Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 14860 - 14879)

  14860. Maybe I did not make the point clear enough, Mr Smith. The point I was asking you about was that those very issues, which we quite accept are terribly important, will be considered by Network Rail and then by the ORR in determination of the access option.

   (Mr Smith) I am glad to hear that.

  14861. Well, you are the expert, Mr Smith, not me, but those are my instructions. Does that contradict your understanding?

   (Mr Smith) I would just repeat myself, that we have not actually timetabled an access option in this industry before. The process for doing that has not yet been agreed, but if the instructions you have are that Network Rail will do this and the ORR will review it and take a decision on the access option even if it runs contrary to the interests of the Promoter, we will watch that with interest.

  14862. Then as far as timetabling is concerned, I want to ask you a couple of questions. The Timetable Working Group, of which Mr Watson was the independent Chair and he gave evidence last week, EWS were on that Working Group, were they not?

   (Mr Smith) We attended that Working Group, yes.

  14863. Can we have up a copy of the Timetable Working Group Report, which is P106. Do you have a copy of that, Mr Smith?

   (Mr Smith) I do not think I do, not within the myriad papers on my desk.

  14864. If we could turn to page 14 of it, first of all, as far as freight growth is concerned, and I am sure you are far more familiar with this document than I am, so hopefully I will not have to read out great chunks of it, but it is correct, is it not, that the Timetable Working Group did take into account forecasts for freight growth up to 2015?[53]

  (Mr Smith) They were advised of those figures, yes.

  14865. And they took them into account in their timetabling work and conclusions, did they not?

   (Mr Smith) The issue with the freight growth is that the only thing the Timetable Working Group have been able to prove is that the timetable that exists in 2004 operates with Crossrail services. They may have had the freight forecasts for 2015, but, as I said earlier on, they did not demonstrate and were not able to come to the conclusion that the 2015 timetable would work either on the Great Western or on the Great Eastern.

  14866. Can we just focus on the question please, Mr Smith, and look at the top paragraph. What that says, and I am not asking you about the conclusion, I am just asking you about what they took into account, the second line of that says, "The initial stage of the freight route utilisation strategy work has been to take forecasts from rail freight users", presumably including yourselves, "and potential users together with the rail freight operators and to put these together to create a single forecast for different route sections of the network", so those forecasts were taken into account, were they not?

   (Mr Smith) Those forecasts were advised to the Industry Working Group.

  14867. That was the appendix and then, as far as the scope for growth is concerned, if we go back a few pages into the body of the report itself at page 8 of the exhibit.[54] We can see there in the small paragraph above "Further work", that so far as the Great Western is concerned, the conclusion of the Freight Working Group was that, "On the Great Western the view of the Group is that the capacity enhancement provided as part of the Crossrail scheme is, with some minor tweaking, adequate to accommodate predicted freight growth".

  (Mr Smith) That was without any testing of the engineering access or freight ban.

  14868. Well, that brings us on, I think, to the last point on capacity which is the freight ban. Perhaps I can ask the Committee to look at Network Rail's exhibits, page 47.[55] This is the addendum to the access option policy paper. I assume you have seen this before.

  (Mr Smith) We have not seen this before. The first time we saw that was this morning when we were handed a copy of the Network Rail exhibits.

  14869. What this says, in essence, is that there is no longer intended to be any freight ban by reason of Crossrail. Yes?

   (Mr Smith) That is what it says.

  14870. There is no equivocation about that, is there?

   (Mr Smith) Correct.

  14871. Mr George: Is that a commitment?

  14872. Ms Lieven: Yes, that is what it says, that the document is a commitment. Access option—your EWS23, which is page 73 of your exhibits, this is where you have set out a number of points about the access option, most of which, I think, have already been dealt with and I can come back to them in closing, but there is one point I wanted to ask you about under "Duration".[56] You say here that the access option would confer rights of capacity for 30 years, whereas other train operators have been permitted track access contracts only over a much shorter period, and 10 years in the case of EWS. You say, "This conflicts with European law which prohibits the granting of access agreements greater than 10 years unless there are exceptional circumstances, which is not the case with Crossrail". Do you see that?

  (Mr Smith) Yes.

  14873. I think the provision that you are referring to is paragraph 18 of the Railway Infrastructure (Access and Management) Regulations 2005 and the relevant provision is 18(9).[57] I am sorry to burden the Committee with a matter such as this. It is quite important to understand the context of the words "exceptional circumstances". What that says is, "The framework agreement for a period in excess of 10 years may only be made in exceptional circumstances", so far so correct, Mr Smith, "in particular where there is large-scale and long-term investment and particularly where such investment is covered by contractual commitments". Now, can we agree that the Crossrail project is both a large-scale and a long-term investment?

  (Mr Smith) That is a subjective comment whether it is long-term or large-scale and also there is a mile of difference between 10 years and 30 years, quite a few years in between.

  14874. Yes, there is an element of subjectivity in it, Mr Smith, but I would have thought we could agree that a £10 billion project was a large-scale project, could we not?

   (Mr Smith) There are large-scale projects throughout the railway network, including, for example, the upgrading of the West Coast Main Line which cost in excess of £10 billion, but I am not aware that the operator there was seeking a 30-year access agreement.

  14875. So you would not be prepared to agree that Crossrail was a large-scale and long-term investment?

   (Mr Smith) I am saying that there are many large-scale and long-term investments and that the length of contract associated with those varies considerably.

  14876. Finally, Mr Smith, site specifics. I am not going to go through the sites, but it is a fact, is it not, that EWS and Crossrail have had a number of meetings about particular sites and, in particular, two meetings in March and April where we went through with you site by site what we needed to do on each site and what interests we needed to take?

   (Mr Smith) You did that up to a point, but, as you were saying earlier on, a number of designs are not yet completed, so you were unable to be absolutely specific about the works on each site.

  14877. No, but it would be quite wrong for the Committee to go away with the impression that until you came here today you had no idea as to what parts of the sites we wanted and how long we wanted them for, would it?

   (Mr Smith) It varies from site to site.

  14878. I will ask Mr Berryman to give further information on that. Thank you very much, Mr Smith.

   Re-examined by Mr George

  14879. Mr George: Mr Smith, if I take Langley and Slough, have you and EWS the slightest idea what precisely is required, which part of the sites and for how long?

   (Mr Smith) They are two of the sites where we do not have an idea of what is wanted and for how long or where.


53   Crossrail Ref: P106, Crossrail Timetable Working Group (LINEWD-GEN13-014). Back

54   Crossrail Ref: P106, Crossrail Timetable Working Group, Further Work (LINEWD-GEN13-008). Back

55   Crossrail Ref: P106, Crossrail Access Option-A Policy Paper: Addendum, May 2006 (LINEWD-21605-047). Back

56   Committee Ref: A168, The proposed Access Option as set out in the Access Option Policy Paper, DfT, 30 March 2006: EWS objections (LINEWD-19605-073). Back

57   Crossrail Ref: P106, Framework agreements, Railway Infrastructure Access and Management Regulations 2005 (S.I., 2005 No. 3049), www.opsi.gov.uk (SCN-20060711-005). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007