Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 13620 - 13639)

  13620. What I found particularly useful was Mr Chapman's exhibit 05 where he overlaid the proposal 4C on the existing structures. I found that quite helpful in identifying what was possible as a result of capping those railway vaults. The pillar remains there and it shows three additional gates. There is a little bit of space left but it would be much more than one beyond that.
  (Mr Spencer) I do not think we disagree.

  13621. I am trying to focus on what the benefits are of 4C as against 3B and it is really in that corner where you get some extra gates. If there is an improved 4C, it is possible there is also an improved 3B.
  (Mr Spencer) I am not disagreeing. I am not an engineer and I am certain that there are better schemes that could come forward. I suppose I should say something on option 7. I am not speaking entirely to my brief because you did not ask me to say anything about option 7. It obviously has appeared very late in the day. There is a substantial extent of agreement between the Promoter and the Petitioner with regard to large aspects of the work that has been done. We did get very close to having a substantial agreed statement to present to you today but unfortunately time did not allow that. I built up a box file yesterday of the information that was sent to me regarding this case. A lot of that information relates to option 7. It has not been subjected to any scrutiny by the Petitioners in terms of their demand forecasting and the key assumptions that were built into the Legion model that you have seen today. We have been party to that but please be aware that that is not a jointly conducted piece of work. I would have severe reservations about point M as it has become known with the extent of conflict at that location with passengers trying to get to and from the Central Line as well as the enormous flows that you may generate from the Metropolitan Line, trying to get to street by what is a superb route, as well as all the passengers coming to and from Crossrail. That creates a severe conflict of location and, as we have recognised, the proposal currently as far as the SOR is concerned is only to remove very small parts of it. As far as the facility itself is concerned, I would see almost that the gateline requirements are reversed. There should be 21 gates in option 7 and 12 in the rest of the station in terms of what people want to do. The vast majority of people want to be at street and this scheme does give them that opportunity to get to street very quickly and easily. That is the vast majority of people who come to ticket hall B. They are not catching trains. Thirdly, there is obviously a severe risk with option 7. If it were to be shown that queues will develop back into the Crossrail corridor itself with the additional gates, there are no effective run-offs between those gates and that corridor. As soon as you have any congestion in that corridor, it will prevent people getting to and from Crossrail, which is the whole purpose of it being there in the first place, particularly for passengers going to Crossrail from the National Rail concourse.

  13622. Chairman: Could you give us a note of your fears over the conflict situation that may arise in relation to 7.
  (Mr Spencer) Absolutely.

  13623. Ms Lieven: I am not intending to cross-examine. On that point you made, sir, there are points on the conflict point and where the development potential is and so on which relates back to the evidence. Perhaps we can respond to Mr Spencer's note?

  13624. Chairman: We would take note of his fears and we would welcome your responses.

  13625. Ms Lieven: I will deal with it in that way.

  The witness withdrew

  13626. In response to some of the questions Mr Laurence has put today, it is worth thinking about why we are here today. Mr Laurence referred on a number of occasions to the letter that you, sir, wrote to us and the petitioners. I am going to assume that the Committee's concern is to ensure that there is adequate provision for passengers at Liverpool Street now and in the foreseeable future rather than that we are constrained to take a very legalistic approach to your letter and we are only looking within ticket hall B physically. Assuming that that is what the Committee is concerned about, the correct starting point is what is the number as a base.

  13627. We say that 42,000 is already a high figure. It is 40 per cent above the observed figure in 2001. On our exhibit three you can see that if you take 42,000 and add the 35 per cent we have planned for a total of 89 per cent above the existing use of Liverpool Street. We say that is on anybody's analysis a high case.

  13628. Taking another 15 per cent becomes unrealistic. That is 117 per cent above observed and we say it is most unlikely that you would manage to squeeze that many people on the trains in the peak three hour level. I do not know how often the Committee travels on the Central Line in peak hours. I do every day and the idea, even taking the Crossrail capacity, of anything like that increase on existing LUL stock seems pretty unrealistic to me.

  13629. I turn then to the options. Option 3, and I cannot stress this too much, achieves acceptable performance at 2016 and at 35 per cent when tested against Pedroute and Legion. We accept, and Mr Berryman accepted it straight off—we could have saved a lot of time this morning—that in terms of the static gate calculation in the standards it does not meet the standards, but that is just one part of the design process. I would simply rely on what Mr Chapman said about designing the static point of view and then optimising the provision, and that is exactly what we have done. As Mr Berryman said, what is the point of all these very expensive models, except to keep me entertained, if it is not that you do your static calculations and then you test against the computer models? If you just did the calculations you could forget the whole modelling exercise. A good example of that, with great respect to Sir Peter, is the point he made a few minutes ago. You could get more gates in. If that is what you want to do there are ways of optimising the layout at more detailed stages which overcome some of the static problems. These things can all be worked on over the period.

