Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 14900 - 14919)

  14900. You welcome those two concessions, but what you say is that there is a need for further bespoke adjustments to the compensation system?

   (Mr Oatway) That is right and that is to meet Crossrail's intention, as I understand it to be, that operators will be compensated on a no net loss, no net gain basis for the building of the project and that is the criterion that certainly we would support.

  14901. Why is it that you consider that the standard industry compensation regime is inadequate for the Crossrail project?

   (Mr Oatway) I believe there are five points I want to raise here quickly. The first one is that the standard industry mechanism, known as the `network change procedure', where train operators are compensated for enhancements to the network, this does not include changes of a temporary nature, of an operational nature which do not last for longer than six months in duration. We believe that the Crossrail project would involve many of these types of operational disruptions and, as they are not compensated under the industry standard procedure of network change, we will not receive compensation for those temporary disruptions.

  14902. Were the standard railway industry compensation regimes drawn up having in mind schemes such as Crossrail?

   (Mr Oatway) The normal standard industry mechanisms are enshrined in our track access agreements, known in the railway industry as the `Schedule 4 possessions regime' and the `Schedule 8 performance regime'. As far as freight is concerned, those regimes were designed to ensure that freight operators would only receive compensation for planning failures by Network Rail, so if they planned possessions at short notice and that caused disruption to our services, we would get liquidated damages for those, not full costs and losses, just liquidated damages. Therefore, those types of issues where under Crossrail the possessions would be planned a long time in advance, ie, they would be pre-planned, as we would expect with a project the size of Crossrail, EWS and other freight operators would not receive compensation for those possessions under the standard industry possessions regime.

  14903. You set out this matter in some detail in EWS25 which I am not going to take you through in detail, but, for instance, you have just been referring to Schedules 4 and 8 and that matter is all explained, is it not, in EWS25?

   (Mr Oatway) Yes, that is correct.

  14904. If we could put up EWS26 please, you are showing there, are you not, some of the heads of claim, ie, some of the areas of loss which you might suffer and which you are anxious to make sure that compensation is provided for?[61]

  (Mr Oatway) These are typical areas of heads of losses that a freight operator would expect to incur where there is disruption or planned disruption of the network.

  14905. I think there are five areas you have mentioned. Can you quite briefly just explain to the Committee the five areas where you feel that EWS is threatened and ought to be given special protection?

   (Mr Oatway) The first one I went through just now which is disruptions of a temporary operational nature which are not compensated for under the network change procedure as it stands at the moment. The second one, which is in some respects the most serious, is that under the network change procedure there is a provision known as `G5'.

  14906. Just pause there because this is not familiar to everyone. Could we put up EWS27 because, as you say, this is one of the most important points and it is a point where we are hoping that Ms Lieven, on behalf of Crossrail, may be able to give some assistance.[62] There we have condition G5, "Changes imposed by competent authorities", and where Network Rail implements a network change as a result of any change of law, then compensation is not payable. Is that right?

  (Mr Oatway) That is correct, yes. Costs and losses lie where they fall.

  14907. The issue is whether the Crossrail Bill becoming an Act is going to be any change of law for condition G5. Now, what have you been told so far by Crossrail?

   (Mr Oatway) So far we have received a letter from the Department basically saying that they would not expect G5 to be activated or invoked.

  14908. That is a letter of 20 June sent to Mr Smith from a Mr Anthony Ferguson of the Crossrail Bill Division saying that the Department would not expect clause G5 to be exercised, but that is their expectation. What is it you are seeking?

   (Mr Oatway) Well, we are seeking a strict undertaking that it will not be invoked because an expectation just falling some way short of that and given the seriousness of if G5 is invoked, it would imply that EWS would not receive any compensation at all for the implementation of the building of the Crossrail project which leaves us very, very concerned indeed.

  14909. What is the third area?

   (Mr Oatway) The third area is another one that is very concerning. It is the implication that Crossrail could invoke the Bill powers to change in some way Part G, ie, the network change procedure, to amend its effects. It has basically got powers or it is seeking powers to be able to do that, so it could, through those powers, change some of the abilities for EWS to be able to object to the detail of such schemes which obviously have not been drawn up yet.

  14910. And the fourth matter?

   (Mr Oatway) The fourth matter is one I touched on earlier which is basically about pre-planned possessions. Unlike franchise passenger operators, freight operators are only compensated, and only then with a liquidated sum, for short-notice possessions. Crossrail possessions are likely to be planned well enough in advance to mean that EWS would not receive any compensation through its Schedule 4 regime in its track access agreement which is the standard industry mechanism.

