what the £1.3 million is meant to cover, whether it is meant to cover the purchase of the land from British Land or it covers the compensation to UBS. I know that British Land are also very concerned that the works might prompt UBS to reconsider whether this is the right building for them and things like that, so there are issues that I am not in a position to give evidence on.


  13566. Mr Chapman, before you conclude your evidence, is there anything else about option 7 that you want to say to the Committee?
  (Mr Chapman) There are two further things to consider. Firstly, if we go back to my exhibit 8 please, this space here is currently occupied by a large amount of electrical equipment.[60] I am not an electrical engineer and I get very confused with electrical engineering, so my wife will not let me do any work at home to do with it, but there is a lot of equipment here which needs to be decanted from this space into this space. This space is currently occupied as a communication equipment room which will be moved as part of Crossrail. I have seen no reconciliation between the equipment which needs to be moved and the space here. Mr Berryman mentioned that some of the equipment, the equipment to power the station, would be moved to a shaft just off Blomfield Street, but I do not know if there is enough space here to put the equipment and I have seen no evidence that it has been considered in any detail whatsoever yet.


  13567. Did you have a second point you wanted to make about 7?
  (Mr Chapman) Yes. At the moment the Promoter is showing no canopy. They have about a 1.2 metre high fence around the escalators. I do not know if that is still the case of what they are promoting. From a safety point of view in terms of actually people throwing things over the side of the fence or just accidentally dropping things over the side of the fence on to the escalators, and especially to do with the weather, I am very surprised they are not showing a canopy. London Underground's standards require a canopy for stairs, so if you go down stairs, London Underground's standards require that you have to have a canopy. They do not require it for escalators, but I think that is probably an oversight in the standards because I can see that the risks of slipping and whatever else are probably a lot more serious with an escalator than they would be with stairs, but that is quite a small issue and one that I am sure could be resolved with time, but it does make the point that at the moment 7A does not allow for the entrance canopy which I think would be required.

  13568. Before you come to your conclusions, can I just ask you about two other matters. So far as 4C is concerned, what degree of confidence could the Committee have that 4C is feasible, buildable and could probably be made the subject of an additional provision with a decision being taken in a relatively few weeks from now?
  (Mr Chapman) I agree with Mr Berryman that a lot of work would need to be done on all of these options to firm up the costs, but it appears to me, and again I have not seen the cost allowance, but the cost allowance appears to us to be generous, from a quantum point of view because we have not seen a breakdown of the figures. Mott MacDonald are an excellent firm of consulting engineers and I assume they have done the engineering properly, and Corduroy are a respectable firm of quantity surveyors and I am sure they have measured it correctly. Then there is a 28 per cent figure on the total that is allowed or roughly one third of the amount of money allowed as risk money, so I would be surprised if there was not enough money to do the work given the calibre of the people doing the work for the Promoter. A 28 per cent allowance is what is normally allowed by the Promoter for this level of design complexity, and the aim is that as certainty increases as the design process continues, that 28 per cent figure reduces, but it is an allowance at this stage for the level of uncertainty and I believe it is what Crossrail are using across the board for this level of uncertainty.

  13569. What about option 7?
  (Mr Chapman) Again I have to be careful with what I say because I have not seen a breakdown of the figures, but option 7, in my opinion, is largely as complex as 4C. There is also an old shaft from a 1913 ticket hall to be filled in and this exhibit shows the two escalator tunnels coming up the side which again Mott MacDonald have shown as partially filled in, although that might not happen with the Cooling the Tube project and they may need to use those to provide fresh air for Central Line commuters. Again it seems to me that 7A is less well formed at this stage than option 4C, but I think that is to be expected because 7A has only been considered since 8 May, whereas 4C has been worked on since January when we last met.

  13570. Mr Chapman, what concluding remarks do you offer to the Committee?
  (Mr Chapman) In a way, we are in a very different situation from that which we were last January. Last January there was a dispute over what was needed to be done and there was no real option on the table of what would be done if something did need to be done. We are now in a different situation and there is agreement that something needs to be done and there are a number of options to achieve it. There are options 3B, 4C and 7A which are being promoted by various parties. All are feasible from an engineering point of view, all have been costed on a more or less similar basis by the Promoter, and sheet 2 gives a comparison of the costs. There are benefits and disbenefits with each and to some extent I think it depends on what criteria are going to be used for choosing the solution. As a taxpayer, I favour something that is reasonably cheap as long as it works. I do not favour something that is cheap that does not work. Mr Spencer, whom I have a lot of respect for, has shown me that option 3B has severe flaws, so, to me, paying to do something that does not work is a false economy. Option 4C is the cheapest one which, I think everybody agrees, does work and 7A has some additional benefits at additional cost, so those are the three options in consideration. Options 5A and 5B also work, I think, but they do not necessarily have people who are pushing them, but all five options, to my mind, work and have been costed on a similar basis.

  13571. Mr Laurence: Thank you, Mr Chapman.

  Cross-examined by Ms Lieven

  13572. Ms Lieven: Sir, I am going to try and keep this as brief as I possibly can. Mr Chapman, option 3, and can we put up exhibit 9 please, you raised a point about the excess fare window clashing with queues going through the gates.[61] The obvious solution to that is to move the manual gate to the other side and then you do not have a problem with the queue coming up against the excess fare window. That is the kind of thing that is done at detailed design. You yourself have referred to an iterative design process.

