Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 16800 - 16819)

  16800. The Promoter's response: The Secretary of State accepts the judgment of the Committee that the exceptional and historical nature of the business of the tenants of Smithfield Market justifies additional rights to compensation with respect to impacts caused by the Crossrail work for this special case. The Promoter's proposal to deal with this is as follows. It applies to the market traders who are tenants of the city corporation at Smithfield Market. Where an event occurs during the construction of Crossrail which triggers a right for the market traders to claim compensation under section 10 of the compulsory Purchase Act 1965 (as modified by clause 50 of the Crossrail Bill) or Section 6 of the Railways Clauses Consolidation 1845 (as incorporated with modifications by paragraph 3 of Schedule 10 to the Bill) against the nominated undertaker, the Secretary of State will require the nominated undertaker to include in the compensation an amount representing any consequential loss, whether or not reflected in the value of land, (1) which was caused by the construction of the works under statutory authority, (2) for which the nominated undertaker would have been liable to pay damages if the construction had not been authorised by statute. The Promoter has written to the Smithfield Market Tenants Association to offer an undertaking on the basis and to explain how the proposal will would work in practice. A copy of that letter is at Annex A. Sir, I should have said, there are a number of annexes to this document, I do not intend to read them out but they are all there for the Committee to see.

  16801. Charterhouse Street—the Committee Decision: Following the Petition of Save Britain's Heritage, we would also ask the Promoter to explore and assess alternatives to the compulsory purchase of 33-37 Charterhouse Street.

  16802. Promoter's response: In response to the Committee's request, the Promoter commissioned an engineering study to investigate whether there is an alternative way of forming a passenger link between the Crossrail station at Farringdon and the eastbound Metropolitan/Circle Line platform at the Barbican London Underground station, providing PRM access to the platforms and street level without the acquisition and demolition of 33-37 Charterhouse Square. The study showed that there were no suitable alternatives which would not have more significant effects on the area than the current Bill scheme. For this reason, the Promoter proposes to continue with the original proposal. The Promoter will work with the relevant planning authority to find the most appropriate solution for developing the site once works have been completed. Further detail of the engineering study carried out is provided at Annex B.

  16803. EMI Limited—Committee Decision: The Committee has listened carefully to the case of EMI. We recognise that the increased value of the building would have to be built into any compulsory purchase order negotiations. Therefore, in order to keep the cost to the public purse as low as possible, we believe that the Petitioners should be subject to a CPO as soon as practicable after Royal Assent.

  16804. Promoter's response: The Promoter will offer to EMI an undertaking to purchase their building at a time of EMI's choosing from the point at which funding for Crossrail has been secured. The form of that undertaking is at Annex C.

  16805. Grand Central Sound Studios—Committee Decision: Similarly, in the case of Grand Central Sound studios, the Committee agreed that the exceptional technical nature of the Petitioner's business required protection against potential disruption from the works. We ask that sound mitigation work is carried out before construction commences, where possible.

  16806. Promoter's response: In its response the Petition of Grand Central Sound Studios, the Promoter proposed mitigation work to the railway itself in order to mitigate the noise produced by the operation of Crossrail and the running of the construction railway. The Promoter is in the process of discussing with Grand Central Sound Studios precisely what form that mitigation should take. The Promoter understands that the Petitioner has written to the Committee to clarify that point. This Petition has yet to be heard by the Select Committee. If the Promoter and Grand Central Sound Studios are not able to agree, therefore, the issue will come before the Committee in due course.

  16807. Shenfield—Committee Decision: We will discuss the cases presented to us about Shenfield in detail in our report. At this stage, we wish the Promoters to demonstrate that they have worked closely with the local community to ensure that appropriate noise insulation has been provided to those who will be affected by the additional noise of the Crossrail works.

  16808. Promoter's response: Following the Select Committee's decision, the Promoter commissioned revised noise impact predictions for the Shenfield area. The results are still being finalised and will be included in the Supplementary Environmental Statement expected to be published in November. On 13 September, Cross London Rail Links met with the relevant local authority, Brentwood Borough Council, to explain what was being done and to discuss how the revised noise predictions, once finalised, might best be disseminated to the affected local community. As a result, CLRL intend to write to the residents concerned, providing copies of both the original and the revised predictions in readily comparable and understandable map form. The letter will explain what the predictions mean in terms of likely qualification for either the provision of noise insulation and/or temporary rehousing, and the trigger levels used for their provision. It will also explain in layperson's terms the process for further predictions to be made, nearer the start of the construction, once the detailed design work has been done and a detailed construction methodology devised, and for the actual provision of noise insulation and/or temporary re-housing. The letter will make it clear that whilst the trigger levels for the provision of noise insulation and temporary rehousing will remain the same, it is these later predictions, as opposed to the predictions done now, that will determine who will qualify for noise insulation and/or temporary rehousing.

