Select Committee on Defence Written Evidence


Memorandum from the Scottish Campaign for Nuclear Disarmament

  The points made below respond to Government plans for the Atomic Weapons Establishment (AWE).

HOW MUCH WILL IT COST TO REBUILD AWE?

  1.  Des Browne said that the £1,050 million expenditure on AWE, which had been announced in July 2005, would fund a wide range of developments.[122] He has refused to disclose the budget for individual facilities in the plan saying "mature costs are not available".[123] These figures are essential if there is to be any proper scrutiny of these proposals.

  2.  Nuclear safety requirements would have a substantial impact on cost. The Shiplift at Faslane went over budget and still did not meet safety standards. The A90 facility built at Aldermaston cost far more than budgeted. (The Audit Office report into A90 should be placed in the public domain). The MoD have just written off £147 million which had been spent on the A91 radioactive waste treatment plant. The cost of the new nuclear facilities at Devonport increased from an initial budget of £576-£650 million to at least £812 million.[124] The Audit Office report into Devonport also revealed that a number of the initial designs did not meet safety requirements.

  3.  The US Department of Energy have plans to rebuild many of their nuclear weapons' facilities. Table 1 shows some of the projects planned for AWE and published estimates of the cost of related facilities in the US. These examples show not only the scale of expenditure involved but also how final costs may be several times higher than the initial estimate.

Table 1
New AWE Facility US Example Cost of US Facility
£ million
High Powered Computing Advanced Strategic Computing £320 per year
Orion LaserNational Ignition Facility Initial estimate £500;

current estimate £2,000

Core Punch FacilityDual Axis Radiographic Hydrodynamic Test Initial estimate £32;

current estimate £174

Uranium Production FacilityUranium Production Facility £400-500
Material Science FacilitiesChemical & Metallurgical Research Replacement £450-550
Tritium FacilityTritium Extraction Facility £270


  4.  The Orion laser is a smaller project than the National Ignition Facility. However the Uranium Production Facility could be similar to that planned for the Y-12 site at Oak Ridge, Tennessee.[125] The Core Punch Facility at Aldermaston would be more complex than the new hydrodynamic facility at Los Alamos.

  5.  This suggests that implementing the AWE Site Development plan in full would cost several billion pounds.

WHAT ARE AWE PLANNING TO DO?

Life Extension

  6.  Des Browne said the developments at AWE were "necessary to sustain Trident for its remaining in-service life."[126] The term "remaining in-service life" is misleading. The life of the warhead is flexible and AWE's main priority has been to extend it.

  7.  In 2001 an official statement on British nuclear weapons' research said:

    "the overarching objective of the UK nuclear warhead programme is to keep the Trident warhead in service, and to be able to underwrite its performance and safety over a period much longer than its originally intended service life."[127]

  8.  AWE will have some confidence in the safety and reliability of the Trident warhead up to a life of 25 years. The substantial programme of production, surveillance, experiments and research is not primarily to support this initial planned life, but to provide a basis for extending it.

  9.  As part of this "Life Extension" approach AWE continues to manufacture a number of warheads every year. For surveillance purposes some of the oldest warheads are completely dismantled. These are replaced with new warheads. The continuous production of warheads means that the average age of the stockpile is lower than would otherwise be the case.

Upgrade

  10.  AWE are preparing to upgrade the Trident warhead in the first half of the next decade.[128] Job advertisements reveal that AWE will shortly replace the Warhead Electrical System.[129] This component is also called the Arming, Fuzing and Firing System (AF&F).[130] A new AF&F for the US Trident warhead has just been designed.[131] Some American warheads will be upgraded with the new AF&F between 2006 and 2020.  The modified warheads have the designation W76-1.

  11.  The introduction of the new AF&F on US and British warheads will increase the capability of Trident. Los Alamos say that the W76-1 will have increased "targeting flexibility and effectiveness", compared with the original design.[132] Modifying British warheads to a W76-1 specification would be more than a "relatively minor" upgrade.[133] Defence Ministers have refused to discuss AWE's involvement in the W76-1 programme or the new AF&F.[134]

New warhead

  12.  The US Administration are now moving away from the Life Extension approach and focusing instead on designing new warheads under the Reliable Replacement Warhead (RRW) programme. During Congressional scrutiny of the budget for 2007 the W80 Life Extension project was cancelled and the amount allocated to RRW was increased. It is likely that the W76-1 Life Extension project will be curtailed and resources switched to the Trident RRW.

  13.  A choice between Los Alamos and Lawrence Livermore designs for the Trident RRW will be made in November 2006.  The third US nuclear weapons' laboratory, Sandia, is substantially involved in both options. Lockheed Martin operates Sandia. They are likely to use their role in AWE Ltd to advocate that Britain develops an equivalent of RRW.

