Select Committee on Defence First Report


Conclusions and recommendations


1.  We congratulate the DPA on achieving its Key Targets and the MoD's Public Service Agreement Target for Acquisition in 2005-06. (Paragraph 8)

2.  We are pleased to see that the MoD is getting a better grip on programme time schedules. Off-the-shelf procurement, where available, can reduce the risk of programme time slippage. We look to the MoD to ensure that project teams are made aware of the lessons from the off-the-shelf procurement of the Javelin medium range anti-tank guided weapon, as this appears to be a good example of the benefits which can be delivered from this procurement route. (Paragraph 13)

3.  While cost growth on defence equipment projects in 2005-06 was below the target, we have concerns that the main reason for this was reduction in the quantity of equipment ordered. Trade-offs between cost, time and performance are part of the Smart Acquisition process, but we expect our Armed Forces to receive equipment in the numbers required and with the capability to do the task required of it. Meeting Key Targets should not be given priority over meeting the requirements of our Armed Forces. (Paragraph 17)

4.  We are concerned to hear that, in the current financial year, potential cost increases on the Astute submarine and Type 45 Destroyer programmes are putting pressure on the DPA's Key Target covering cost growth, and that the Key Target covering asset deliveries is at risk. We look to the MoD to monitor performance closely against these two targets, and to seek to limit potential further cost growth on the Astute and Type 45 programmes. We will also be looking closely at the Major Projects Report 2006 to ensure that the cost increases on these two programmes are not symptomatic of wider problems within the MoD's procurement process. (Paragraph 18)

5.  Work to merge the Defence Procurement Agency and the Defence Logistics Organisation is underway and, on current plans, the new organisation will begin operating on 2 April 2007. The MoD is managing the merger as a project with four phases and target dates for the completion of each of these phases. Given the importance and scale of the merger, we recommend that the MoD provide us with quarterly progress reports. (Paragraph 24)

6.  A key objective of the new Defence Equipment & Support organisation is to improve the management of acquisition on a through-life basis. We are pleased to learn that there will be new targets to measure the performance in this area and a target covering how quickly the new organisation responds to the needs of our Armed Forces. Given some of the substantial cost increases and time slippage experienced by some equipment programmes in the past, we expect the MoD to continue to monitor its performance at procuring equipment to time, cost and quality, and for the performance data to be published on an annual basis as it is now. Otherwise, there is a risk that poor procurement performance could be buried in long-term project management data. (Paragraph 26)

7.  The success of the Defence Equipment & Support organisation will depend on whether the new organisation has the staff with the required skills to improve Through Life Capability Management and provide more agility in responding to the needs of the Armed Forces. Much work is being undertaken to identify the current skills gaps and to address these through training or external recruitment, and we welcome this. It is essential that the MoD commit the investment required to address the skills gaps identified. (Paragraph 31)

8.  We recognise that collocating the Defence Logistics Organisation with the Defence Procurement Agency is a sensible step, given that the aim of the merger of these two organisations is to improve Through Life Capability Management. The merger will result in a substantial number of job losses and the collocation will have a major impact, particularly on those who work for the Defence Logistics Organisation and their families. We expect the MoD to continue to consult with the Trades Unions during this period of change and to provide appropriate support to those affected. (Paragraph 34)

9.  We would expect the merger of the Defence Procurement Agency and the Defence Logistics Organisation to deliver substantial efficiency gains. We look to the MoD to identify what efficiency gains are likely to be delivered, and to monitor whether these gains are achieved. (Paragraph 35)

10.  The new Defence Equipment & Support organisation will be huge, in terms of both manpower and expenditure. Its roles of procuring equipment and managing equipment through-life are key to ensuring the effectiveness of our Armed Forces. We are concerned that, as the organisation will not have agency status, its activities may lose transparency. We recommend that the new organisation publish an annual report so as to allow proper public accountability, and parliamentary scrutiny in particular. (Paragraph 38)

11.  We were impressed during our visit to Barrow in September 2006 with the commitment of BAE Systems' management and workforce to deliver the first Astute class submarine before the revised MoD date of 2009. (Paragraph 46)

12.  We are surprised to learn that the prices for boats 2 and 3 have still to be agreed and, as a consequence, the financial liability to the MoD is unknown. We look to the MoD to ensure that the negotiations on the prices for these boats are resolved as soon as possible. Lessons must again be learned from this programme, as letting contracts without pinning down prices, and negotiating prices when equipment is at an advanced stage of manufacture, cannot be considered 'Smart Acquisition'. (Paragraph 47)

13.  The delay in agreeing prices on Astute boats 2 and 3 is delaying the placing of a contract for boat 4. This, in turn, has an impact on the submarine skills base in the UK. We are examining this issue as part of our inquiry into the Future of the Strategic Nuclear Deterrent: the manufacturing and skills base and plan to report at the end of the year. (Paragraph 48)

14.  The price for the two future aircraft carriers had yet to be agreed. The MoD has sensibly commissioned an independent financial review to advise on what the carriers 'should' cost, and it is to be hoped that this will lead to agreement on a challenging contractual price which industry will seek to beat. We look to the MoD to ensure that negotiations on price are moved forward as quickly as possible so that the main investment decision on the future carriers can be taken. (Paragraph 54)

15.  Discussions on the Future Carrier programme will be crucial to the future of the UK shipbuilding industry. The programme is a key element of the Maritime Industrial Strategy. We will examine the Maritime Industrial Strategy as part of our inquiry looking at the progress of the Defence Industrial Strategy. (Paragraph 56)