  14911. And the fifth matter?

   (Mr Oatway) The fifth matter is about compensation for access into our depots, sidings, access to stations and to other facilities along the network. Again we do not believe the standard industry mechanisms are sufficient to be able to give us full compensation on a no net loss, no net gain basis.

  14912. Those are the five areas. Can we just come back to the third area which is the intention to prevent operators from blocking a Crossrail-related network change. Why do you find that objectionable?

   (Mr Oatway) Well, basically Crossrail, as I understand it, have said that they do not believe that operators should have the veto to block any Crossrail network changes because of the parliamentary procedure that is currently taking place, ie this procedure, being part of that and, therefore, once Parliament has said that Crossrail should go ahead, then it should go ahead. Now, we do not dispute that once that process is gone through, the principle of Crossrail going ahead is not something that we would find we would need to veto. However, the concern we have got is the fact that there are more ways to implement things than just one and there will be lots of individual network changes no doubt coming out of this project and if some of that detail is not of sufficient comfort to us, then we would seek to rely on our current right under the standard industry mechanisms of being able to challenge that and having any disputes independently arbitrated.

  14913. Your conclusion then on the application of standard industry compensation entitlements for freight?

   (Mr Oatway) My overall conclusion is that basically we are satisfied that compensation on a no net loss, no net gain basis, which Crossrail has indicated in page H2, is sufficient for our purposes. What is not sufficient is the fact that the current standard industry procedures for freight do not compensate freight operators on a no net loss, no net gain basis and, therefore, we are seeking to have a bespoke measure to be able to top up that compensation so that we are held blameless for the effects of Crossrail.

  14914. Do you see a potential for really quite considerable losses as a result, for instance, of temporary speed restrictions and the like?

   (Mr Oatway) Yes. As Mr Smith said earlier on, our trains travel across the whole network, across the whole country and just a small delay on one part of the network can have a domino effect by the time that train reaches other parts of the network. If there are many disruptions in the London area, that will ripple across the whole network and eventually our customers will be very concerned and angry that EWS is not providing the performance and timings of the trains that it is committed to, which could then lead to loss of customer confidence and loss of contracts.

  14915. Mr Oatway, is there anything unusual in legislation making special provision for the compensation consequences of work such as this?

   (Mr Oatway) No, I do not believe there is. There are a couple of examples that have occurred in the past which I would like to touch upon and bring the Committee's attention to. The first one is to do with the CTRL project. When the CTRL project was being put through back in 1996, a bespoke provision was inserted into all affected operators' track access agreements which would enable those operators to receive full compensation for any disruptions that the CTRL project would have on their services that affected Network Rail's network. That would take out any dubiety over whether any disruption would last less than six months or over six months. You would be satisfied and confident that you would be fully compensated for any of those disruptions.

  14916. So far as the CTRL Act—we know that those works are now getting towards completion—what was the position about when you had a temporary speed restriction lasting for not less than six months? Was compensation paid?

   (Mr Oatway) Yes. It enabled EWS to claim compensation for the effects of that speed restriction on similar terms to what the network change procedure would have given had they constituted network change.

  14917. That is the sort of provision which you think ought to be put into this Act as well?

   (Mr Oatway) I believe so.

  14918. Secondly, you refer to the East London line extension, exhibit EWS 28.[63] The East London Line is a new extension of a railway in London. It is done under a Transport and Works Order under the 1992 Transport and Works Act rather than a Bill but it includes, does it not, provisions such as you would seek to be inserted into the Crossrail Bill?

  (Mr Oatway) It does. The East London line is typical of these types of third party schemes affecting Network Rail's network.

  14919. The next page of the exhibit should be schedule 11.[64] There is a black line against paragraph 1(2) against relevant costs. We can see that the relevant costs are the costs, direct losses and expenses reasonably incurred by each train operator. Is EWS a train operator?

  (Mr Oatway) Yes, it is.


61   Committee Ref: A168, Non-Compensatable Disruption Losses (LINEWD-19605-081). Back

62   Committee Ref: A168, Condition G5-Changes imposed by competent authorities (LINEWD-19605-082). Back

63   Committee Ref: A168, The London Underground (East London Line Extension) (No. 2) Order 2001 (S.I., 2001, No. 3682), www.opsi.gov.uk (LINEWD-19605-083) Back

64   Committee Ref: A168, Schedule 11, Protection for Railtrack, The London Underground (East London Line Extension) (No. 2) Order 2001 (S.I., 2001, No. 3682), www.opsi.gov.uk (SCN-20060711-006) Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007