Select Committee on Defence Third Report

 
 

 
Report


Introduction

1. The Winter Supplementary Estimates for the Financial Year 2006-07 were laid before the House on 21 November 2006.[1] The Ministry of Defence (MoD) is seeking a net increase in resources of £1,599.982 million—in cash terms a net increase of £1,699.982 million.[2]

2. The Supplementary Estimate includes funds taken up from some of the MoD's under-spends in previous years under the End Year Flexibility arrangements—£120 million resource and £72 million capital. It also splits out Defence Estates net expenditure into its gross expenditure and appropriations-in-aid components, correcting an error in the Main Estimates. And it reallocates funds between Top Level Budgets mainly to reflect changes in the way in which the MoD accounts for its fixed assets.[3]

3. Most of the additional funds requested in the MoD's Winter Supplementary Estimate are to meet the additional costs of operations in Iraq and Afghanistan, which the MoD estimates to be £1,040 million in resources and £360 million in capital in the current financial year.[4]

4. The House of Commons will be asked to approve the Winter Supplementary Estimates on Thursday 7 December.

Approval of expenditure for operations

5. The MoD does not make provision for the cost of operations in the Main Estimates, on the ground that the unpredictable nature of operations makes it difficult to forecast their cost with accuracy at the beginning of the financial year. Until this year, it has waited until the Spring Supplementary Estimates in February to present estimated costs of operations.

6. In our report on the Spring Supplementary Estimate 2005-06, we said that we considered the arrangement by which the MoD waited for the Spring Supplementary Estimates before seeking Parliament's approval of expenditure on operations to be unsatisfactory; and we recommended that in future provision for already commenced operations be made in the Main Estimates in the usual way, if necessary with a large element for contingency.[5] The Government's response did not accept this recommendation, arguing that costs were difficult to forecast in fast moving operational circumstances and Supplementary Estimates were the first occasion when the Department could reach a reasonably firm conclusion. However, in the light of our recommendation, the Government undertook to seek provision for conflict prevention for commenced operations in the 2006-07 Winter Supplementary Estimate, rather than waiting for the Spring Supplementary Estimates as in the past.[6]

7. In our report on the Main Estimates 2006-07, we recommended that the MoD reconsider whether provision for commenced operations might be included in the Main Estimates in future.[7] The Government's response merely reiterated that "Requests for resources for Conflict Prevention have normally been made in the Supplementary Estimates, because costs are difficult to forecast in fast moving operational circumstances".[8] We find this explanation insufficient. Military operations are by their nature unpredictable and it would be understandable if estimates made at the beginning of the financial year required revision. But the MoD will undoubtedly have made internal planning assumptions about the costs of the operations in Iraq and Afghanistan and we believe these should be shared with Parliament.

8. While we commend the MoD for bringing forward the presentation of estimates on the cost of operations in Iraq and Afghanistan to the Winter Supplementary Estimates, we still consider that there ought to be provision for the cost of commenced operations in the Main Estimates. We repeat our earlier recommendation that the MoD consider this. We expect this change to be made unless a more compelling argument can be offered for not doing so.

Approval of the costs of Balkans Operations

9. Our argument that the cost of commenced operations could, and should, be presented in the Main Estimates is strengthened by the fact that the Government manages to make provision for the cost of operations in the Balkans in the Main Estimates—albeit in those presented by the Foreign and Commonwealth Office (FCO) rather than by the MoD. The current practice is for the FCO to seek funding for peacekeeping in the Balkans in the Main Estimates, and for some of this to be transferred to the MoD in the Spring Supplementary Estimates.

10. In our report on the Spring Supplementary Estimate 2005-06, we stated that we failed to see why funding was not sought by the MoD in the first place and recommended that in future provision be set out in the MoD's Main Estimate.[9] The Government did not accept this recommendation, on the grounds that the FCO had always been the lead department for administering the Global Conflict Prevention Pool, that managing the UK's peacekeeping activities as a whole was beneficial and that the current arrangements allowed flexibility to respond to a volatile international scene.[10]

11. In our report on the Main Estimates 2006-07, we stated that, while we appreciated the value in managing peacekeeping activities centrally, we could not see why this should preclude separation of the anticipated costs by department. We recommended that the Government reconsider this.[11] In its response, the Government said it would reconsider this in the preparation of the Main Estimates 2007-08.[12] We repeat our earlier recommendation that provision for operations in the Balkans should in future be set out in the MoD's Main Estimate, and hope that this will be done in the Main Estimates 2007-08.

