Contingency
51. No
final decision has been taken on the size of contingency which
should be allowed for the Games. The bid document gave a contingency
figure for LOCOG of 4% of its total expenditure, namely $105 million
at 2004 prices;[106]
this would translate to £87 million from its overall budget,
allowing for inflation and the £1 to $1.6 exchange rate used
in the Candidature File. The contingency allowed for projects
funded from the Public Sector Funding Package - principally construction
projects - was calculated individually and ranged from 20% to
23% for each.[107]
52. Discussion
now centres on whether a "programme contingency" should
be applied on top of the various project contingencies already
allowed for, and what the size of that contingency might be. The
Secretary of State told us that programme contingency had not
been part of the original advice in drawing up the original bid,
but she believed that there was "broad consensus" now
that it was necessary (and she confirmed that she was part of
that consensus);[108]
and she added that that view was supported by KMPG, who had advised
DCMS on reviewing the costs of the Games project. [109]
53. The question
of what level of contingency would be appropriate is disputed.
The Mayor of London has stated on the Today programme on
BBC Radio 4[110] that
20% should be the maximum figure for programme contingency, although
he indicated to the London Assembly that the Olympic Delivery
Authority favoured 30%.[111]
The Treasury has produced guidance, in the form of supplements
to the Green Book,[112]
on adjustments which should be made to estimates of a project's
costs, benefits and duration to allow for "optimism bias"
(defined as "a demonstrated, systematic tendency for project
appraisers to be overly optimistic"). That Treasury guidance,
which draws on advice provided by consultants,[113]
proposes adjustment percentages for different types of project,
ranging from single-figure percentages for low-level capital expenditure
projects to 51% for "non-standard building" projects
and 66% for "non-standard civil engineering" projects.
Footnotes in the guidance point out that these are indicative
starting values.
54. The Management
Statement and Financial Memorandum which governs the ODA instructs
it to comply with Green Book requirements.[114]
Depending on how the Olympic project is categorised, what the
final cost is, and whether Treasury guidance is adhered to rigidly,
the programme contingency could approach £2 billion. The
Mayor of London has publicly expressed reservations about the
principle of announcing a contingency, believing that to do so
encourages overspend; and the Secretary of State told us that
"the Mayor is absolutely right that we will take every available
step to avoid and prevent a contingency being translated into
a cost".[115]
The Mayor has also acknowledged
that he is in direct disagreement with the percentage figure proposed
by the Treasury, saying that "there are no circumstances
under which I'd agree to a contingency of that size".[116]
The Secretary of State has made it clear, however, that the final
decision on the level of contingency is a matter for the Government.[117]
55. The Committee
questions the rationale for allowing for programme contingency
on top of project contingency, especially at a percentage as high
as that proposed in Treasury guidance. We find it difficult to
see how a programme contingency of any substance, rather than
simply being prudent, does not run the risk in itself of escalating
the costs. We note that programme contingency was not included
in advice to those responsible for co-ordinating the bid but that
there is now an informed consensus that it should be included.
This new issue of additional 'programme contingency' gives the
impression, rightly or wrongly, that the initial advice upon which
DCMS relied appears to have been deficient; and we believe that
the Treasury could and should have drawn attention to this alleged
deficiency before the bid was submitted.
Given the possible scale
of such a new provision, the rationale for 'programme contingency'
should be thoroughly explained, with practical reference to other
major building projects around the world, and the professional
advice to the Treasury and DCMS (including that of KPMG) to justify
this should be published for the benefit of public understanding.
Cost increases: the £900
million identified so far
56. The
Secretary of State instituted a fundamental review of the costs
of the Games immediately after London had been selected as Host
City; and KPMG consultants were engaged in October 2005 to support
that review.[118] KPMG's
role was "to re-assess costs to ensure that there is a sound
cost baseline and to help identify the scope for savings in potential
costs with a view to keeping costs down".[119]
That work is largely complete, although the overall cost review
is continuing.[120]
The Secretary of State said that the re-assessment had confirmed
that whereas core cost estimates of the venues were unchanged,
increases in core expenditure were to be anticipated in other
areas.[121]
57. There is now
a concentrated effort within Government to quantify the real costs
of the Games and to set a budget for the ODA. That work is expected
to conclude "soon" and the Secretary of State has undertaken
to report to Parliament on the findings.[122]
The review has already identified £900 million of extra costs
which relate exclusively to the Olympic Park and which bring the
Public Sector Funding Package from the £2.375 billion agreed
at the time of the bid up to £3.3 billion. This £900
million increase takes into account increases in commodity prices
as well as adjustments to transport figures "so that they
reflect 2012 prices" and a revised estimate for construction
inflation.[123] We
have since noted an indication by the Secretary of State that
"the additional cost of the site security of the Olympic
Park
was included in the £900 million increase
announced to the Select Committee on 21 November 2006".[124]
58. The £900
million increase also reflects the cost of cost control itself.