  (Mr Chapman) Yes. I believe the Promoter has talked about having two gates in there because having a barrage of gates here at this side with an excess fare window, you need a gate here, which I agree with, but there is also concern that people coming out are having to cross over the flow, so I believe that probably by putting two gates in the line, one here as well at the westernmost end, would allow disabled access and children to cross over the flows in. I think the 3B gateline has been more optimised than the 4C gateline which has been presented.

  13573. Can we move on to engineering and 4C and 7. You sought to compare the work that would be needed on 4C with the work on 7 in terms of capping the shaft. Now, if we can put up our exhibit 5 rapidly followed by our exhibit 8, 5 is the cross-section of the post office vaults and 8 is what we need to do.[62] The crucial point here is that we are not simply capping the shaft. That is what we thought we were going to be doing in January, but in fact we have to insert a new transfer level in there, do we not?

  (Mr Chapman) Yes, and that has been fully allowed for by Mott MacDonald and fully costed by Corduroy.

  13574. But in comparison with option 7 where you referred to the shafts of the old escalators, all that has to be done to those option 7 shafts is literally to put a concrete cap on them with a manhole cover to let somebody down if necessary. There is no transfer level being put in there, is there, for option 7?
  (Mr Chapman) Mott MacDonald's drawings show that they are to be filled, but if you are saying something different now, I will take your word for it.

  13575. It is just that there is nothing comparable to the transfer level that we need to put in with option 4, is there?
  (Mr Chapman) That option is very simple, but what you are not showing is the fact that at the surface here, that is actually roadway. You can break a hole here and this work is being done basically to ground level, so putting a cantilever of four metres in here which Mott MacDonald have said is very feasible, and I agree with them.

  13576. I am going to work on the basis that the Committee has the point and I will move straight on. As far as option 7 is concerned, if we can put up our exhibit 7 please, this shows option 7 at street level.[63] UBS's building is here, the one of which British Land own the freehold and UBS are the tenants.

  (Mr Chapman) Yes.

  13577. There are two concerns of UBS. Construction phase—we have not got to the stage of working out how the construction phase access would be provided, but I do not know if you are familiar with what we are doing at Tottenham Court Road with Centrepoint where we are working on three sides of a building, I think, but it is perfectly possible to provide access to that building throughout the work period, is it not? It is a matter for detailed design.
  (Mr Chapman) I know the letter has not reached Mr Berryman yet, but UBS is a bank, I believe, with 2,000 traders and I know they are very, very concerned about security, but that is a matter that would be addressed later.

  13578. Mr Chapman, just try and answer the question to speed things along. The fact is that access to that building could be provided throughout the construction works, yes? It is a perfectly standard thing to do on that type of site.
  (Mr Chapman) Access to the front door and the issue that I mentioned earlier on, access is one of many, many issues and there is the security and there is fuelling of the building. They have got back-up generators which I believe are fuelled from this side of the building and there need to be large petrol tankers which come here which might not be that near the construction site. There are a number of issues which need to be addressed, but I agree with you, that it is possible to do it, but there is a lot of disruption to people in the building.

  13579. As far as once Crossrail opens is concerned, if option 7 is built and there is an access here, then for UBS staff who use public transport, they will have absolutely brilliant access to Crossrail, will they not?
  (Mr Chapman) Everyone will have absolutely brilliant access in the area. That is why Crossrail is being built.


55   Committee Ref: A152, Crossrail at Liverpool Street Station-Liverpool Street Ticket Hall Option 7A using existing Sub-station (SCN-20060629-014). Back

56   Committee Ref: A152, Crossrail at Liverpool Street Station-Option 7A Mott MacDonald/CLRL (LONLB-20505-009). Back

57   Committee Ref: A152, Crossrail at Liverpool Street Station-EdF Equipment Room (LONLB-20505-011). Back

58   Crossrail Ref: P104, Liverpool Street Station: Cost Summary Comparison of Ticket Hall options (LONDLB-20504A-002). Back

59   Committee Ref: A152, Crossrail at Liverpool Street Station-Original Options 1 and 6 (LONLB-20505-002). Back

60   Committee Ref: A152, Crossrail at Liverpool Street Station-Option 7A Mott MacDonald/CLRL (LONLB-20505-009). Back

61   Crossrail Ref: P104, Liverpool Street Station-Option 3B-Test 4, LUL MIP Addition-(21 Gate lines)-Ticket Hall Level (LONDLB-20504A-009). Back

62   Crossrail Ref: P104, Liverpool Street Station: Ticket Hall B Post Office Vaults-Existing Condition Section AA through vaults (LONDLB-20504A-005); and Ticket Hall B Post Office Vaults-Proposed Extension of Ticket Hall Concourse Section AA through vaults (LONDLB-20504A-008). Back

63   Crossrail Ref P104, Liverpool Street Station-Option 7A Substation Ticket Hall Options-Western Escalators Street Level Plan (LONDLB-20504A-007). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007