3 Performance
Key
Targets
25. The MoD Annual Report and Accounts 2005-06 summarises
Dstl's performance against its Key Targets:
- 2005-06: 7 of 10 Key Targets
achieved;
- 2004-05: 7 of 7 Key Targets achieved; and
- 2003-04: 7 of 7 Key Targets achieved.[46]
2005-06 Key Targets
26. Dstl's performance against its Key Targets for
2005-06 is set out in Table 2.
Table 2: Dstl's performance against its 2005-06
Key Targets
Target |
Outcome |
1. Maintain and by the end of a three-year period show an increase in score for scientific and engineering capability in the technical benchmarking exercise from 67% in 2002/03 to 72% in 2005/06moderated by external assessors agreed with MoD's Chief Scientific Adviser (CSA)
| Achieved |
2. Identify and agree with MoD's CSA the top 10 Dstl capability needs, their alignment with the future programme and the required MoD funding by March 2006
| Achieved |
3. By the end of the three-year period show a linear improvement of at least 1.5% on the FY2004/05 customer satisfaction score of 75.4% for service provision
| Not achieved |
4. Implement a process for identifying and publicising Dstl's major achievements during the year
| Achieved |
5. Achieve Health and Safety Executive approval of the category 4 microbiology containment facility by 31 October 2005
| Achieved |
6. Define the scope, structure and funding requirements of a new defence and security research and development centre and, subject to new funding being available from customers, prepare a specific proposal for its creation
| Achieved |
7. Achieve planned progress within budget to meet the completion date of 2008 for the transfer of Dstl onto three core sites at Porton Down, Portsdown West and Fort Halstead. The key milestones for 2005/06 are: appoint the preferred bidder (August 2005); negotiate with the preferred bidder a reduction in facilities management costs of Dstl of at least 15% from August 2006; sign the contract (March 2006)
| Not achieved |
8. By December 2005, complete the detailed design and build phases of the new Integrated Corporate Applications System (iCAS) that will deliver Dstl's business information requirements from 2006/07
| Not achieved |
9. Maintain the average charge rate for staff for 2005/06 and beyond below that for 2001/02 uplifted by GDP deflator
| Achieved |
10. Achieve a ROCE of at least 3.5% averaged over the period 2004/05 to 2008/09 and an MoD dividend of £3 million in 2005/06
| Achieved |
Source: MoD[47]
27. We asked about the 2005-06 Key Targets which
were not achieved and what action Dstl had taken. MoD told us
that:
- for Key Target 3, the 2005-06
customer satisfaction score for service provision was 74.7%a
decrease of 0.7% on the baseline 2004-05 score. An investigation
showed that the main cause was a "notably reduced score from
customers in the Research Acquisition Organisation" (RAO).[48]
Steps were being taken to improve the relationship with MoD Head
Office and RAO science staff;
- for Key Target 7, the rationalisation project
to consolidate Dstl's activities onto three core sites achieved
two of its three key milestones, but it was not possible to sign
the Facilities Management (FM) contract in March 2006. Serco had
now been appointed as the FM provider. The handover of Facilities
Management took place, as planned, on 1 August 2006. We examine
the Dstl site rationalisation project later in this report (paragraphs
58-63); and
- for Key Target 8, the target to complete the
detailed design and build phases of the new Integrated Corporate
Applications System (iCAS) by December 2005 was not met. A decision
was taken to delay the project to incorporate the latest version
of the Peoplesoft 8 software into the design. Work was progressing
well and the project was scheduled for completion in February
2008.[49]
28. Dstl
achieved seven of its ten Key Targets in 2005-06. Action is in
hand to address those targets which were not fully achieved in
the year.
29. The CSA told us that the MoD was constantly evolving
the Key Targets.[50]
Mr Trevor Woolley, MoD's Finance Director, told us that
some of the targets are harder than others. Some
of the more qualitative targets in this area are inevitably going
to be difficult
.The targets are evolving. We are trying
to reduce the number of targets to try and make them a little
more relevant and in some respects they have got tougher over
the years.[51]
2006-07 Key Targets
Table 3: Dstl's Key Targets for 2006-07
Area
| Target
|
Delivery
| 1. Achieve a level of overall customer satisfaction in our delivery of at least 76.4% for FY2006/07 against a three-year target of 76.9% (FY2007/08)
2. Deliver high-quality outputs that have impact on MoD customers' top ten priority issues
|
People
| 3. Achieve an overall score of at least 72% for scientific and engineering capability in the technical benchmarking exercise. Develop, and agree with CSA, a robust process for assessing the quality of Dstl's evolving technical capabilities for the period 2007-2011
|
Environment
| 4. As part of the strategic aim to bring Dstl onto three sites by 2009, agree the overarching construction and facilities management contract and achieve key milestones on programme to time and cost, including delivering predicted efficiency gains
5. To enable greater knowledge sharing, improved management and operational efficiencies, by meeting agreed in-year targets to ensure Dstl has in place an integrated corporate business environment by the end of FY2008/09
|
Business Essentials
| 6. Achieve an average Return on Capital Employed (ROCE) of at least 3.5% over the period 2004/05 to 2008/09
|
Source: MoD[52]
30. Dstl's Annual Report and Account 2005-06 states
that Dstl had "set out three overarching key result areas
to focus the whole organisation's efforts on achieving results".
