Select Committee on Crossrail Bill Minutes of Evidence


Examination of Witnesses (Questions 17580 - 17599)

  17580. There is mention there of the need to close for about a month. We have communicated that to the Petitioner. Is there anything more on that?

   (Mr Berryman) No, I do not think so, unless the Committee have any questions on that.

  17581. Let us turn, please, from that point to the question of settlement. Again trying to take this fairly quickly—just a series of points really: have we assessed the combined impacts, in respect of settlement, of the Crossrail tunnels and the sewer proposals?

   (Mr Berryman) Yes, we have.

  17582. Have we prepared a report in relation to that?

   (Mr Berryman) We have.

  17583. The Petitioners have been provided with a copy.

   (Mr Berryman) That is correct.

  17584. Does that also embrace an assessment of the sewer shafts?

   (Mr Berryman) Yes, it does, although all the sewer shafts are quite remote from buildings.

  17585. What are the principal protective measures that we anticipate will be required in relation to this facility of work.

   (Mr Berryman) We do not think there will be any protective measures at all required to the sewer tunnel. The issue is more with the running tunnels, which, as you are aware, are very shallow at this point. There we are doing our usual assessment of the impacts on properties and offering a settlement deed for all the people who are affected.

  17586. Turning to the particular point of the Petitioners' document, page 25, would you comment on the accuracy of this image.[42]

  (Mr Berryman) This is not to scale, contrary to what was said. We have a drawing which is to scale, substantially to scale.

  17587. That is 001.[43]

  (Mr Berryman) The diameter of the tunnel is, of course, as it says here, internally six metres and externally about 6.6 metres. The design of the tunnel lining is something undertaken normally by the contractor, so the exact thickness, whether 300 mm or 375 mm or whatever, we do not know at this stage, but it is in that area. Page 001 is a section which is to scale. It shows the house at the top and at the same scale the tunnel underneath. I believe this was prepared for Mrs Wheeler, one of the Petitioners we will be hearing from later. You can see the relative scale of this is substantially different from the other sketch.

  17588. There was mention, I think, this morning of a figure of 1.7%. Can you explain the significance of that?

   (Mr Berryman) If you recall all the way back to the beginning when Professor Mair gave a talk on certain petitions generally, the 1.7% refers to the ground loss or relaxation which would occur when the tunnel is driven, and it is a reference to the percentage of the volume of the tunnel which will be lost. If you remember, that is spread over a very wide zone of settlement. I think Professor Mair may have given quite a long talk about that. The 1.7% does not relate to the compression of the ground between the top of the tunnel and the ground surface; it relates to the volume which is lost to tunnel. The 1.7% we have used, we know from other tunnelling projects, is very conservative and normally on the Channel tunnel Rail Link they have been achieving about 1.5% as a general rule. So we know they make very, very conservative assumptions. It is also worth mentioning the difference between settlement, which is what we expect to happen over a tunnel in any event, to a greater or lesser degree, and the kind of catastrophic collapse which the Petitioner mentioned this morning. Obviously, there are ways of avoiding that by effective management of the proposals, but it is not something that we would expect to happen.

   Mr Binley: Just to get 11 metres in my mind, would this ceiling be 11 metres?

   (Mr Berryman) Eleven metres would be six people standing on top of each other. It may be 9 metres, I do not know.

  17589. Probably a bit more.

   (Mr Berryman) It is very hard to estimate in here.

  17590. I am just trying to get a feel. Thank you.

   (Mr Berryman) That, of course, is to the top of the tunnel.

  17591. Chairman: Just on the ground in the tunnel, what kind of ground is in this particular area? It is not the same—or is it the same—as we discussed in the City: London clay and so forth?

   (Mr Berryman) I think at this point we are out of the London clay. I think it is reasonable ground. I can get an answer to that very quickly.

  17592. Mr Mould: I am told it is mainly London clay with gravel overlaying.

  17593. Chairman: Could you give us that note anyway?

   (Mr Berryman) I will give you a note, sir.

  17594. Mr Mould: Can we move away from settlement and just touch on another matter, which was the question of night-time working. I have put up an extract from the additional provisions which sets out, in 5.3.5, the reference to 24-hour working.[44] Can you summarise for the Committee the position in relation to night-time working in relation to this part of the project?

  (Mr Berryman) The significant impacts of night-time working are at the existing McDonald's site near the junction of the A12 and the A11, down near the flyover which the Petitioner pointed out earlier. That would be a 24-hour-a-day site. The other sites will generally be daytime only, except for specific items of work. If you could put slide 38 up, just to illustrate the point. The shaft at Grove Hall Park will, generally speaking, be a daytime only site. There might be a very small amount, a couple of nights, of night work when we join on to the new tunnel. This site here will be a 24-hour-a-day site, although, as you will appreciate, this is a very noisy location anyway with the Blackwall Tunnel Road. This site will be generally a daytime site except for the restriction of a retaining wall here, which may have to be done at night. When I say "may have to be done at night" it may have to be done, and if it is done it is done at night. There is a possibility we may be able to get away without doing it at all. Then there will be some night-time working when we withdraw the tunnel boring machines from here. At these two sites there will be night work because what we are doing here is filling the disused sewer with foam concrete, and that is just a question of bringing a truck mixer in and literally pouring concrete down a manhole. Of course, this road will be kept open; it is very busy. The noise of that work will be not detectable above the background levels there, and similarly for this site here. Again, for very short durations, I think from memory about six nights and this one is about four nights.

  17595. Finally, sir, if I can make this point, the question of the potential impact of a lorry route past the local school was mentioned this morning. I am bound to say that was news to me. I can say that if it is right that lorries would be routed past a local school—we will check that—then I am told that the arrangements that we have already told the Committee we will commit to in relation to schools in Whitechapel and going in and coming out times will be applied in relation to that school as well.

   (Mr Berryman) That is correct.

  17596. Chairman: All lorries used will be sheeted over?

   (Mr Berryman) Yes, throughout the project that will be the case.

  17597. On the top sites, which is concrete mixing, is the mixing on site?

   (Mr Berryman) No, that will come from a ready-mix concrete plant and, as I say, just literally poured down the manhole. It is not quite as simple as that, but that is the general gist of it.

  17598. The final thing is in relation to the request for similar arrangements as Whitechapel on the one-stop kind of shop for all inquiries, and to liaise.

   (Mr Berryman) In principle the answer is yes. We will be producing a community relations strategy in due course.

  17599. When will that be available?

   (Mr Berryman) It is available in draft already. It is going round for discussion with local authorities. It is not going to be ready in the next few weeks but it should be ready by the end of the year.


42   Committee Ref: A193, Fairfield Conservation Area Residents Association, Baldock Street (TOWHLB-29105-025). Back

43   Crossrail Ref: P126, Tunnel Gradient and Long Section-Mrs Barbara Wheeler, 1 Baldock Street, Bow E3 2TP (TOWHLB-31204-001). Back

44   Amendment of Provisions Environmental Statement-May 2006, Chapter 5, Route Windows C13 and C13A: Pudding Mill Lane Portal and Abbey Mills Duration of the Works, billdocuments.crossrail.co.uk (SCN-20061018-002). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 14 November 2007