1. Analysis of the technologies, capabilities
and issues associated with Key User Requirements identified critical
technologies and risks that must be mitigated in order to deliver
the overall FRES capability. The main aims of the FRES TDP programme
are to:
Serial | Title
| Contractor | Status
|
1 | Stowage and Capacity |
Dstl | Contract placed February 2005 Completed in May 2006
|
2 | Hard Kill Defensive Aid System
| Akers Krutbruk | Contract placed May 2005 Completion due December 2006
|
3 | Chassis Concept TDP (AHED)
| General Dynamics | Contract placed August 2005 Completion due February 2007
|
4 | Chassis Concept TDP2 (SEP)
| BAES | Contract placed December 2005 Completion due September 2007
|
5 | Electronic Architecture TDP 1
| Lockheed Martin | Contract placed August 2005 Completion due March 2007
|
6 | Electronic Architecture TDP 2
| Thales | Contract placed August 2005 Completion due March 2007
|
7 | Electric Armour | Lockheed Martin/Insys
| Contract placed December 2005 Completion due June 2007
|
8 | Integrated Survivability
| Thales | Contract placed December 2005 Completion due November 2006
|
9 | Gap Crossing | BAES
| Contract placed December 2005 Completion due October 2007
|
| | |
|