  16809. CLRL then propose to organise, in liaison with the local authority, and advertise widely, including by leafleting all properties within 100m of the proposed work, a drop-in centre or meetings at which concerned residents can be taken through the revised predictions and the process outlined in the letter.

  16810. Committee Decision: The Committee would also like the Promoter to look again at the possibility of using the existing sidings at Shenfield as highlighted by Mr Jardine on 29 March, paragraph 6145.

  16811. Promoter's response: CLRL have considered Mr Jardine's proposal again and reached the same conclusion as before that it is not possible to make use of the existing sidings safely for Crossrail services. More detailed information is provided at Annex D and this has also been provided to Mr Jardine.

  16812. London Borough of Havering—Committee's Decision: In the case of the London Borough of Havering, the Committee has found certain merit with the Petitioner's case. At this stage, we invite the Promoter to find a way to provide appropriate access for mobility impaired people to the developed station in the location of the current ramp. In the same way, we expect access to all Crossrail stations to be developed with awareness of the access needs of people with impaired mobility.

  16813. Promoter's response: The Promoter will provide a new access ramp complying with modern standards for access for people with reduced mobility at the south side of Romford Station. The new ramp will be built to the west of the existing door, providing access to the south end of the mezzanine level subway of Romford Station.

  16814. Southend Arterial Road Action Group—Committee Decision: We are aware that these Petitioners did not have the opportunity to fully finish their case. However, the Committee agreed with the Petitioners that the cul-de-sac was not appropriate for the level of access proposed. We believe that the Promoter must find either an alternative access to this worksite or an adequate solution to this particular problem.

  16815. Promoter's response: The Promoter will bring forward an additional provision to provide for an alternative access to the Crossrail worksite. The access will make use of a vacant residential plot immediately adjacent to the worksite. This proposal would remove the need to access the site from the cul-de-sac off the Southend Arterial Road.

  16816. Freight—Committee Decision: The Committee is persuaded that the freight industry faces an increasing challenge with current capacity insufficient for the needs of growth in the industry, and we believe that the Government should take steps to address this. However, the Committee believes that these issues are largely the responsibility of Network Rail and others and not wholly that of the Crossrail project. We will return to this issue in our full report. The Committee is concerned about the uncertainty regarding the Access Option and asks that Promoter to ensure that the Committee is updated on these issues later in the year.

  16817. Promoter's response: The Promoter agrees with the Committee's analysis that there are issues in relation to freight capacity which are broader than the impact of the Crossrail project and which need to be analysed and solutions considered by the rail industry's planning mechanisms (including developing further two short-listed applications for Transport Innovation Fund support). This work will progress at the pace of the industry mechanisms rather than necessarily before the Select Committee completes its work. The focus of the work in relation to Crossrail is developing the Access Option with Network Rail, and consulting the ORR, which is currently at the stage of heads of terms. To support this, a considerable volume of technical analysis and modelling have been commissioned to demonstrate operational viability, as explained in the paper put to the Committee shortly before the summer recess. This includes, but is not confined to, further train timetabling work. As this work develops, input will be sought from the rail industry via the Reference Group that has been established to replace the Timetable Working Group. Formal consultation will be undertaken by the ORR once it receives the application for the Access Option. Further updates on progress will be given to the Committee.

  16818. Ealing Broadway—Committee Decision: The Committee asks the Promoter to demonstrate that a good cross platform interchange could be made available at Ealing Broadway between the Reading and Crossrail lines.

  16819. Promoter's response: Although Crossrail will not directly serve Reading and Twyford, passengers from these stations will find significant improvement in the journey times into central London. This is because they will be able to interchange onto Crossrail trains either at Paddington or at Ealing Broadway. Interchange will be particularly attractive at Ealing Broadway where same platform interchange will be possible. To do this, a passenger will simply get off their semi-fast service from Reading or Twyford and get onto the next train, which will always be a Crossrail train. As an example, passengers travelling from Twyford to Liverpool Street by relief line trains will experience at least a 15-minute reduction in journey time by making a same platform interchange at Ealing Broadway when Crossrail opens.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007