Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Supplementary memorandum submitted by Accenture (RPA Sub 14a)

  Thank you for your letter of 26 May in which you ask Accenture to provide further supplementary evidence in relation to a number of questions. I attach a memorandum which provides responses to these questions.

  I would also like to take this opportunity to emphasize to the Committee the following key points:

    —  Accenture's involvement in the project has been to build and maintain to build and maintain a new claim processing system, known as RITA (RPA Information Technology Application).

    —  RITA is an important but single piece of the overall jigsaw to enable the RPA to make payments. There are a range of other IT systems and business processes which need to be functioning for the RPA to make payments. Accenture does not have responsibility for these other systems and processes.

    —  Accenture has delivered RITA within the timeframe and budget agreed with the RPA despite a challenging environment. RITA is functioning as designed and has been in operation and fully stable since October 2005, which is what was required from the RITA system to allow the RPA to make payments from February 2006. The RITA system did not "gum up".

  As you know, we have provided evidence at different times to the Committee: in addition to the attached memorandum, we provided written submissions on 2 December 2005 and 5 May 2006, oral evidence on 22 May and the corrected transcript of that oral evidence. Please treat all of this evidence as a whole and the various components should be read in conjunction with one another.

  Accenture remains committed to assisting the Committee with its enquiry and if you have any additional questions please do let me know.

1.   Any interchange of ideas Accenture had with paying agencies (or IT providers for paying agencies) in other EU countries (Qq 448-449).

  Accenture works with the Department of Agriculture and Food in Ireland where we have built a number of IT systems to support the processing of Arable Area Aid, SPS and Forestry payments. This work commenced in 2001 and is ongoing. The SPS system was built to support an implementation of SPS specific to Ireland.

  eSpatial is our subcontractor for the work for the Department of Agriculture and Food in Ireland, providing a spatial software package (iSmart), spatial software development expertise and spatial data cleansing. We understand that eSpatial has had some involvement with other Paying Agencies.

  The RPA held a workshop with their Dutch counterparts in early 2004 to exchange ideas and experiences. Accenture was invited by the RPA and participated in this workshop. We also had also some contacts with the Dutch Ministry of Agriculture between June and August 2004 when it commenced its procurement of the IT system to support payments to farmers but we did not maintain our interest in the procurement and did not subsequently bid.

  We have also built the Integrated Fisheries Information System (SI2P) for the Portuguese General Directorate of Fisheries and Aquiculture (DGPA). The SI2P system provides functions including processing of applications for EU fishery project grant aid and the management of fishing boat licences.

  We are not aware of any of our staff having attended conferences which have discussed how IT could be used to implement CAP Reform.

2.   The dates of meetings between Accenture and the Defra Permanent Secretaries, and the subjects of discussion at those meetings (Qq 469-475).

  According to our records, meetings between Accenture and the DEFRA Permanent Secretaries took place on the following dates:2003: 11 March, 7 November, 11 December 2004: 14 May, 2 July, 20 July, 3 September, 5 October, 5 November, 3 December 2005: 14 January, 2 March, 6 April, 6 May, 13 June, 14 July, 19 September, 18 October, 18 November, 16 December 2006: 6 February, 6 March, 19 April, 22 May.

  These meetings were primarily to discuss the status and progress of the RITA project and to address any key issues facing the RITA project.

  In our communications with the Permanent Secretaries we did provide updates about the RITA system and highlighted some factors critical to the RPA getting the full benefit from the RITA system, and therefore being able to make payments on time. These were factors that were outside the scope of our contract and beyond our control and into which we had limited visibility and we were therefore not in a position to comment on their deliverability by the RPA (as per our note to Q454 of the transcript of oral evidence).

3.   Confirmation of the date on which it was communicated to Accenture that the volume of land changes was significantly higher than was originally anticipated (Q 552).

