5  Conclusion

92. Nine years on from the Strategic Defence Review, the Army's requirement for a medium-weight vehicle remains unmet. Despite having spent £188 million on the TRACER and MRAV programmes and at least £120 million so far on FRES, the solution is nothing more tangible than a concept.

93. This is a sorry story of indecision, constantly changing requirements and delay. We are concerned that the FRES requirement may simply be unachievable without a major technical breakthrough. The tension between the survivability and deployability is particularly acute: satisfying both requirements may prove impossible. It is high time the MoD decided where its priorities lay. We shall take further evidence on the FRES programme in the Autumn of this year.


 