The key result areas are: delivering high-quality output on the
really important issues; enabling people to realise their full
potential; and creating an environment in which excellence can
thrive.[53] Dstl's Key
Targets for 2006-07 are set out in Table 3.
31. The number of Key Targets for Dstl has reduced
from ten in 2005-06 to six in 2006-07. The six Key Targets in
2006-07 are now more aligned to the areas where Dstl is seeking
to deliver results. It is important that targets should reflect
an agency's central functions and not just its financial performance,
but identifying targets which measure quality of output in a meaningful
way can be difficult. Dstl's targets try to measure the quality
of scientific and technical advice by setting as a target a percentage
score for scientific and engineering capability in a technical
benchmarking exercise. We note that Dstl plans to develop, and
agree with the CSA, a robust process for assessing the quality
of technical capabilities for the period 2007-2011. We
look to the MoD to review the Key Targets set for Dstl to ensure
they are challenging and reflect their central function: providing
expert advice to Government.
Financial performance
32. The MoD Annual Report and Accounts 2005-06 provides
the following summary of Dstl's financial performance in 2005-06:
Although turnover remained static during 2005-06
at £353 million, net profit for the Dstl
. rose from
£20.2 million in 2004-05 to £21.8 million in 2005-06.
The ROCE [Return on Capital Employed] fell from 9.4% for 2004-05
to 8.8%. Manpower charge rates continued to be held below the
target for the fifth consecutive year indicating a reduction in
real terms of the cost to customers. Dstl's wholly owned technology
management company, Ploughshare Innovations Ltd, successfully
completed its first full year of operations.[54]
The MoD received a £3 million dividend from
Dstl in 2005-06 (£3 million in 2004-05).[55]
As a Trading Fund, Dstl is allowed to retain profit to fund future
investment. In 2005-06, Dstl retained £18.8 million.[56]
33. The MoD considers that Dstl has had a strong
financial track record since its inception. It has never failed
to meet its financial targets, which include Return on Capital
Employed (ROCE) and the MoD dividend.[57]
A summary of Dstl's financial performance over the last four years
is set out in Table 4.
Table 4: Dstl's financial performance over the
last four years
| 2002-03
£ million
| 2003-04
£ million
| 2004-05
£ million
| 2005-06
£ million
|
Turnover
| 343.5 | 358.1
| 353.3 | 353.4
|
Operating profit
| 13.3 | 19.8
| 23.2 | 18.7
|
Profit for the financial year
| 14.9 | 20.5
| 20.2 | 21.8
|
Retained profit for the year
| 8.9 | 17.5
| 17.2 | 18.8
|
Fixed assets
| 109.8 | 125.5
| 122.9 | 124.6
|
Cash and cash equivalents
| 29.7 | 26.6
| 61.9 | 78.7
|
Net Assets
| 140.5 | 176.5
| 198.9 | 218.18
|
Source: MoD[58]
34. Turnover in 2005-06 remained the same as in the
previous year. MoD considered that this performance reflected
the confidence placed in Dstl by its customers. Work for the MoD
declined marginally during 2005-06, but work from "other
government departments and non-exchequer customers increased".[59]
35. We asked whether Dstl would see any increase
in MoD income, if the MoD were to increase its investment in defence
research. Dr Saunders told us that Dstl's forward projections
of its income were relatively flat and it was only likely to see
a possible rise to cover inflation. She considered that "at
the moment we are not expecting to see any big increase in investment
in Dstl".[60]
36. Dr Saunders told us that Dstl currently receive
around 37% of the defence research budget and expected to receive
"roughly about the same proportion into the future".[61]
Mr Starkey said that, as Dstl only did those things which needed
to be done in government
that in itself determines the volume of our work
.