  14.  A crucial difference between Life Extension and RRW is that the latter involves redesigning the plutonium pit at the core of the primary of the warhead. The decision on whether to replace the pit in British warheads will be related to estimates of its service life. Des Browne said that AWE undertakes a range of studies to: "enable regular assessments of the service life of any particular pit."[135]

  15.  As with the submarine platform, the MoD may be preparing for both Life Extension and, later, replacement of the warhead.

Facilities and options

  16.  Table 2 indicates how the proposed facilities relate to future options.

Table 2
Facility Dismantle Trident 2020-25 with no replacement Trident Life Extension Design and build replacement warhead
High Powered Computing No need to increase capability Some investment Substantial investment
Hydrodynamics New facilities not essential Limited programme of experiments to extend pit life Substantial programme of experiments for new pit
Orion Laser Not required Limited programme of experiments Substantial programme of experiments
New Uranium Production FacilityNot required; use A90 Limited production related to the surveillance programme Substantial production if secondary or radiation case replaced
A90 Plutonium Production Facility Plutonium and Uranium work Limited production related to the surveillance programme Upgrade of A90 required for substantial production of new pit
Tritium Extraction Facility Not required New facilityNew facility
Warhead Assembly and Disassembly Facility Scaled down new facilityNew facility New facility
Explosive facilitiesLimited requirement New facilityNew facility
Material science facilitiesNot essential New facilityNew facility


  17.  The workload of AWE, in terms of research, surveillance, production and dismantlement, will vary depending on what the plans are for the future of British nuclear weapons. That workload would be substantially greater if a decision was made to design and build a new warhead. It would be much less if Trident was scrapped in 2025 and not replaced.

  18.  The Site Development Plan would create a range of new facilities which could design, build, sustain and dismantle two-stage thermonuclear warheads between 2020 and 2050, with assistance from the US.

COMMENT

  19.  The MoD are trying to preempt crucial decisions on the future of nuclear weapons by initiating a very expensive rebuilding programme. Vital resources should not be committed to expanding an infrastructure for building and maintaining nuclear weapons. Britain clearly has no need for these weapons and they undermine our potential to tackle global issues of proliferation and disarmament.

  20.  In addition to the billions of pound which may be wasted, we would also be squandering the talents of men and women whose skills could make a valuable contribution to the future welfare of this country. The computer scientists who are being recruited to perfect the design of nuclear warheads could use their expertise for climate modelling, which also requires supercomputers. The hundreds of mechanical and electrical engineers being drafted into AWE would be far better employed designing and producing alternative sources of energy supply.

  21.  AWE are not, as they claim, a forward looking establishment. They are a historical relic whose time has passed. Scarce human resources and capital expenditure should be directed towards projects which tackle the real needs of the 21st century.

30 September 2006






122   Reply by Des Browne MP to a written question from Nick Harvey MP who asked which facilities would be funded by the £1,050 announced in July 2005; Hansard 5 July 2006. Back

123   Replies to written questions in July 2006. Back

124   National Audit Office report into the Construction of nuclear submarine facilities at Devonport; 6 December 2002. Back

125   Report of recent visit by AWE staff to their US counterparts in the Y-12 newsletter. Back

126   Reply by Des Browne MP to a written question from Nick Harvey MP Hansard 5 July 2006. Back

127   High Energy Density Physics, National Nuclear Security Administration, April 2001, Appendix G-United Kingdom Statement on High Energy Density Physics. Back

128   MoD Memorandum to Defence Committee 19 January 2006; Annex B Expected Life of the Trident System. Back

129   A vacancy for a Warhead Electrical Engineer refers to "the approval programme for the introduction of the [Warhead Electrical] System into UK Trident". There are other related positions. www.awe.co.uk Back

130   Appendix F to the Report of the Fundamental Classification Policy Review Group Report of the Weaponization and Weapons Production and Military Use Working Group, 15 January 1997, James B Wright, Chair Sandia National Laboratories. Back

131   The new US Arming Fuzing and Firing System is designated MC4700. It has a similar fuzing system to the W88 warhead and a replacement contact fuze. Back

132   www.lanl.gov/orgs/d/d5/projects/W76/W76-1-LEP-Overview.htm Back

133   MoD Memorandum to Defence Committee 19 January 2006; Annex B Expected Life of the Trident System. Back

134   Reply by Lewis Moonie MP to a written question from Lynne Jones MP Hansard 6 February 2002, and reply by Des Browne MP to a written question from Nick Harvey MP 6 July 2006. Back

135   Reply by Des Browne MP to a written question from Nick Harvey MP Hansard 13 July 2006. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 19 December 2006