Select Committee on Culture, Media and Sport Minutes of Evidence


Supplementary memorandum submitted by DCMS

WRITTEN QUESTIONS TO THE SECRETARY OF STATE

Question references relate to evidence on 21 November

  1.  What has happened to the KPMG review of costs which you described in oral evidence to the Committee on 25 July 2006? What conclusions were reached by KPMG? [Q 144]

  The review of costs is ongoing. KPMG's contribution was two-fold: to re-assess costs to ensure that there is a sound cost baseline and to help identify the scope for savings in potential costs with a view to keeping costs down. The re-assessment of costs confirmed that the core cost estimates of the venues was unchanged but identified other areas, where, as I reported to the Committee, increases in core expenditure are anticipated. This work informs the basis of discussions within Government about the cost of the Games and how they are to be funded. KPMG's work also contributed to the identification of savings of some £700 million in potential costs.

  2.  You said in answer to Q 138 and Q 173 that the NAO has agreed to work closely with DCMS on costs and ensuring value for money. Can you tell the Committee more about how this work will be structured?

  The NAO is currently undertaking a review of the preparations for hosting the London 2012 Olympic Games and Paralympic Games, including the progress that has been made to put in place the necessary delivery and financial arrangements. We have also discussed with the NAO their programme of further work and they are currently drawing up their plans which we understand could involve looking at the process used to generate financial estimates.

  3.  How much private sector funding has been secured for (a) the Olympic Village, (b) the International Broadcast Centre/Media and Press Centre and (c) sporting venues in the Olympic Park? [The Committee would welcome figures in confidence if necessary] [Q 143]

    (a)  Our expectation is that the Olympic Village will be procured by a development partner with the aim of making a commercial return post-Games and that the private sector will provide the majority of the financing for its development. Negotiations with potential developers to agree the arrangements under which the Village will be procured are still in progress with the ODA.

    (b)  The net cost of building the International Broadcast Centre and Media and Press Centre is reflected in the increase in core costs that I reported to the Committee. A mix of public and private financing is envisaged but the specific arrangements for this have yet to be negotiated.

    (c)  Our figures assume that the costs of constructing the sports venues will be met entirely from the Olympic Budget.

  4.  Can you give an indication of the likely increase in security costs? [Q 143]

  The events of 7 July 2005 changed the security landscape in London and there will be other considerations that will impact on security plans for 2012. We are committed to a safe and secure Olympic Games and Paralympic Games in 2012, and we will continue to work with all relevant security organisations to ensure this. My officials are working with the Home Office and the Metropolitan Police Service and other agencies—together with Her Majesty's Inspectorate of Constabularies—to clarify and verify longer term issues, actions and costs as far as that is possible at this point in time. We will also ensure that security costs falling to the ODA and LOCOG are reviewed and clarified in the context of their wider budgets—that work is well underway.

  5.  Where, in the bid documents, was it made clear that the bid was submitted net of the cost of VAT? [Q 161]

  When the bid was submitted the precise nature of the delivery vehicle was not decided, so it was impossible to determine the tax treatment of the ODA. The assumption was that VAT was recoverable in line with the treatment of bodies such as local authorities and in line with previous Games. The public sector funding package was agreed on that basis.

  6.  You refer in answer to Question 171 to "different views" on whether a programme contingency is necessary, and you said that "I think the broad consensus is that it is". Are you part of that consensus? If so, why do you believe that a programme contingency is necessary, and why was it not included in the original bid?

  Yes, I am a part of that consensus. In my view, contingency is necessary in order to allow for the inevitable uncertainties and risks associated with a seven year project on the scale of the Olympic Games and is a practice recommended by HM Treasury. PWC prepared a detailed report modelling the costs of the Games. The detailed budget for the Games, including the allowance for project contingencies, was prepared on the basis of this advice. Project Contingency is built up from the contingency for individual projects, whereas Programme Contingency is a contingency that is applied to the programme as a whole. The cost review that I initiated immediately after winning the bid has pointed to the need for a substantial Programme Contingency in recognition of the scale and risks associated with the Olympic construction programme. The issue now is what the appropriate level of Programme contingency should be as we move forward.

7.  When do you expect the site survey to be completed? What timetable was originally set for the site survey? [Q 167]

  As much of the land for the Olympics sites was not under London Development Agency ownership during the bid process, it had not been possible to gauge accurately the time requirement for site surveys. Now that 93% of the land has been secured, the Delivery Partner consortium, CLM (CH2M HILL, Laing O'Rourke and Mace), is currently working to establish contamination levels across the site. There are, at present, eight drilling rigs on site working on ground analysis, with over half the site assessed to date. In line with the programme to secure vacant possession of land, there are three phases to the geotechnical surveys across the site:

    —    The first phase consists of geotechnical surveys (eg ground bore holes and sampling) in "open areas" as access is gained. This is programmed to complete end of March 2007. Currently this is on programme and is forecast to complete on time.