12. In the meantime, it was not clear to us why the transfer to the MoD had to wait for the Spring Supplementary Estimates, rather than appearing in this Winter Supplementary Estimate, alongside the costs of operations in Iraq and Afghanistan. The MoD's supplementary memorandum states:

Unlike operations in Iraq and Afghanistan, funding for operations in the Balkans comes from the Peacekeeping element of the Conflict Prevention Pools. This funding is sought from the FCO in the Spring Supplementary Estimates, when they will have received full funding for Global Conflict Prevention Pool activities.[13]

We do not find this a sufficient explanation.

Estimated costs of operations in 2006-07

13. The Winter Supplementary Estimate estimates the additional costs of operations in Iraq and Afghanistan in 2006-07 as £1,040 million in resources and £360 million in capital.[14] The MoD's Estimates Memorandum breaks this down as follows:[15]

Table 1: The cost of operations in Iraq and Afghanistan
Cost Type  Iraq

Actual £ m

2005/06  

Iraq

Forecast £ m

2006/07  

Afghanistan

Actual £ m

2005/06  

Afghanistan

Forecast £ m

2006/07  

Resource - Direct       
Personnel 94  77 9  32 
Stock / other consumption  219 191  57 103  
Infrastructure costs  82 106  11 73  
Equipment support costs  220 189  24 81  
Other costs and services  111 112  38 67  
Income foregone 10  8  
Total 736  680 147  360 
Capital      
Capital Additions 160  180 51  180 
Total 160  180 51  180 
Grand Total  896 860  198 540  

Source: Ministry of Defence

14. The costs of operations are identified on the basis of net additional costs. Expenditure such as wages and salaries for permanently employed personnel are not included, as these costs would have been incurred anyway. Costs of activities such as training and exercises which have been cancelled owing to operational commitments are deducted.[16]

15. The MoD's supplementary memorandum states that, of the estimated personnel costs, £29 million is attributable to civilian personnel (£22 million for Iraq and £7 million for Afghanistan).[17] While the Department's estimate is that additional personnel costs in Iraq will be £17 million less this year than last, civilian manpower costs will increase from £14 million to £22 million.[18] Civilian manpower costs will account for over 28% of the MoD's additional manpower costs in Iraq this year, in contrast to only 15% in 2005-06, suggesting that the role of MoD's civilian personnel in Iraq is becoming increasingly significant.

16. The MoD's supplementary memorandum explains that the infrastructure costs cover estates and facilities management services, building rental or maintenance and provision of IT and communications. Examples of current major projects are, in Iraq, the development of the single Contingency Operating Base at Basrah Air Station, and a water generation plant; and, in Afghanistan, the upgrade of living accommodation at Kandahar Airfield and Camp Bastion, upgraded hospital facilities at Camp Bastion, and the relocation of the UK Task Force HQ to Lashkar Gah.[19]

17. Other costs and services include utility costs, personnel and freight movements, hire of transport, staff training, medical treatment, welfare services, food and administration costs.[20]

18. The MoD's Estimates Memorandum states that the MoD has not included a contingency in the Winter Supplementary Estimate, which will be updated at the Spring Supplementary Estimates if required.[21] We note that last year the MoD included a large element for contingency —£146 million—which in the event was not needed (see Table 3 and paragraph 26 below).

19. The Estimates Memorandum also points out that the MoD has not included in the Winter Supplementary Estimate an estimate for indirect resource costs (stock write-off, provisions, depreciation, cost of capital charges etc). These will be funded by an internal transfer from the main 'defence capability' Request for Resource estimate, which will be requested at the Spring Supplementary Estimates.[22] This could be significant. In 2005-06, indirect resource costs of Iraq and Afghanistan operations were £63 million.[23]

20. Nor has the MoD included in the Winter Supplementary Estimate the costs of the tax-free bonus to personnel on designated operational deployments, announced by the Secretary of State for Defence on 10 October 2006.[24] This is expected to cost around £60 million a year. Provision for the costs of the operational allowance in the current year will be requested in the Spring Supplementary Estimates.[25]

21. It seems likely, therefore, that the actual additional costs of operations in Iraq and Afghanistan in 2006-07 will exceed the amounts requested in the Winter Supplementary Estimate.

Outturn costs of operations in 2005-06

22. In our report on the Spring Supplementary Estimate 2005-06, we pointed out that the MoD's Annual Report and Accounts 2004-05 presented little more than an overall outturn figure for the costs of operations in the Balkans, Afghanistan and Iraq, and recommended that in future the Annual Report and Accounts should contain significantly more detailed information on the cost of operations.[26] The Government accepted this recommendation.[27]

23. The overall net additional cost of these and other operations in 2005-06 was £1,266 million, of which £957 million was for operations in Iraq, £199 million for operations in Afghanistan, and £63 million for operations in the Balkans (Bosnia and Kosovo). The Annual Report and Accounts first breaks this down as follows: [28]