we receive a particular proportion of most of the research programme37%
of thatbut that depends on our role. We do not go up and
down with the general volume; we look just at our role.[62]
37. During our inquiry into the Defence Industrial
Strategy (DIS), the Minister for Defence Procurement told us that
the MoD would open up more of its research spending to competition.[63]
We asked how this would impact on Dstl, as it was unclear whether
the work Dstl undertook would be opened up to competition, and
whether Dstl would be allowed to compete for defence research
work currently undertaken by others. Dr Saunders told us that
Dstl's Framework Document said that Dstl did not compete, so the
proportion of the research budget that was opened up to competition
was not open to Dstl.[64]
She reiterated that Dstl received 37% of the defence research
budget and there had been no indication that "anybody is
going to change that percentage at the moment".[65]
38. We asked whether Dstl's work might be reduced
by QinetiQ expanding the defence research it undertook, thereby
squeezing out Dstl. Dr Saunders considered that Dstl had "done
pretty well over the last five years
. we have not been squeezed".
In her view, Dstl had carved out a "niche" for itself
and it was doing something "distinctively different"
from QinetiQ and others.[66]
39. Since it
was formed Dstl has demonstrated a strong financial track record
increasing its profits and its net assets. However, Dstl's income
is very dependent upon the amount of work which the MoD considers
must be done within Government, which is some 37 per cent of the
MoD's defence research budget. Dstl is not expecting any increase
on this percentage and does not see it as its role to compete
for other research work funded by the MoD. We consider that there
could be benefit in Dstl operating in a more competitive environment
and look to the MoD to assess whether there is scope to open up
to competition some of the defence research budget currently allocated
to Dstl and scope to allow Dstl to compete for defence research
work currently carried out by others.
Trading Fund status
40. Dstl is a Trading Fund agency of the MoD. The
other Trading Funds are: ABRO (Army Base Repair Organisation);
the Defence Aviation Repair Agency (DARA); the Met Office and
the UK Hydrographic Office.[67]
In its memorandum, the MoD states that it has re-examined the
status of its Trading Funds. The MoD had reached the following
conclusion:
The confines, within which Dstl operates
. meant
that the options in the Dstl review were restricted to either
maintaining the status quo or returning the agency to "on-vote"
status. The review concluded this summer and recommended that
Dstl should retain Trading Fund status pending a further review
once the "i lab" change programme has had sufficient
time to become firmly embedded.[68]
The '"i lab"' programme is a major change
programme intended to transform Dstl into an integrated laboratory
("i lab"). We examine the change programme later in
this report (paragraphs 55-66).
41. Given that we had been told that Dstl only undertakes
work which has to be done within Government and does not compete
for other research work, we asked why Dstl was a Trading Fund.
Dr Saunders told us that reviews undertaken in 2004 and 2005 had
concluded that "there were a couple of quite big advantages
of [Dstl] being a trading fund". The most important was "the
customer/supplier relationship and the real focus on the customers".
Another advantage for Dstl was being in charge of its financial
future: the Trading Fund status had allowed Dstl to retain profits
to invest in the major change programme. Also, the Trading Fund
status meant that the Chief Executive was more accountable for
making sure that the infrastructure and skills were maintained
than if it was "an on-vote organisation".[69]
42. Dstl is
a Trading Fund, but only undertakes work that has to be done within
Government and does not compete for work. There are advantages
to Dstl remaining a Trading Fund, notably its ability to retain
profits for future investment in the business. However, given
the constraints under which Dstl operates, we look to the MoD
to review, on a regular basis, whether Trading Fund status is
the most appropriate option.
46 Ministry of Defence Annual Report and Accounts 2005-06,
HC 1394, p 263 Back
47
Dstl Annual Report and Accounts 2005-06, HC 1163, p 24 Back
48
The RAO is part of the MoD and is responsible for ensuring effective
delivery of the MoD's non-nuclear Science and Technology research Back
49
Ev 29 Back
50
Q 171 Back
51
Q 174 Back
52
Dstl Annual Report and Accounts 2005-06, HC 1163, p 25 Back
53
Dstl Annual Report and Accounts 2005-06, HC 1163, p 25 Back
54
Ministry of Defence, Annual Report and Accounts 2005-06,
HC 1394, p 264 Back
55
Ibid., p 215 Back
56
Ev 25 Back
57
Ev 24 Back
58
Ev 25 Back
59
Ibid. Back
60
Q 15 Back
61
Q 18 Back
62
Q 19 Back
63
Defence Committee, Seventh Report of Session 2005-06, The Defence
Industrial Strategy, HC 824, Q 300 Back
64
Q 34 Back
65
Q 36 Back
66
Q 26 Back
67
Defence Committee, Second Report of Session 2006-07, Ministry
of Defence Annual Report and Accounts 2005-06, HC 57, p 26 Back
68
Ev 26 Back
69
Q 38 Back
|