Select Committee on Defence Written Evidence


Second memorandum from the Ministry of Defence

POST MAIN GATE PROJECT SUMMARY SHEET

  General Service Respirator (GSR)

  Integrated Project Team Responsible: Chemical, Biological, Radiological and Nuclear (CBRN)

  Single Point of Accountability for project capability: Director Equipment Capability (CBRN)

  Senior Responsible Owner for broader capability: Capability Manager (Battlespace Manoeuvre)

SECTION 1: ABOUT THE PROJECT

1a  Project description, progress and key future events

  GSR will replace the in-service, personal issue, S10 respirator, providing more appropriate levels of protection, equipment compatibility and reduced user burden. GSR is currently within the Demonstration Phase, contracted with Scott Health and Safety Ltd, having been selected by competition. The In-Service Date (ISD) is currently forecast for October 2006.

  A quantity of 500 pre-production GSRs have been manufactured for the User Trials. User Trials are now nearing completion—covering Common User Tasks, Special to Arms aspects and extreme climatic conditions. A "hot weather" trial has been scheduled for mid-April 2006 in Australia to confirm the GSR design against specific climatic categories. This trial is being scrutinised by the MoD Ethics Committee to safeguard the interests of the volunteers involved with the trial. The Design Acceptance meeting is set for 3 May 2006 to allow production to commence.

1b  Associated projects
Critical to Achievement of ISD Critical to Initial Gate Requirement
Project TitleForecast ISD Project TitleForecast ISD


1c  Procurement strategy
Contractor(s)Contract Scope Contract TypeProcurement Route
Scott Health & Safety LtdDemonstration and Manufacture
Firm price to October 2007, then fixed price subject to Variation of Price
UK competition

SECTION 2: PROJECT COSTS

2a  Performance against approved cost
millions (outturn prices)Procurement Cost
Current forecast cost  52
Approved cost at Main Gate  65
Variation-13
In-year changes
2b  Reasons for variation from approved cost
Date Variation (£m) Factor Explanation
5 October 2005    3 Technical factorsAdvanced Respirator Test System (ARTS) solution reworked following unforeseen technical problems. Additional costs associated with special users respirator.
10 June 2005-14Procurement strategy Hybrid twin design now on contract, ARTS solution identified and risk reduced.
Historic-2Risk differential Difference between the risk allowed for in the most likely (50%) and the highest acceptable (90%) estimates at Main Gate.
Net Variation-13
2c  Expenditure to date
Expenditure to (£m)7
2d  Years of peak procurement expenditure
2007-082008-09


2e  Unit production cost
Unit Production Cost (£m) Quantities Required
at Main GateCurrent at Main GateCurrent
0.00010.0001309,228 309,228

SECTION 3: PROJECT TIMESCALE

3a  Definition of in-service date
ISD Definition:Achievement of Initial Operating Capability (IOC) defined as the provision of sufficient GSR to support an operational deployment of 26,215 personnel, fully supported (ie logistic support requirements achieved), with mature Lines of Development.
3b  Performance against approved in-service date
Date
Current forecast ISDOctober 2006
Approved ISD at Main GateDecember 2006
Variation (months)-2
In-year changes  0
3c  Reasons for variation from approved ISD
DateVariation (months) FactorExplanation
Historic-2Risk differential Difference between the risk allowed for in the most likely (50%) and the highest acceptable (90%) estimates at Main Gate.
Net variation-2
3d  Cost resulting from ISD variation
Type of Cost/SavingCost £m Saving £mExplanation
3e  Operational impact of ISD variation


    —    No operational impact as current capability will continue until replaced.

SECTION 4: KEY USER REQUIREMENTS

4a  Performance against approved key user requirements
KUR NameKey requirement Forecast to be metAt risk Not to be met
KUR 1The User shall be afforded respiratory and facial protection against airborne and deposited Chemical Biological and Radiological hazards. Yes
KUR 2The User shall be afforded respiratory and facial protection that is integrated with the full range of current and planned operational clothing and personal issue equipment. Yes
KUR 3The User shall be afforded respiratory and facial protection that can be donned correctly without external support within nine seconds. Yes
KUR 4The User shall be afforded respiratory and facial protection that enables continuation and timely completion of the operational mission before, during and following CBRN contamination. Yes
KUR 5The User shall be afforded respiratory and facial protection that can be decontaminated whilst continuing the operational mission. Yes
KUR 6The User shall be afforded respiratory and facial protection that allows replacement of any consumable component within a CBRN environment without assistance. Yes
KUR 7The User shall be afforded respiratory and facial protection that will maintain the specified Protection Factor (PF) over a period of 14 Battlefield Missions (BFMs). A BFM comprises up to 48 hours continuous use followed by not longer than a period of one hour during which respiratory and facial protection shall not be worn. Yes
Percentage currently forecast to be met 100%
In-year change 0
4b  Reasons for variation against approved key requirements
DateKey Requirement FactorExplanation

SECTION 5: HISTORY UP TO MAIN GATE APPROVAL

5a  Description of the Assessment Phase

  The GSR project was initiated within the Defence Procurement Agency (DPA) following a successful Technology Demonstration Programme (TDP) conducted by DSTL. The TDP demonstrated the integration of advanced technologies to a stage that proved the design concept for enhanced respiratory protection. The Initial Gate Business Case was approved on 24 July 2002. Competitive procurement then ensued through two contracts awarded to Scott Health and Safety Ltd (Skelmersdale) and Avon Technical Products Ltd (Melksham). These contractors were required to further develop these concept technologies, using their skills and expertise, and provide Proof of Principle Prototype respirators that provided the required performance. The technical performance of these prototypes were independently assessed and validated against the User Requirements Document (URD). The evaluation demonstrated that both Contractors had viable solutions that would be compliant against all Key User Requirements (KURs) and the majority of Priority 1, 2 and 3 Individual User Requirements (IURs). However, Scott Health and Safety Ltd were selected as the preferred Contractor on the basis of the Value for Money that their tender offered. The Main Gate Business Case was approved in October 2004.

5b  Cost of the Assessment Phase
£m (outturn prices)Assessment phase cost Proportion of total estimated procurement expenditure
Actual cost  6   8%
Approved cost at Initial Gate   710%
Variation-1
5c  Duration of Assessment Phase
Date of Main Gate approvalOctober 2004
Target date for Main Gate approval at Initial Gate September 2004
Variation (months)+1
5d  Cost boundaries at Initial Gate and Main Gate Approvals
£m (outturn prices)
Lowest
Budgeted For
Highest
Cost of Demonstration and Manufacture Phase forecast at Main Gate 6163 65
Cost of Demonstration and Manufacture Phase forecast at Initial Gate n/a53 61
5e  ISD boundaries at Initial Gate and Main Gate Approvals
Earliest Budgeted ForLatest Acceptable
Forecast ISD at Main GateAugust 2006 October 2006December 2006
Forecast ISD at Initial Gaten/a December 2005May 2006

31 March 2006




 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 8 December 2006