Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 16420 - 16439)

  16420. A great deal of time has been spent before the Committee by the freight industry raising issues related to capacity and access which, while they may be genuine issues, are ones not for the Bill or the Committee. The Promoter does not, of course, dispute the importance of the use of rail by the freight industry or aggregates industries but much, if not most, of what is being put before you can be dealt with in one of the following ways. Firstly, the issues arise in any event due to existing capacity constraints on the network. Secondly, they do not arise because Crossrail does not generate significant capacity issues or, thirdly, they fall to be addressed by the normal regulatory processes in seeking an Access Option from Network Rail with the approval of the Office of the Rail Regulator.

  16421. The freight sector has been at pains to point out the importance of its operation but the Committee may think its approach to the issues of capacity almost as if Crossrail were engaged in attempt of theft. It has been anxious to stress the shortcomings of the assessments made to date, the issues which remain to be addressed, and, by strong implication, the virtual entitlement of the freight sector to take up future capacity in the network.

  16422. The reality is that the public interest lies in striking a balance between the various rail interests, passenger and freight, and it is indisputable, giving the approval in principle of the Bill, that Crossrail is a major project demanding major investment to achieve a range of objectives in the public interest. I will remind you of what Mr Steel of ATOC said on day 48, that the rail industry was firmly in favour of Crossrail. I have quoted that.

  16423. The Committee may find it helpful when reflecting on the attitudes of some within the freight industry to review, for example, the evidence of Mr Smith of EWS on day 51, paragraphs 14874 till 14875, when under cross-examination from Ms Lieven, Mr Smith could not even bring himself to admit that Crossrail was a large-scale and long-term investment. We say that is indicative of the sort of attitude we have been faced with.

  16424. The rail industry is of major national importance for many reasons. However, that does not make it either reasonable or realistic to demand, as many Petitioners have, that Crossrail should be required to resolve. Such matters lie outside the Bill and, if you will forgive me for saying, sir, the concerns are ones which are under consideration by the Secretary of State, and, indeed, raised by Mr Hopkins in a PQ to the Secretary of State on 11 July. He received an assurance from the Secretary of State that these matters were under active consideration.

  16425. I repeat our opening statement without reading it out on day 48, paragraphs 13669 to 13691. The reason I do that is because I said a lot on that day, which I am not going to repeat today, about there being adequate capacity on the Great Western for rail passengers. There is clearly legitimate concern that for those coming into London from the West on passenger services—and I know it is a matter that was raised by Mrs James in particular as a concern—there is not a capacity issue so far as the west is concerned. You will know from our evidence that we gave that there are some minor beneficial effects to the works proposed at Paddington and, indeed, that further works to upgrade that part of the network are proposed in any event. I have not set that out here because I have set that out at length in opening.

  16426. I turn first to the Access Option. It is essential that the Promoter can be sure that the Crossrail service will operate at the levels that Parliament have been told that it will. Raising finance for the project depends on there being secure track and station access rights sufficient to run the level and quality of service necessary to realise the benefits of the project. That security must be provided over a timescale which enables potential investors to have some security that there will be return on their investment. There is a precedent found for this security in section 17 of the London Olympic Games and Paralympic Games Act 2006.

  16427. The issue then is whether it is by means of an Access Option or by means of Bill powers that the security should be provided. We have given you our detailed position in information papers H3 and H4.

  16428. The Committee has heard Petitions from a large section of the freight community who are concerned about the implications of the Crossrail Bill on the ability of the industry to grow in the future. The consistent theme is one of fear concerning the scope of the Bill powers in relation to the utilisation of capacity. Rather than utilise the Bill powers, some Petitioners have submitted that an Access Option should be sought pursuant to the existing rail regulatory regime. We confirmed on day 48 in opening that this was the approach that was going to be adopted, see paragraphs 13675 and following on day 48. It is anticipated that the Access Option will be obtained during the passage of the Bill and before it passes to the House of Lords. Once the Access Options have been granted, the Promoter has indicated that it will review the extent of the Bill powers and cut them back accordingly. Until the Access Option has been granted, it is not possible to specify the nature of the amendments that will be pursued. As you know, sir, the Minister, Mr Twigg, wrote a letter on 29 June of this year confirming the approach which is also the approach set out in information papers H3 and H4. So, there is no doubt—and we repeat the points we have made so often during the last few weeks—an Access Option is being pursued for Crossrail. It will be considered by Network Rail and the OFF under the existing and unmodified regulatory regime. Network Rail and ORR will want to be satisfied of operational viability, and once they are, the industry will be consulted. Operational viability includes matters such as demonstrating a robust timetable and that the infrastructure will be sufficient.

