Select Committee on Environment, Food and Rural Affairs Written Evidence


Further memorandum submitted by Iosis Associates (RPA Sub 13b)

RURAL PAYMENTS AGENCY: REASONS FOR FAILURE

INTRODUCTION

  1.  This submission is primarily a response to a statement made on the BBC Radio 4 programme "File on Four" on 20 June. Towards the end of the programme, Michael Jack MP, Chair of the EFRA Committee, stated that he "can't easily identify where the body is buried that tells me fundamentally why the RPA weren't able to make their payments on time as particularly advertised by Lord Bach in January this year".

  2.  This response particularly takes information from the Uncorrected Oral Evidence (HC 1071-iv) of the 22 May session of the EFRA Committee, at which representatives of Accenture were questioned in depth.

  3.  In this note I point to one key failure which was particularly responsible for the very late realisation that the Accenture systems could not produce those all important lists of payments for authorisation by an RPA operative so that the data could be sent to the cheque writing process: end-to-end tests of the complete business process (including the technology) were not carried out.

  4.  Then I go back to a key failure in the management, one that is probably common to numerous government projects: the failure by RPA to properly assess and manage risk and report risk to the core of Defra.

  5.  Also another mystery is mentioned below—but I don't have a complete analysis of that one.

THE KEY FACTOR

  6.  Q561 (Mr Drew) produced an answer from Mr Naish that gives the key to the "buried body":

    "The way the system works when it establishes entitlement is that it needs to take the claims across the whole of England in order to make those entitlements. It is difficult to run those end pieces of the programme on a small part of the population."

  7.  It ought to have been possible, during system tests, and then at any stage once some claims had been verified, to advise the system that it has a complete set of data, give it a notional sum of money in the pot, and then run "those end pieces of the programme" ("the last stages of the process") as a test. This would probably be done by taking a copy of the dataset of verified claims to date, using a separate computer system loaded with the necessary software, and running the last stages on the partial data accumulated to date at the time of the test.

  8.  Thus it would have been possible to see if the entire process could be run to completion:

    —  if it had any problems, or even a fundamental problem, with the data; and

    —  if (as repeated tests were run during the build up of data to the full set of claims) the growing size of the data was going to cause any problem as the process was scaled up to the full 120,000 claims.

  9.  An extension to this would have been to generate test data with 120,000 records, but the evidence from the 22 May session suggests that that would have been a significantly large sub-project in its own right.

METHODS TO AVOID SUCH PROBLEMS

  10.  The primary way in which the customer should seek to avoid the problems found with the RPA SPS is to have in place and make use of the necessary expertise to assess and manage risk, and propose mitigation methods. Then the reporting structure from Programme Manager to Chief Executive (and in this case all the way to Defra Chief Executive) has to be through personnel who themselves are skilled in risk management, operate an environment in which the full facts are clearly seen as essential to decision making, and are accountable for failure. That requires an organisation in which personnel have a regular cycle of assessment of capability and contracts of employment that include provision for best practice methods for resolving under-performance.

  11.  At a recent meeting (5 May) of a group of specialist ICT[24] suppliers with Join Wailing, a Director in Cabinet Office e-Government Unit, I introduced the use of a contracted technical audit team as one way for a customer organisation to monitor the progress of a large project. Such teams were used successfully in the mid 1980s when the Stock Market moved to screen-based trading, using completely new computer systems. The audit team has to have access to the main delivery contractors, and the resources to undertake system tests as necessary. Such teams are used in, for example, the auditing of safety-critical industrial processes, and one was engaged to audit and test a massive update of the ticketing system of Singapore's rapid transit public transport system (the move from simple processes using magnetic stripe tickets to more complex processes using smart cards). This approach was clearly news to eGU.

  12.  If the statements by RPA to me in their letter of 16 May[25] are true, clearly the OGC Gateway reviews fail to identify serious risks of failure—on the one hand core documentation was not present; on the other hand the programme is managed in a professional manner. However, the File on Four radio programme stated that the SPS project had become stuck at one of the OGC gates, which merits further investigation.

A NOTE ABOUT THE POSITION OF CONTRACTORS SUCH AS ACCENTURE

  13.  Within the 22 May session there is a sub-theme suggesting that Accenture had what is eventually described as a "moral and... professional obligation" (Q443) and later a "moral responsibility if not a contractual responsibility" (Q631) to guide the client towards a better solution, warn that the business process outcome may not be delivered, etc Assuming that Accenture's answer is confirmed by a study of their contract, Accenture was right to say that they do not have such a responsibility.

  14.  Certainly it is possible for the relationship between contractor and customer to include giving advice on best practice, but in the end the customer makes the decision. With a contract that does not include the requirement to give such advice, the customer is liable to react very negatively if the contractor says that they should do the job differently: the contractor may then be labelled "difficult" and excluded from further work. (Personally I'm currently in that position with an organisation that is constituted as a Membership Company without shares: I was a contractor to the Company at a time when I was also a Director of the Company—unpaid as a Director, paid as a contractor.) These are business relationships, governed by business law, and the customer, in this case the public sector, has to be organised and managed in such a way that it can discharge the moral responsibility to the public. From the supplier's point of view, the professional obligation within a supplier company may well cause personal anguish to its employees and Directors, but it is only those organisations where there is legal obligation and/or contractual obligation to warn their clients (eg advisers such as lawyers, accountants, even technical consultants) who can be taken to task if they do not issue the necessary warnings. Personally, it causes me grief if my tax monies are not spent wisely by the public sector.

ANOTHER REPEATED THEME IN MEDIA REPORTS

  15.  Throughout the spring of this year, media reports were indicating that throughput of the SPS team operating the claim verification stage was very low. If those reports were correct, it was easy to demonstrate that the promised payment dates would not be met, yet apparently RPA management did not take any remedial action. As reported widely, and addressed in the 22 May session of the Committee (eg Q405), a change, under the new Chief Executive, from a task-based approach to a claims-based method, including bringing mapping system technical support staff into the processing centre, dramatically improved throughput. This again suggests that RPA management was not operating its risk management and mitigation processes in an adequate manner.

Peter Tomlinson

Proprietor

Iosis Associates

July 2006







24   Information and Communications Technology. Back

25   See my submission to the Committee on 19 May. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 29 March 2007