  13630. As far as sticking to the statics as they are at the moment and the gatelines are concerned, we have every confidence, after very expensive discussions with LUL about the layout of this station, that we can achieve the appropriate concessions where we need them.

  13631. Following on option 3, Mr Laurence, I think intending to be dismissive, says I call it "cheap and cheerful". Actually, sir, cheap and cheerful can be a good thing if it works. That is the question. One great advantage of option 3 is that it minimises the disruption to existing passengers, those very passengers that the City and British Land are so concerned about. It minimises the impact on 42,000 people travelling through here at the design year. It has got to be a very good thing from that point of view.

  13632. On option 4C, again I am very happy to rely on Mr Chapman's evidence. He said it is a complex piece of engineering and he went on to say, yes, there are other more complex ones, and we accept that on Crossrail, there are some horrendous bits of engineering going on on Crossrail, but, as Mr Berryman said, that is where we have no choice. Mr Chapman then said it needs to be done very carefully, which is exactly what Mr Berryman was emphasising. Mr Chapman also said it is not unprecedented. No, Mr Berryman has not suggested that it is unprecedented, but it is complex and it is quite unnecessary, and in those circumstances it cannot be recommended. Because it is complex that impacts on cost. The important point about the cost figures is that the same risk or contingency or optimism bias figure has been applied to each. In my submission, on the evidence you have heard today there is no doubt that option 4 is the most complex in engineering terms and, therefore, on any contingency or optimism bias you apply a higher percentage than you would to, say, option 3 which has really got no risk to it whatsoever, or option 7 which has got nothing more than minimal risk.

  13633. The other point about option 4C is that it is very disruptive in the ticket hall just at this point where British Land are so concerned about 42,000 people because they are all having to get round what will be a major engineering site. It is not impossible, not unprecedented, but highly undesirable.

  13634. Then we come to option 7. It is completely offline. It can be done obviously if it is done at the same time as the rest of Crossrail with no interface with existing passengers, but one of its great benefits is if it is done later then, again, it can be done behind a hoarding and it has absolutely no impact on existing passengers whatsoever. It is important to note that British Land and Mr Chapman have not know said that it impacts on the developability of the site next door at the 100 Liverpool Street site. It has minimal engineering risk because it is in an existing structure and it is not comparable, for the reasons I went through briefly in cross-examination, with the work that has to be done on the post office vaults because of the issues of both underpinning and putting in a transfer level on the post office vaults.

  13635. The Committee has to ask itself why we moved to option 7 when we had been discussing, quite rightly—British Land was entirely right about this—options within the ticket hall and post office vaults. The answer to that is precisely because unexpectedly the post office vaults started throwing up these really significant problems and that is why we have moved to looking at the sub-station in more detail and why we see it as a better option.

  13636. Can I say something very briefly on cost, because it is clear from Mr Laurence's questions that he is going to make a lot of this. This is a very unusual situation and I hope the Committee will notice that. This is the first time on Crossrail before the Committee that we have said that we should go for a more expensive option and the Petitioner has said go for a cheaper option. That is not because we want revenge on British Land or to be horrible to them or deliberately mess them around. That is because the advice from our engineers, and Mr Berryman in particular, is that the risks attached to option 4 mean that it is a less desirable option in engineering terms, and the advice from Mr Anderson's team is that if you have got to choose between 4 and 7 then 7 has major benefits in passenger terms which 4 does not have. It would be absolutely bizarre for the Secretary of State through this team to be suggesting to you that we want to go for a more expensive option when again and again we have said to this Committee the Secretary of State is deeply concerned about pushing down the costs of Crossrail generally. This is not an exception to that, it is that we have taken the advice of our experts and reached the view that if it has got to be 4 or 7 then 7 is much the preferable option.

  13637. I do submit to the Committee, with respect, that the Committee should be extremely wary of overriding Mr Berryman's expert engineering judgment and seeking to force the Secretary of State to undertake an option that he is being advised by his own experts is not a sensible engineering thing to do. That is somewhere where I would suggest the Committee tread very, very warily.

  13638. Finally, can I just emphasise, because there is a danger here that we lose sight in the battle between 4 and 7, of the Secretary of State's core point, which is that option 3B is wholly acceptable; not just now and in base year 2016 but in 60 years' time. I would pick up a point that you made, sir, and urge that Members of the Committee who were not here today but who are in the deliberation session do see the CD or DVD of the Legion runs because they do show so graphically that option 3 is absolutely fine. I do not want the Committee to get locked into this "is it 4 or is it 7?" when actually the answer is 3.

  13639. Thank you very much, sir. As always, I have done it in a mad rush but I hope I have covered the main points.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007