Select Committee on Defence Written Evidence


Fourth memorandum from the Ministry of Defence

POST MAIN GATE PROJECT SUMMARY SHEET

Maritime Composite Training System Phase 1

Integrated Project Team Responsible: Maritime Training Systems (MTS)

Single Point of Accountability for project capability: Director Equipment Capability (AWE)—Above Water Effects

Senior Responsible Owner for broader capability:

SECTION 1: ABOUT THE PROJECT

1a  Project description, progress and key future events

  The Maritime Composite Training System (MCTS) is an incremental programme enabling a coherent approach to future warfare operator training. Phase 1 delivers the shore training capability and provides a central warfare hub to facilitate training through a common synthetic environment. The closure of the Maritime Warfare School (MWS) Southwick Park site (formerly within HMS DRYAD) and the planned transfer of all surface flotilla warfare training to the MWS at HMS COLLINGWOOD has provided an opportunity to combine coherency with innovation in the provision of training facilities for new and legacy platforms.

  The procurement strategy was open competition for a Prime contract which was awarded to BAE Systems Insyte. Flagship Training Limited was a nominated sub-contractor due to their existing partnering arrangement with the Naval Training and Recruitment Agency (NRTA).

  At 31 March 2006 the project is 3½ months into a 43 month contract for Demonstration and Manufacture (noting that the initial In-Service phase is also under the same contract). The key future milestones are the:

    —    Critical Design Review (CDR), current forecast for January 2007;

    —    Ready For Training Date (RFTD) current forecast for July 2008;

    —    Initial Operating Capability (IOC) current forecast for July 2009; and

    —    Full Operating Capability (FOC) current forecast for October 2010.

  A key strength of MCTS is it brings together a number of projects[1] that have Maritime training requirements into a single coherent programme which has enabled requirement synergy to be exploited and capability to be met in a more cost effective manner.

  Initial work required in support of Earned Value Management (EVM), a key element of project monitoring and control, identified issues regarding the extent of risk within the programme plan. The IPT is in close dialogue with the BAE Management Team to understand the potential impact to the overall programme and the most appropriate action should it be required.

1b  Associated projects
Critical to Achievement of ISD Critical to Initial Gate Requirement
Project TitleForecast ISD Project TitleForecast ISD
1c  Procurement strategy
Contractor(s)Contract Scope Contract TypeProcurement Route
BAE Systems Insyte BroadoakDemonstration to Manufacture Firm priceInternational competition

SECTION 2: PROJECT COSTS

2a  Performance against approved cost
£ millions (outturn prices) Procurement Cost
Current forecast cost  77
Approved cost at Main Gate  79
Variation-2
In-year changes  0
2b  Reasons for variation from approved cost
Date Variation (£m) Factor Explanation
1 August 2005-2Risk Differential Difference between the risk allowed for in the most likely (50%) and highest acceptable estimates at Main Gate.
Net Variation-2
2c  Expenditure to date
Expenditure to (£m)11

2d  Years of peak procurement expenditure
2006-072007-08
2e  Unit production cost


  Note: not applicable to MCTS as it is a single system.
Unit Production Cost (£m) Quantities Required
at Main GateCurrent at Main GateCurrent

SECTION 3: PROJECT TIMESCALE

3a  Definition of in-service date

ISD Definition:
Initial Operating Capability—IOC will be declared by FLEET when all aspects of the throughput have been achieved for each role trained at the Individual Career, Warfare Team (Sub Team, Command Direction Team and Platform Warfare Team) and Continuation level.


3b  Performance against approved in-service date
Date
Current forecast ISDJuly 2009
Approved ISD at Main GateJuly 2009
Variation (months)  0
In-year changes+7
3c  Reasons for variation from approved ISD
DateVariation (months) FactorExplanation
16 December 20057Contracting Process Protracted negotiations and extended acceptance process.
1 August 2005-7Risk Differential Difference between the risk allowed for in the most likely (50%) and the approved figures at Main Gate.
Net Variation0
3d  Cost resulting from ISD variation
Type of Cost/SavingCost £m Saving £mExplanation
3e  Operational impact of ISD variation

