Select Committee on Defence Written Evidence


Supplementary memorandum from Devonport Management Limited

  Minimum skill levels: A note on the breakdown of the minimum number of personnel in each key skill area necessary to sustain core skills [Q17]:

  These numbers are based on the resources needed to support a single stream of SSBN refuelling/refits (which will be the submarine refit load when Devonport completes the current, final Trafalgar class refit on HMS Triumph in early 2008) in parallel with a single defuelling and lay-up workload on end-of-life SSNs:

    250 mechanical fitters, 140 electrical fitters, 150 fabricators, 30 welders, 15 nuclear welders, 50 marine pipe fitters, 150 health physics/radiological/environmental support staff, 200 test and commissioning engineers, 140 refuelling and fuel handling personnel of all types, 400 infrastructure/plant management, technical and safety case specialists and 300 planning and programme management staff.

  Note that within the large groups such as fitters there are very many instances of sub-sets of typically two to four individuals who have unique experience in, say the strip, survey, rebuild and commissioning of particular equipments and systems within the submarines.

  There are other personnel involved in support to overall site operations, etc, but these have not been detailed in the above answer.

  Decommissioning: A note on the number of people required to decommission the current Vanguard submarines if a decision was taken to abandon the deterrent and how those numbers compare to current employment levels at Devonport [Q19]:

  These numbers are based on the experience with SSN defuelling and lay-up preparation, but do not include any work to take the submarines beyond the stage where they are prepared for long term storage afloat (ie it does not allow for complete scrapping and disposal):

    440 defuelling and lay-up preparation staff (includes all planning, project and management team), 50 health physics/radiological/environmental support staff, 100 plant management and technical specialists and 50 infrastructure maintenance personnel.

  Naval Base Review: A note on the scale of what is involved in the Review, how the Review relates to the deterrent decision, and how DML is consulting with the MoD on the Review [Q47]:

    The Review is looking at the options for reducing the scale of Naval Base infrastructure to re-establish the balance between operational base port capacity/costs and the current requirements of the Royal Navy.

    The way in which the Review relates to the deterrent decision is explained in my written evidence—[136]

    "A decision not to replace the deterrent would have a fundamental effect on the maritime element of the DIS [and the Naval Base Review] through:

    —  a potential impact on the operational and support strategies for the existing deterrent system;

    —  knock-on effects into the planned Astute procurement programme (the SSN force is partly committed to supporting the SSBNs); and

    —  changed priorities in respect of build and support yards [and Naval Bases] that are required to deliver the other elements (ie, non SSBN-related) of military capability in the naval sector.

    Conversely, a decision to replace the current deterrent system would make the existing UK submarine-related engineering skill-base and infrastructure essential in maintaining availability of the current and future SSBNs and the SSNs that support their deployment.

    A positive decision on a future submarine-based deterrent must, in turn, influence decisions about where and when other naval build and support work is carried out—a good example is Devonport where the availability of surface ship support work will be vital during the inevitable periods of low submarine throughput that the future upkeep programme contains, if submarine affordability is not to be seriously impaired.

    There is also therefore a very important interaction with the current Naval Base Review where, for instance, the resultant surface ship base porting strategy will influence the availability of ship maintenance work in Fleet Time at Devonport.

    Hence a positive decision to replace the current deterrent with a new submarine-based system will generate a "pivot point", centred on the UK's sovereign submarine build and support infrastructure, around which a wide range of other maritime industrial base issues [as well as Naval Base strategy] should be determined if the affordability and availability of overall naval capability is to be optimised."

  DML is providing a wide range of cost and other data to the Naval Base Review team relating to the various options that are being considered. Much of this is being supplied and justified through direct discussions with RN and civil service personnel who work in Devonport Naval Base.

ASTUTE KEY SUPPLIER FORUM

  DML is not actually a supplier into the Astute programme and I assume that this is why my company is not a member of this group.

  DML's input to the Astute design has been limited. However, DML has extensive knowledge of the current classes of RN submarines and their in-service support, knowledge which is relevant to the development of the Astute class support strategies.

  DML is fully engaged in the work streams that are considering the requirements for future nuclear submarine capability and associated designs.

24 November 2006





136   The text in [square brackets] is additional to the written evidence text but is relevant to the specific question asked. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 19 December 2006