Table 2: Costs of operations 2005-06
Net Additional Costs of Operations 2005-06 (£ million)  
 Final Voted Provision  Outturn Variation  
Resource     
Iraq (Operation TELIC)  838 797  (41) 
Afghanistan (Operation HERRICK)  150 148  (2) 
Balkans (Operation OCULUS)  64 63  (1) 
Programme Expenditure (African and Global Pool)  49 47  (2) 
Total Resource  1,101 1,055  (46) 
Capital     
Iraq (Operation TELIC)  260 160  (100) 
Afghanistan (Operation HERRICK)  70 51  (19) 
Balkans (Operation OCULUS)  0  
Total Capital  330 211  (119) 
Total Net Additional Cost of Operations  1,431 1,266  (165) 

Source: Ministry of Defence

24. The Annual Report and Accounts 2005-06 also provides a much more detailed breakdown, as follows:[29]

Table 3: Costs of operations in Iraq, Afghanistan and the Balkans 2005-06
 
Total Outturn 2005-06 ( £000)  
 Iraq  Afghanistan  Balkans  
 Total Outturn  Total Departmental Allocation

2005-06  

Outturn

2004-05  

Total Outturn  Total Departmental Allocation

2005-06  

Outturn

2004-05  

Total Outturn  Total Departmental Allocation

2005-06  

Outturn

2004-05  

Resource Cost (by area)           
Direct costs             
Service manpower 80,237  80,278 115,590  7,575 7,172  14,898 11,509  11,640 15,960  
Civilian manpower 14,213  11,688 13,889  1,627 1,116  996 4,949  7,336 7,614  
Infrastructure costs 81,407  84,082 87,550  10,522 25,663  7,197 12,633  13,954 15,912  
Equipment support 220,232  243,097 198,273  24,399 14,832  6,488 7,840  7,339 4,399  
Other costs and services 111,186  103,984 110,169  37,595 46,070  19,863 11,824  16,935 32,480  
Income 10,054  3,812 2,110  7,792 5,917  (2,054) 2,369  (9,209) (8,681)  
Stock consumption 218,920  202,936 156,280  57,171 33,918  10,178 9,332  8,566 7,642  
Contingency -  55,000 -  14,000  -  -  
Indirect Costs            
Stock write-off  51  44 1,559  (2) (2)  -  -  
Provisions 1,560  3,000 6,192  -  (437)  87 299  
Depreciation and amortisation (inc UORs)  33,611 15,577  41,270 1,255  1,596 177  2,376 6,944  8,608 
Fixed asset write-off 21,848  30,000 8,000  -  -  -  
Cost of capital 4,441  4,594 6,186  183 162  185 284  408 444  
Total 797,760  838,092 747,068  148,117 150,444  57,937 62,679  64,000 84,677  
Capital cost (by area)             
Capital addition (inc UORs and Recuperation)  159,838 199,944  162,862 51,231  53,053 9,097  174 -  2,430 
Net Book Value of fixed asset disposals   -  -  -  -  (547) 
Contingency -  60,000 -  17,000  -  -  
Total 159,838  259,944 162,862  51,231 70,053  9,097 174  - 1,883  
Total by Operation 957,598  1,098,036 909,930  199,348 220,497  67,034 62,853  64,000 86,560  

Source: Ministry of Defence

25. We commend the MoD for including considerably more detail on the cost of operations in the Annual Report and Accounts 2005-06, and recommend that it continue this practice in future.

26. We note that the outturn for 2005-06 was significantly less than the final voted provision: the MoD over-estimated the cost of operations by £165 million (12%). This included an over-estimate of capital costs by more than 36%. We appreciate that the cost of operations is hard to estimate, but the variation between anticipated and actual capital spend is surprising, particularly since the estimates were not made last year till more than half way through the year (and presented to the House in the Spring Supplementary Estimates in February). Where there is significant variation in the cost of operations between voted provision and outturn in future, we shall expect the Annual Report and Accounts to contain some explanation of it, just as there is for significant variations against budgets in other parts of the Defence Estimate. However, we fully accept that, if the MoD agrees to publish estimates of the additional costs of commenced operations at the beginning of the financial year, as we recommend, the scope for error in those estimates might be increased. We accept that in following this approach the MoD might subsequently need to seek additional funds to correct its initial estimates, by seeking a Supplementary Estimate later in the year.