    —    The second phase is geotechnical and chemical sampling below the footprints of buildings after they are made available to the ODA and have been demolished. This is scheduled to be complete by end April 2008.

    —    The third phase is sampling of soil samples as areas are excavated for forming the "platform" for all other facilities and infrastructure.

  The completion of stages one and two will substantially reduce related risks, as there will be greater clarity on the exact nature of the materials to be dealt with. There is one area, the bus station, which may sit beyond the April 2008 milestone, depending on the arrangements for an alternative site.

  There are no current plans to release a detailed timeframe into the public domain. However, the overview of the Olympic Park Delivery Programme was published in July 2006 and includes high-level timelines for land preparation.

  8.  You told the Committee that the £1.044 billion to cover the costs of linking the Olympic Park to the rest of the Lower Valley "sits within the budget of DCLG" and is "routed through the Olympic Delivery Authority" [Q 177]. Will any element of that £1.044 billion be spent at the discretion of the ODA?

  The £1.044 billion includes expenditure on a range of infrastructure projects, in particular, the project to put into tunnels the high voltage transmission cables that cross the site of the Olympic Park. The programming and delivery of the projects is a matter for the ODA, subject to the approval of the Olympic Board. The individual projects are set out in the ODA's annual budget and funds are made available to the ODA subject to evidence of spend. In the current arrangements, funds are transferred from DCLG to DCMS on the basis of evidence of need and issued by DCMS as the ODA's sponsor Department.

  9.  You stated that a further £400 million had been identified to cover the appointment of the delivery partner to oversee "cost control and timeliness" (Q 180). Was no provision made in the original bid for these functions? What has occurred to make the extra expenditure necessary?

  The original bid did not include provision for a Delivery Partner because at that early stage the shadow organisation for the construction of the Olympic Park, ie the interim ODA, had yet to be determined and its Chair and Chief Executive had yet to be appointed. Following the bid I initiated a thorough re-appraisal of the costs. This took into account the post-bid wish by the interim ODA to appoint a Delivery Partner; and the assessment by the newly established ODA of its needs. This assessment concluded that there was a need for further expenditure of around £400 million in order to provide the level and quantity of expertise and skill necessary to deliver the emerging Olympic Park project in the Lower Lea Valley and to undertake effective project and programme management and cost control. The recently appointed Delivery Partner will play an important part in this role. However, the c£400 million includes not only the costs of the Delivery Partner but also the costs of site mobilization and the costs of additional staff required by the ODA itself.

10.  You stated (in answer to Q 187) that the £410 million second tranche of funding from the National Lottery Distribution Fund would be "shared equally across all the distributors... by about £12 million". How is the £12 million figure reached, and can you confirm that this rate would apply equally to each of the 16 non-Olympic distributors?

  I have no recollection of using a figure of £12 million. No final decision has yet been reached on how and when to transfer the £410 million. It is not possible to confirm precisely what the monetary impact on the good causes, and on individual distributors, will be. The basic proposition, however, has always been that we will take the £410 million from the good causes as fairly as possible and in a way that minimises the impact on those causes.

  11.  What would be your preferred method for meeting short-term funding problems at the ODA, if Lottery ticket sales cannot meet that need?

  At present Lottery ticket sales are on target. However, were there to be a short-term funding shortfall, we would look first, by agreement with the other funding parties, to bring forward funding from the other sources from which the ODA is already funded.

  12.  Have any cases involving possible infringement of the Olympics association right (or of the brand) yet been determined by a court?

  LOCOG's Brand Protection Team has been very active working with a range of organisations who have used the brand incorrectly. In the main, people have been very co-operative and the LOCOG team have been able to resolve these issues amicably. LOCOG has not yet had to issue proceedings in any case.

  13.  How many responses have you received to the consultation on a tourism strategy for 2012?

  We received 168 responses from organisations and individuals by the close of the consultation period. This number is likely to rise, as we are contacting a number of stakeholders who missed the deadline. I should emphasise that many of the responses were from umbrella organisations that represent a large number of members; for example, the Tourism Alliance represents over 200,000 businesses.

  14.  How do you intend that performance towards the objectives drawn up for stakeholders in the London 2012 project should be measured?

  Performance will be reviewed by the Olympic Board on advice from the Olympic Board Steering Group and the Olympic Programme Support Unit (OPSU). The latter has been established to provide an overview of the entire programme. Monthly dashboard and status reports against the specific objectives (and associated sub-objectives) are reported to the Olympic Board and classified in a red, amber, green status. In addition, a risk management reporting process is fully operational across the programme with the OPSU taking a centralised role in its monitoring function.

1 December 2006


 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 24 January 2007