  16429. We have set out our position in greater detail in the paper that was provided at the Committee's request, the Crossrail Timetable Working Group and Access Options process Next Steps which we referred to briefly yesterday and was sent to the Committee at your request.

  16430. The issues which will have to be demonstrated to Network Rail and the ORR are set out on the fifth page of that paper and at appendix C. It explains all the many elements that go into improving operational viability, which include the two factors I have mentioned and on which the rail industry has focused in the last couple of weeks. It will not be considered, as Professor O'Keefe believed, on the basis that Crossrail should have a priority, that is what he said on day 51, paragraph 15022. This misunderstanding undermines the Professor's evidence because the basic premise upon which his allegations of conflict with EU law is flawed. No modification would be made, of course, until the regulatory regime under the Bill became law, so the Access Option currently sought will be under the current law and in accordance with the normal industry practices. Contrary to Mr Kingston's suggestions for Tarmac, day 54, paragraph 16394, there is no threat hanging over the ORR's head. The Access Option must be granted according to the current law and practices. Indeed, you may well think, sir, that the freight industry would be the first to challenge a decision by the ORR which sought to depart from current law and industry practices.

  16431. The Bill powers are highly likely to change. The relationship of the Bill powers to the existing regulatory regime and to European law is highly likely to change as the Minister has already pointed out. It would therefore be premature and may well be a pointless exercise for the Committee to concern itself with issues relating to the relationship of the Bill to the exiting regulatory regime and to the EU directives.

  16432. I turn to deal briefly with the duration of the Access Option which was a point raised. As to the appropriate duration of the Access Option, that matter is one best left to Network Rail and to the ORR to determine on the evidence presented to those bodies according to normal practices. The EU Directive and the transposing regulations both make it clear that Access Options can be granted that exceed 10 years in duration in exceptional circumstances: "In particular where there is large-scale and long-term investment and particularly where such investment is covered by contractual commitments". That is regulation 18(9) of the Railway Infrastructure and Management Regulations 2005.

  16433. It is apparent that the regulatory regime recognises that Access Options may need to be of longer duration in order to enable the financial security necessary for the funding of the project to be obtained. We suggest that it is obvious that Crossrail is "large-scale" and "long-term investment" despite Mr Smith and EWS's unwillingness to accept that on day 51.

  16434. Capacity: The Timetable Working Group's conclusions that there is sufficient capacity for Crossrail and freight growth on the GWML is made clear. That covers concerns of the aggregate industry about which the Committee heard much last week. The TWG included substantial representation from the freight sector and, as Mr Watson told you on day 48, reached substantial agreement on the report. It is all the more curious that having done so they should now be seeking to distance themselves from it for the purposes of their Committee appearance.

  16435. Despite criticism from some Petitioners, it is clear that TWG has carried out a significant amount of work. This was made clear not only by Mr Watson on day 48 (see paragraphs 13697 and following) but it was confirmed by Mr Steel for ATOC on day 48, at paragraph 13904. What he said was: "There has been a considerable amount of joint working, in particular the Timetable Working Group has carried out some good work, as has the Rail Industry Stakeholders' Forum, and the Government has brought forward proposals which in principle begin to address many of our concerns including information papers H1-4 dealing with railway matters". He goes on in similar vein.

  16436. Of course, while it is correct that work remains to be done, clearly much work has already been done to show the Committee that there are sound reasons for considering capacity issues are not created by Crossrail.

  16437. So far as traffic from the haven ports is concerned, Crossrail makes virtually no impact, and any impact there is balanced by the provision of the Chadwell Heath Loop, which was dealt with on day 53.

  16438. As far as the Great Eastern Mainline from the Thames Ports is concerned, the Timetable Working Group concluded that there was insufficient capacity for the freight growth beyond 2015 because of the capacity constraint between Forest Gate and Stratford even if Crossrail did not come along. The Committee will recall that Mr Garratt's own figures in his table 8 lend support to the Working Group's own conclusions and what he said yesterday, day 54 at 16329 in response to questioning from me and when I put to him the 197% for 2030 he did not deny that further works either on this route or on other routes will be required to reach that level of utilisation.

  16439. Mr Steel of ATOC also agreed that work would have to be done ahead of Crossrail to improve capacity on the Great Eastern; again day 48, paragraphs 13930-13932. The point is made by reference to the tables appended to the Working Group report that Crossrail makes the position worse. However, this argument fails to acknowledge that what is made worse is already not working because the system is at capacity without Crossrail. Crossrail cannot break what is already broken. A solution to the capacity constraint on the Great Eastern Mainline has to be found whether Crossrail is constructed or not. It is therefore a problem that does not fall for Crossrail to solve.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007