In August 2006, the ODA appointed the CLM Consortium as Delivery
Partner to "programme and project manage the whole procurement
construction cycle, from design to post-2012 transformation".[125]
The Secretary of State told us that the ODA, when established,
had concluded that further expenditure was needed "to provide
the level and quantity of expertise and skill necessary to deliver
the project
and to undertake effective project
and programme management and cost control".[126]
A further £400 million is therefore being invested "in
order to secure the services of the delivery partner" and
also to cover "costs of site mobilisation and the costs of
additional staff required by the ODA itself".[127]
A substantial extra sum, not provided for in the initial bid,
is to be paid to the Delivery Partner to provide effective management
and cost control. We welcome the determination to ensure proper
delivery of the 2012 London Olympics. However, we are surprised
that, given the original assurances about the rigour of the budgeting
process, it is only now seen to be necessary to include this additional
element of control and that it is such a significant cost. We
can only conclude that cost control procedures were not fully
thought through at the time that the bid was submitted. We call
upon the Government to provide a detailed explanation of how the
figure of £400 million for the Delivery Partner was arrived
at, including any total cost of construction which has been used
in arriving at this fee. We further call for the main terms of
the agreement with the Delivery Partner to be made public.
59. The £900
million increase already announced is not the final say: the Secretary
of State added that "there are also further funding requirements
not yet translated into firm costs which are a matter for discussion
in Government".[128]
These further funding requirements include costs of security,
contingency and tax liability, each of which we have discussed
above. Clarification of these further funding requirements is
essential when the Secretary of State reports to Parliament, as
promised, on the findings of the cost review in train. The Secretary
of State also undertook to disclose as much information as possible
to the Committee and to return at any time to brief us further
on costings.[129] We
welcome the Secretary of State's readiness to provide as much
information as possible to the Committee. We recommend that, given
recent controversy about the cost of the Games, the Secretary
of State's report to Parliament on the conclusions of the cost
review currently under way is as comprehensive as possible and
should be in the form of an Oral Statement.
60. We note the
statement made by the Secretary of State to the Committee in October
2005 that "I can confirm again the rigour which we are applying
to the costs in order that they are contained within that expenditure
limit" [£2.375 billion].[130]
Similar statements were made later in 2005.[131]
The Committee is disturbed that such statements have been disproved
in such a relatively short space of time. It is particularly ironic
that part of the extra costs already identified will be incurred
in paying a delivery partner to exercise cost control.
61. The Committee
is concerned about the distance between the figures submitted
in the bid and the true costs, which will not become evident until
after the Games. We believe that everyone involved should draw
lessons from this in terms of project appraisal, management and
communication at this relatively early stage so that there is
no repetition which would prejudice public support for the Games,
their success or their legacy.
62. The Accounting
Officer for the Government Olympic Executive (essentially the
unit within DCMS which is responsible for developing policy on
the 2012 Games) outlined a number of budgetary control procedures
used in relation to the Games. The Olympic Board itself, comprising
the Secretary of State at DCMS, the Mayor of London, the Chair
of the British Olympic Association and the Chair of LOCOG, is
responsible for approving and analysing the ODA and LOCOG budgets
before they are set. The Olympic Programme Support Unit, an independent
body of secondees from stakeholders which provides secretariat
and monitoring functions for the Olympic Board,[132]
provides a monthly analysis of progress in expenditure and delivery;
and Treasury consent is required for ODA projects costing more
than £20 million.[133]
63. Importantly,
in our view, there is external scrutiny. The Office of Government
Commerce (OGC) provides continuing oversight on risk within the
project;[134] and the
Secretary of State confirmed to us that the National Audit Office
will have a particular role in relation to value for money, possibly
including examination of the process used to generate financial
estimates.[135] We
stress the value of external assessment in building public confidence
that money is being spent properly, and we particularly welcome
the involvement of the National Audit Office.