Votes A

27. In addition to the Winter Supplementary Estimate, the MoD has also laid a Supplementary Estimate to the Votes A for the financial year 2006-07.[30]

28. The Votes A provide the mechanism by which Parliament exercises control over the maximum number of personnel in the Armed Forces. The Votes A for the financial year 2006-07, agreed by the House on 20 March 2006, provided for a maximum of 42,050 personnel serving in the Royal Navy and Royal Marines, and 16,550 in the Reserve Naval and Marine Forces.[31] The Supplementary Estimate increases the maximum number of personnel in the Royal Fleet Reserve Marine Other Ranks category from 1,200 to 1,350, raising the maximum for the Reserve Naval and Marine Forces to 16,700 overall. The MoD's Estimates Memorandum states that this increase is caused by "higher than anticipated numbers of Regulars leaving the Royal Marines and automatically entering the Reserve this year".[32]

29. An increase in 150 reservists is not a significant number, increasing the Tri-Service Votes A maxima by only 0.04%.[33] But it is worrying that more Regulars have been leaving the Royal Marines than anticipated. Evidence provided by the MoD to our inquiry into the MoD's Annual Report and Accounts 2005-06 showed that the voluntary outflow rates for Royal Navy and Royal Marine Ratings has significantly exceeded target for the past three years, and identified Royal Marine Junior Ranks as a pinchpoint trade.[34] The recent report from the National Audit Office on Recruitment and Retention in the Armed Forces states that, as at 1 April 2006, there was a shortfall of 9.6% of Royal Marines Other Ranks.[35]

30. The Estimates Memorandum states that the MoD has proposed to the Armed Forces Pay Review Body measures that aim to improve the retention within the Royal Marines. We welcome the MoD's proposal of financial incentives to aid retention in the Royal Marines. We shall be monitoring the retention figures closely.

Conclusion

31. While we continue to have some concerns about the manner in which the MoD seeks parliamentary approval for the costs of operations, we recommend that the House of Commons approve the request for resources set out in the MoD's Winter Supplementary Estimate.


Central Government Supply Estimates 2006-07 Winter Supplementary Estimates and New Estimates, HC 2, November 2006 Back

HC Deb, 21 November 2006, col 29WS; and HC 2, p 8, Table 1.3, and pp 171-184. The £1,599.982 million additional funding comprises £1,592.272 million additional DEL cited in the Written Statement on the Supplementary Estimates (for Request for Resources 1 and 2) and £7.710 million additional AME (for Request for Resources 3). Back

See Ev 1-3 and Ev 6-8 Back

HC 2, p 171-172 Back

Defence Committee, Fourth Report of Session 2005-06, Costs of Operations in Iraq and Afghanistan: Spring Supplementary Estimate 2005-06, HC 980, para 15 Back

Defence Committee, Fifth Special Report of Session 2005-06, Costs of Operations in Iraq and Afghanistan: Spring Supplementary Estimate 2005-06: Government's Response to the Committee's Fourth Report of Session 2005-06, HC 1136, Appendix, para 4 Back

Defence Committee, Ninth Report of Session 2005-06, Ministry of Defence Main Estimates 2006-07, HC 1366, para 9 Back

Defence Committee, Tenth Special Report of Session 2005-06, Ministry of Defence Main Estimates 2006-07: Government Response to the Committee's Ninth Report of Session 2005-06, HC 1601, para 2 Back

HC (2005-06) 980, para 17 Back

10  HC (2005-06) 1136, paras 11-14 Back

11  HC (2005-06) 1366, para 12 Back

12  HC (2005-06) 1601, para 3 Back

13  Ev 7, response 7 Back

14  HC 2, p 171-172 Back

15  Ev 3-4, para 5.1 Back

16  Ministry of Defence Annual Report and Accounts 2005-06, HC (2005-06) 1394, p 201, para 2.3 Back

17  Ev 7, response (6) (i) Back

18  See Table 1 and Table 3; and Ev 3-4, para 5.1 Back

19  Ev 7, response (6) (ii) Back

20  Ev 7, response (6) (iii) Back

21  Ev 3, para 5.1 Back

22  Ev 3-4, para 5.1 Back

23  See Table 3 below and HC (2005-06) 1394, p 201 Back

24  HC Deb, 10 October 2006, col 175 Back

25  Ev 4, para 8.1, and Ev 8, response (8) Back

26  HC (2005-06) 980, para 10 Back

27  HC (2005-06) 1136, Appendix, para 2 Back

28  HC (2005-06) 1394, p 128, para 260 and Table 11 Back

29  HC (2005-06) 1394, p 201 Back

30  Ministry of Defence Votes A 2006-07 Supplementary Votes, HC 18 Back

31  Ministry of Defence Votes A 2006-07, HC (2005-06) 869 Back

32  Ev 5, para 14.1 Back

33  Ibid. Back

34  Defence Committee, Second Report of Session 2006-07, Ministry of Defence Annual Report and Accounts 2005-06, HC 57, Ev 27; and HC (2005-06) 1394, p 140, para 282 and Table 20 Back

35  National Audit Office, Recruitment and Retention in the Armed Forces, HC (2005-06) 1633-I, 3 November 2006, p 14, Table 3 Back


 

 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index  

 
© Parliamentary copyright 2006 
Prepared 7 December 2006