Select Committee on Defence Written Evidence


Supplementary memorandum from BAE Systems

  Further to the hearing of 7 November 2006 I would like to provide this written note to expand on the following questions:

    —  Q17—"minimum number necessary in each specialist area".

    —  Q31—"timeline for ourselves—our resource plots".

  To address Q17 first BAE Systems Submarines is currently organised to support a 22 month interval between each ASTUTE Class Submarine. This results in three submarines in various stages of production at any one time. The 22 month drumbeat has been agreed with MOD as the optimum interval to retain key skills and to address the issue of affordability. Work has taken place with trade unions to remove the last vestiges of demarcation and promote flexibility. Significant opportunities have been taken to outsource non specialist activities (eg laying electrical cables in predetermined routes) and stringent `make v buy' analysis has taken place to ensure that manning is at a minimum whilst maintaining key skills. Further investigation has shown that even single digit changes in manning levels can impair performance.

  Retention of resource surplus to immediate requirements is seen as both uneconomical and also unrealistic because of the irreversible attrition of skilled and particularly experienced personnel which would inevitably result. Skilled workers need real and challenging work to retain their qualifications and expertise in the design/build of such a complex product.

  The current production headcount represents the minimum requirement to support the 22 month drumbeat, and the figures for Production and Engineering are as follows:

Production
Skill Number
Steelworkers 298
Pipe Mechanical 379
Electrical 174
Sheet Metal Workers 51
Joiners 17
Painters 21
Ancillaries 150
Direct Support 200


Production Support
SkillNumber
Weapons Systems Engineers60
Test and Commissioning60
Supervision/Management160


Engineering
Skill Number
Professional Engineers148
Detail Designers220
Technical Support60


Engineering Support
SkillNumber
Combat Systems Engineers150
Systems Engineers140
Nuclear Safety Engineers (Site and Submarine) 50


  These skill sets can be further sub divided, and a detailed breakdown for Steelworkers, Pipe Mechanical, Electrical, Professional Engineers and Detail Designers is shown at Annex A.

  It should also be noted that the retention of Nuclear Safety Engineers is critical to the maintenance of the Nuclear Site Licence, without which the construction of Nuclear Submarines is impossible.

  In addition to this the following should be recognised:

  Expansion from the minimum capability levels will be required to support a potential Successor Programme, and there would be a significant time delay before full operating capability and efficiency was reached whilst personnel are recruited, trained and gain experience.

  Consideration should also be given to what work would be available to maintain the skills and currency of these minimum levels. Unless it is possible to secure challenging, relevant work, it would be difficult to retain the workforce.

  These figures were presented to MoD ASM IPT in August 2006 and have since been independently reviewed for the MoD. They are a development of the analysis prepared for the Rand report "Sustaining Design and Production Resource".

  With regard to Q31, the graphs at Annex B show the minimum level of Production and Engineering resource required to support current contracts (Boats 1-3 of the ASTUTE Programme)

  During the Select Committee hearing Mrs Linda Gilroy raised an issue regarding why DML had not been included in the Key Supplier Forum, a focus group of key contractors who's objective is to pursue significant improvements in affordability, (led by BAE Systems and which to date has been highly successful). Our reason for not including them, although through-life cost issues are covered by the inclusion of the Defence Logistics Organisation representative, are that they do not procure a significant amount of first fit items; however they are, and increasingly will be, an active participant in our Lean Design studies for the Astute Class which look not only into opportunities to reduce the UPC (unit production costs) but also in particular to include considerations of through-life maintenance and support into the design.

  I trust this is helpful should you require any further information please do not hesitate to contact.

Murray Easton

Managing Director, Submarines

30 November 2006

Annex A

STEELWORKER SKILL SET BREAKDOWN
SteelworkersWelders Caulkers/GougersOther
Reactor Lead/Poly Lining—3

Machine Specialists—13

Unit/Module Fabrication—21

(Qualified to Tack)

Pressure Hull Erectors—19

(Qualified to Tack)

Technically based Liner Offs/Dry Survey Specialists—6

Minor Fabrications—9

Outfit/Boat Steelworkers—27

Flank Array Trained and Qualified—7

Apprentices—17

Cladding—8

A-grade—40

A-grade (sub-arc)—13

Specialist Stainless—7

A—grade Instructors—2

Service Welders—11

Apprentices—20

Burners—2

Gougers—9

Dry Survey Grinders—5

Tank Testing Team—8

Apprentices—5

Plumbers (Reactor lead/Poly fitting)—2

Joiners (Reactor lead/Poly fitting)—4

Ships Loft men (Mock ups, templates)—5

Drillers—all areas inc pressue hull and reactor—20

Apprentices—6

PIPE MECHANICAL SKILL SET BREAKDOWN
FittersPipeworkers Pipe WeldersTurners
Test Team—17

Nuclear Facilities—build of primary plant—12

Plant Maintenance—16

SMITE—Gearbox/Main Engine build—11

SMITE—Testing—6

Boat Restricted Access—83

Pipe Manufacture—40

Plant Maintenance—11

Nuclear Facilities—build of primary plant—12

SMITE—pipe installation—11

Pipe Installation—105

Boat Restricted Welders—18

Nuclear Coded—12

PPS Specialist Welders—10

SMITE Restricted Welders—2

DDH Machine Shop—16

ELECTRICIAN SKILLS SET BREAKDOWN
Electricians
Nuclear and Combat Systems Experience—44

Termination Specialists—36

Plant Maintenance and Production Services—32

Test ElectriciansServices and General Electricians—40

PROFESSIONAL ENGINEERS AND DETAIL DESIGNERS SKILL SET BREAKDOWN
Minimum Engineering skills base:
Professional Engineers:
Electrical32
Mechanical40
Structures9
Stress and Dynamics 14
Naval Architects7
Signatures4
Noise and Vibration 8
Radiation and Shielding 4
Metallurgists and Welding 10
Safety5
Weights3
Engineering Management 8
Operability4
Total148
Detail Designers:
Electrical27
Electrical Layout9
Cable Management12
Electrical Specialists 7
Electrical Management 7
HVAC6
Mechanical Systems27
Mechanical Integration 11
Mechanical Specialists 7
Mechanical Reactor5
Mechanical Management 7
Hull Outfit11
Hull Structure25
Hull Mechanics8
Hull Specialist6
Hull Integration5
Hull Management6
Production Engineering 6
Minimum Engineering skills base:
Field Engineering (liaison with Operations) 6
Standards13
Bill of Materials 9
Total220


Annex B

PRODUCTION RESOURCE

Graph showing production resource to support Boats of 1-3 of the ASTUTE class

Annex B

ENGINEERING RESOURCE

Graph showing engineering resource to support Boats 1-3 of the ASTUTE Class





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 19 December 2006