56 Q 6; also DCMS memorandum para 3.5, Ev 56 Back
57
Q 6 Back
58
Candidature File, section 6.5.3 Back
59
Includes national government subsidies, disposal of assets and
other sources Back
60
TOP - The Olympic Partners programme Back
61
Q 17 Back
62
Q 17 Back
63
Daily Telegraph, "2012 funding alliance", 9 November
2006 Back
64
The first invitations were announced for firms in the banking
and insurance sectors in October 2006: See London 2012 Media Release,
28 September 2006. Back
65
Ev 35 Back
66
Q 20 Back
67
Q 17 Back
68
Q 6 Back
69
Q 182 Back
70
General Purpose Standing Committee No.1 ; Report No. 11, Olympic
Budgeting, Paper 430 Back
71
Ofcom Press Release, 17 November 2006 Back
72
DCMS Press Release 146/06, 17 November 2006 Back
73
Q 19 Back
74
Q 184 Back
75
Information supplied by LOCOG Back
76
Ev 35 Back
77
Ev 89 Back
78
Q 21 Back
79
Q 185 Back
80
Candidature File, Table 8.4.3 Back
81
Ev 2 Back
82
Q 143 Back
83
DCMS Annual Report and responsibilities of the Secretary of
State, HC 1551-i (Session 2005-06), oral evidence taken on
25 July 2006, Q 21 Back
84
Q 198 Back
85
Q 143 Back
86
HC 552-i, Session 2005-06; also Ev 3 Back
87
Q 143 Back
88
Ev 73 Back
89
Candidate File Table 6.6.1: rising to just over £30 million
if the assumed uplift for inflation is applied. Back
90
HC Deb, 5 December 2006, Col. 287W Back
91
Q 143; see also supplementary memorandum from the Secretary of
State, Ev 73 Back
92
See http://www.london.gov.uk/assembly/assemmtgs/2006/mqtnov15/minutes/transcript1.pdf Back
93
Q 8 Back
94
See Annex A to DCMS memorandum, Ev 59-60. Back
95
HC Deb 7 December 2006, cols. 596-7W Back
96
See The Times, 22 November 2006 Back
97
HC Deb, 6 November 2006, col. 565 Back
98
Q 155 Back
99
Q 161 Back
100
Ev 73 Back
101
http://www.bbc.co.uk/radio4/today/listenagain/ztuesday_20061107.shtml Back
102
QQ 155 and 161 Back
103
See transcript: http://www.london.gov.uk/assembly/assemmtgs/2006/plenaryexnov15/mins-app2.pdf Back
104
Q 156 Back
105
QQ 155 and 160 Back
106
Candidate File, Table 6.6.1 Back
107
Q 171 Back
108
Supplementary memorandum from the Secretary of State: Ev 73 Back
109
Q 171 Back
110
22 November 2006 Back
111
Mayor's Question Time, 15 November 2006 Back
112
The Treasury Green Book provides guidance for Government bodies
on economic appraisal of projects; see www.hm-treasury.gov.uk/greenbook. Back
113
Review of Large Public Procurement in the UK, Mott MacDonald
(2002): see www.hm-treasury.gov.uk/greenbook Back
114
HC Deb, 22 November 2006, col. 115W Back
115
Q 171 Back
116
Interview on BBC Radio 4 Today programme, 22 November 2006
Back
117
HC Deb, 14 December 2006, col. 1237W Back
118
Q 144: HC Deb, 4 December 2006, col. 99W Back
119
Supplementary memorandum from the Secretary of State, Ev 72 Back
120
Mr Higgins, Chief
Executive of the ODA, told us in October 2006 that KPMG had "essentially
finished their work"; Q
12 Back
121
Further memorandum from the Secretary of State, Ev 72 Back
122
Q 138 Back
123
Q 143 Back
124
HC Deb, 5 December 2006. col. 287W Back
125
Ev 2 Back
126
Supplementary memorandum from the Secretary of State, Ev 74 Back
127
QQ 143 and 180; See also footnote to Q 143 Back
128
Q 143 Back
129
Q 143 Back
130
Q 117, HC 552-ii, Session 2005-06 Back
131
See for example HC Deb, 19 December 2005, Col. 2522W Back
132
Memorandum from the Olympic Lottery Distributor, Ev 26 Back
133
Q 172 Back
134
The OGC conducted a Gateway Review of the project in April 2006.
The Review's conclusions were "positive": see summary
of the meeting of the Olympic Board on 24 May 2006, London 2012
website Back
135
Q 173 and Ev 72; see also supplementary memorandum from the Secretary
of State, Ev 72 Back