SECTION 4: KEY USER REQUIREMENTS

4a  Performance against approved key user requirements
KUR NameKey Requirement Forecast to be met
At Risk Not to be met
KUR 1The User requires MCTS to enable the Operational Capability (OC) of the surface Fleet to be maintained through the training of individuals at different levels and standards of professional experience and expertise. Yes
KUR 2The User requires MCTS to enable the training of surface flotilla warfare operators of all ranks/rates to a level of individual competency defined by the relevant OPS. Yes
KUR 3The User requires MCTS to enable an individual to be trained, both independently and within their platform teams, to maintain and improve upon the level of competency defined by the relevant OPS onboard their platforms. Yes
KUR 4The User requires the throughput of personnel trained to be that required to sustain the requirement of NRTA's Warfare training plans. Yes
KUR 5The User requires the training of individuals within their platform warfare teams to be that required to maintain Readiness. Yes
KUR 6The User requires MCTS to output trained personnel to the front line within current training pipeline lengths as defined by the warfare TPAG. Yes
KUR 7The User requires that MCTS shall be available to meet the training throughput profiles. Yes
KUR 8The User requires MCTS to provide a suitably representative training context for delivery of the warfare operator training requirements. Yes
KUR 9The User requires MCTS to support the management and control of warfare operator training. Yes
KUR 10The User requires MCTS to support the brief and debrief of warfare operator training. Yes
KUR 11The User requires MCTS to integrate with Initial (Phase 1) Training. Yes
KUR 12The User requires MCTS to be fully interoperable with other platform warfare team, Joint and Combined training capabilities. Yes
Percentage currently forecast to be met 100%
In-year change     0
4b  Reasons for variation against approved key requirements
DateKey Requirement FactorExplanation

SECTION 5: HISTORY UP TO MAIN GATE APPROVAL

5a  Description of the Assessment Phase

  Initial Gate Approval was given 25 February 2004. The assessment phase for MCTS focussed on the expansion of the User Requirement Documentation (URD) and production of the System Requirement Documentation (SRD). The approach taken sought to achieve early engagement with Industry by inviting prospective Prime Contractors, for the Demonstration, Manufacture and In Service phases, to take part in a "Rainbow team" to work alongside the MoD Integrated Project Team and the Royal Navy Customer 1 and 2 community. Industry participation was formally invited through the contracts bulletin and was subject to Industry participating at their own cost; in return they would gain early insight and understanding of the requirement, be involved in shaping the programme and be invited to tender for the D, M & initial In Service Phase. Six companies agreed; Alenia Marconi Systems (AMS) (now BAE Systems Insyte), CAE, Electronic Data System (EDS), Lockheed Martin, Serco, and Thales.

  The output from the assessment phase was an agreed SRD and a robust and well understood suite of commercial and project requirements to support the Invitation To Tender (ITT). The ITT was issued to the six companies late in 2004 and AMS and Lockheed Martin responded with tenders. BAE Insyte [formerly AMS] was announced as the preferred bidder and the contract was signed on the 16 December 2005.

5b  Cost of the Assessment Phase
£m (outturn prices)
Assessment Phase cost
Proportion of total estimated procurement expenditure
Actual cost  1   1%
Approved cost at Initial Gate   45%
Variation-3
5c  Duration of Assessment Phase
Date of Main Gate ApprovalAugust 2005
Target date for Main Gate approval at Initial Gate December 2005
Variation (months)-4
5d  Cost boundaries at Initial Gate and Main Gate Approvals
£m (outturn prices)
Lowest
Budgeted For
Highest
Cost of Demonstration and Manufacture Phase forecast at Main Gate 7377 79
Cost of Demonstration and Manufacture Phase forecast at Initial Gate 6573 92
5e  ISD boundaries at Initial Gate and Main Gate Approvals
Earliest Budgeted ForLatest Acceptable
Forecast ISD at Main GateSeptember 2008 December 2008July 2009
Forecast ISD at Initial GateDecember 2007
March 2006





1   Sonar 2087 (the new Anti Submarine Sonar for Type 23 Frigates), WARSPITE (the move from MWS Southwick Park to HMS Collingwood), Type (the new Anti Air Warfare Destroyer), UAT Capability Upgrade (Electronic Surveillance Measure system), Sea Wolf Mid Life Upgrade and Link 16 (Radio Tactical Data Link system). Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 8 December 2006