Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Memorandum submitted by Country Land & Business Association (CLA) (RPA Sub 07)

  1.  We are delighted that the Efra Committee are following up the horrendous problems at the RPA. We consider Defra's decision not to review the failure of the RPA's administration of the 2005 Single Farm Payment is completely unacceptable. A thorough post mortem of this process is needed. However, we would not in any way wish to see the examination delay the current processing.

  2.  Our advice is that the Committee should accumulate the detailed questions and understanding of the magnitude of the failure that we and other organisations can supply, but that you delay putting those questions to the RPA until the bulk of the payments have been made, which I suspect will not be until the end of June or later.

  3.  Clearly we do not have access to the sort of detailed information that your investigation will be seeking from RPA. However, some of the issues and questions that we think you should look at include the following:

    A.  It has been suggested by some groups that the choice of a dynamic hybrid system is the root cause of all the problems. We don't accept this. Certainly a number of other EU countries have adopted equally complex systems—including Denmark, Finland and Germany—and they have managed to make almost all their payments by the end of last year. The problem is not with the system, but with the implementation and management of the system.

    B.  Choices made by Defra and the RPA made a complex system far worse than it needed to be. Why, for example, has the RPA been subjected to an ongoing "change programme" while this complicated system was being implemented. Surely this is a time when all resources should be focused on delivery of the SPS. The "change programme" is all the more questionable when Defra and the RPA are also introducing the new environmental stewardship programmes, and a grand, all-encompassing new customer register. In our view, it is clear that the RPA has been overloaded and under-resourced.

    C.  Changes introduced by the new acting CEO, Mark Addison, suggest the processes under his predecessor were fundamentally flawed. Why, for example, were there six levels of authorisation after level 2 validation had been completed? Why was mapping—so fundamental to the new programmes—so decentralised around the country? Why was a task-based system used for processing claims, instead of a claims-based system? The changes introduced by Mark Addison are very welcome and will help to expedite processing, but, if their need was so obvious to him within days of taking over, why were they not implemented much sooner?

    D.  We would also ask about the degree of DEFRA supervisory input into this whole project? What intensity of scrutiny was put in by the most senior DEFRA officials, through what processes? We can only observe that the senior official who used to chair the Stakeholder group dropped out of that process in spring 2005 leaving it to quite junior officials. Also what did ministers ask and when? Certainly, the RPA consistently failed to take seriously the comments of stakeholders, and rejected our repeated warnings eg about the volume of mapping work in Autumn of 2004, and the slowness of the processing in early summer and autumn of 2005. This was a particularly frustrating experience as, despite the paucity of information—and misleading information—that the RPA provided us with. We have anticipated all the problems faced by the RPA and warned them in good time. In every case we were told that we didn't understand and that everything would be alright. At each stakeholder meeting we asked for statistics, were denied them, given obscure IT brush offs and were told repeatedly that "everything was on track". It has appeared to us that there was an absence of supervisory management processes. The RPA could not, or would not, provide us with basic information that should have been available including the numbers of claims by type, the incidence of problems among the claims. The RPA consistently seemed to have a poor appreciation of scale and make-up of problems they faced.

    E.  We suggest you might probe more deeply into Defra's role in all this. From the very beginning, Defra have been exceptionally slow in reaching decisions. For example, the seemingly simple matter of "who is a farmer" for the purpose of entitlement transfers took months to resolve. DEFRA as ever, took refuge by hiding behind the Commission and it took us a large amount of time and continual badgering to get a letter from the Commission which said that the problem was of DEFRA's making and the solution we had been suggesting for months was the correct one. Similarly, it was Defra that decided that six weeks' advance notification were needed for transfers of land and/or entitlements. This decision alone caused hundreds of anquished letters, emails and telephone calls to be made, and hours of discussions, and finally they reduced the period to three weeks. The decision about the moorland line is another case in point. Defra have been very slow in reaching policy decisions, which has meant that much needed information was not available until the very last minute. At the same time, the seniority of Defra's involvement in the RPA stakeholder meetings has fallen precipitously. In short, from everything we have seen, Defra appear on occasions to have been more of a hindrance than a help for the RPA.

    F.  When we responded to your earlier inquiry we made a number of suggestions about lines of questioning which I am not sure you were able to follow up on. Specifically, can you track down the dates of when RPA invited tenders for outsourcing the help with mapping? We had been asking about this from Autumn 2004 onwards. It was plain to all stakeholders that a great deal more land would have to be mapped than previously and we were concerned they did not have the resources. We suspect that this was not acknowledged until quite late in spring 2005. When did the contract come into force? In similar vein, it appears to us that the computer system at the heart of the SP5 processing was never specified adequately for the task. Was the fault the initial specification, or failure of the IT company to deliver to the specification, or failure of the systems operation to use the system correctly? We understand that the system simply could not cope with the number of operators who required to be online simultaneously and thus it continually crashed leaving operatives drumming their fingers. It might be worth getting some expert IT witnesses to give opinions on this.

    G.  Extremely poor communications and customer relations have been a hallmark of the RPA over the past months. Not only have they provided limited and misleading information to stakeholders, but—more importantly—they have all but abandoned their customers, the farmers. The frustration amongst farmers at not knowing what is happening to their maps, their claims, or their support payments is palpable, we could provide sample letters and emails. Until very recently—after much protest from stakeholders—their website was woefully un-informative about decisions the RPA were making about the process. At the critical point, when entitlement statements were first being sent out, the call centre was actually shut for over two weeks. Even now, with many farmers having been caught up in a Kafkaesque application procedure—especially the mapping—for up to a year in some cases, over half the claimants have no idea what is happening to their claims or when they can expect to be paid, and thousands were sent blank application forms which the explanatory letter said were pre-populated. All summed up by one of our members as: "unvalidated, unpopulated, unpaid and unhappy".

  4.  I hope that you find these remarks and observations helpful to your enquiry. We would, of course, very much like to have the opportunity to explain and expand on these points in an oral examination.

April 2006





 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 29 March 2007