16.  We have no doubt that the Minister for Defence Procurement, the Chief of Defence Procurement and MoD officials have made considerable efforts to ensure that the United States are fully aware of the information required by the UK on the Joint Strike Fighter to allow the aircraft to be operated independently. However, it is still uncertain whether the United States is prepared to provide the required information. If the UK does not obtain the assurances it needs from the United States, then it should not sign the Memorandum of Understanding covering production, sustainment and follow-on development. Such an impasse on a procurement programme of such strategic importance to the UK would be a serious blow to UK-US defence equipment co-operation, which has hitherto been of such positive benefit to both our nations. If the required assurances are not obtained by the end of the year, we recommend that the MoD switch the majority of its effort and funding on the programme into developing a fallback 'Plan B', so that an alternative aircraft is available in case the UK has to withdraw from the Joint Strike Fighter programme. We must not get into a situation where there are no aircraft to operate from the two new aircraft carriers when they enter service. (Paragraph 64)

17.  We are concerned to hear that possible changes to the early production of the Joint Strike Fighter aircraft programme could lead to an increase in the price for each aircraft. We look to the MoD to monitor this situation very closely and keep us informed of developments. (Paragraph 65)

18.  There has been a long list of defence equipment projects that have experienced severe problems in terms of cost overruns and time slippage, including Eurofighter Typhoon, Astute submarines and Nimrod MRA4 aircraft. The procurement of eight Chinook Mk 3 helicopters is a case which illustrates the impact that poorly managed procurement can have on operations. Our Armed Forces in Afghanistan and Iraq desperately need heavy lift helicopters, yet eight such helicopters are sitting in hangars in the UK and no-one can tell us when they will be operational. We look to the MoD and Boeing to resolve this problem as quickly as possible. The reputations of both parties have already suffered from this sorry episode. (Paragraph 73)

19.  The Defence Procurement Agency is to be congratulated for its performance, to date, in procuring Urgent Operational Requirements for UK Forces deployed on operations. We consider that there are some important lessons which can be learned from the procurement of Urgent Operational Requirements and applied to mainstream equipment procurement, and we expect the MoD to ensure that this is done. (Paragraph 77)

20.  We think it vital that the actual user of equipment is involved in defining the requirement for both equipment procured through the normal procurement process and equipment procured through the Urgent Operational Requirements process. MoD should have arrangements in place to ensure that the actual user of equipment is consulted and involved in defining the requirement for new equipment. (Paragraph 78)

21.  During our visits to UK Armed Forces in Afghanistan and Iraq before the Summer recess, we were told that additional equipment was required urgently, such as more helicopters. We welcome the Prime Minister's commitment that whatever package of equipment commanders on the ground want will be provided. There will always be a need for requests from the front line to be evaluated by the chain of command, and ultimately approved by Ministers, but this must be done quickly. We note the high satisfaction with the Urgent Operational Requirements process, and look to the Ministry of Defence and the Defence Procurement Agency to rise to the challenge presented by the Prime Minister's commitment, ensuring that requests from the field are processed as quickly as possible. We also look to the Treasury to speed up the approval of the funding for such equipment procurement and to recognise that the MoD will require additional funding to support the equipment once in-service. Service commanders must not be inhibited from asking for equipment required in the field by fears that this will impact on their future budgets. (Paragraph 83)

22.  It is disappointing that modifications are required to the General Service Respirator which will result in a ten month delay in getting the respirator into service. We look to the MoD to ensure that the necessary investment is made, and the required re-trialling undertaken, to ensure that the General Service Respirator is fit for purpose when it enters service. (Paragraph 89)

23.  Given that UK Armed Forces personnel, and police and ambulance personnel, are likely to be working together in the future, we look to the Home Office and the Department of Health to consider the benefits of procuring the same General Service Respirator as is being procured for UK Armed Forces. (Paragraph 90)

24.  The ASUW Littoral Defensive Anti Surface Warfare project will protect Royal Navy ships from emerging threats posed by fast attack craft. We are pleased to see that the project is progressing well and that the MoD is procuring one of the systems off-the-shelf which has already been proven and is in-service with the United States. (Paragraph 95)

25.  The Maritime Composite Training System has the potential to provide flexible and efficient training for Royal Navy personnel. We look to the MoD to claw back some of the slippage that this project has experienced and to ensure that the lessons learned from the use of Earned Value Management techniques on this project are promulgated to other project teams in the Defence Procurement Agency. (Paragraph 101)

26.  The Thermal Sighting System being procured by the MoD will allow the Self Propelled High Velocity Missile system to be operated at night, through cloud or in poor visibility and address a significant capability gap. Changes in the threat mean that 51 of the 134 Thermal Sighting Systems being procured are no longer required. We expect the MoD to identify how these surplus systems might be best used to ensure value for money for the money spent. We also look to the MoD to find an alternative use for the surplus 51 vehicles fitted with the Self Propelled High Velocity Missile system. (Paragraph 106)

27.  There are lessons to be learned from the successful management of smaller-size equipment projects which can usefully be applied to larger equipment projects, and we look to the MoD to ensure that such lessons are promulgated. We are pleased to hear that the MoD is working with the Australian Defence Materiel Organisation and the National Audit Office to identify better ways of defining project complexity and better ways of controlling projects. It is vital that what is learned is fully embedded in the new Defence Equipment & Support organisation, which will be formed following the merger of the Defence Procurement Agency and the Defence Logistics Organisation. (Paragraph 110)



 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 8 December 2006