  The increased volume was not formally notified to us, but in our capacity of Senior (External) Supplier on the Programme Board, Accenture became aware over time from regular business reports generated by the RITA system and Board discussions that the volume of land changes was higher than anticipated and increasing over time. During early 2005 we noticed the increasing number of land changes to the extent that we raised it as formal issue with the RPA in April 2005. In October 2005, we agreed to the RPA's request to support the outsourcing of land change updates to a third party.

  Neither the January 2003 nor the May 2004 contracts provided estimated volumes of land changes. These were first provided by the RPA to Accenture in September 2003 as part of developing Release 1A (RLR implementation) which went live in September 2004.

4.   The specific reasons why the optical character reader system was not deployed for the 2005 SPS scheme year (Q597-598). (+Q600)

  There are two factors which contributed to the RPA's decision not to deploy the Optical Character Reader (OCR) System for the 2005 SPS scheme year.

  In April 2003, a technical pilot of the OCR System was undertaken. Although the pilot was technically successful, the RPA had concerns over the impact of this technology on existing business processes and associated risks. The RPA therefore decided not to take the OCR System forward at that time within IACS, but it was marked for consideration in a future delivery after the initial implementation of pre-CAP Reform IACS Support. The CAP Reforms of June 2003 then caused the programme to be re-planned and the OCR System was targeted for Release 3.

  In August 2004, the RPA and Accenture entered into a Change Request to increase confidence that Release 3 would be delivered on schedule, in time for SPS 2005 processing. This included splitting the Release into Release 3A and Release 3B. The OCR System was moved to Release 3B.

  The High Volume Data Capture (in Release 3A0) facility was introduced through the same change request to provide data capture support for SPS 2005 within Release 3A.

  The OCR System has since been installed in March 2006 for the 2006 SPS scheme year.

5.   When the first test on the partial payments system was carried out to establish whether the interface between the RPA software systems worked correctly (Q 621). (+Q607-609)

  As part of our contractual commitments to the RPA, Accenture provided a contingency management plan to the RPA in May 2003 which outlined contingency management arrangements that Accenture had put in place to manage any potential delays in delivery of RITA. In line with our normal practice in relation to contingencies, we advised the RPA at this time to consider contingency arrangements outside the RITA system.

  The first test of the interface between RITA and the RPA's partial payments system took place in late November 2005. This was the earliest opportunity to undertake this test using fully synchronised RITA and RPA environments. A further test took place between 1 December and 7 December 2005.

  A final retest of the partial payments system interface from RITA was undertaken between 11 April and 28 April 2006 following revisions by the RPA to the partial payments approach. These tests were successful.

6.   An estimate of the increased costs associated with the changes that became necessary as a result of the increased volume of land parcels and mapping changes (Q 637).

  A number of changes were made by Accenture to the RITA system to address the increased volumes but these did not result in an increased cost to the RPA.

  Additional hardware was purchased by the RPA from third party suppliers and commissioned into the live RITA service by the end of August 2005 to provide increased processing capacity on the RITA system.

7.   It might be inferred from your oral and written evidence (paragraphs 29-30) that the stability issues surrounding RITA had been addressed by increasing the capacity of the IT system to allow for more operators to use it at any one time. It would be helpful if Accenture could confirm this understanding and also let the Sub-Committee know whether the system was at any point working to its newly enlarged capacity, or whether there would have been scope for the RPA to have deployed more users onto the system to deal with the additional tasks that were being generated.

  The increase in the capacity in July/August 2005 of the RITA system did have a major contribution to improving the stability of the system and through this enabled the RITA system to support more RPA users. In addition, Accenture continued to tune RITA in the live service to remove performance bottlenecks identified and allow better use of the available capacity, as is common practice on any new major implementation.

  Standard RITA service hours are from 8 am-6 pm Monday to Friday. In order to make full use of RITA, the RPA requested Accenture to increase the service hours from 6 am-9 pm Monday to Friday and 8 am-6 pm on weekends which Accenture did at no increased cost to the RPA. In terms of users, in September 2005 for example, the average daily peak was between 850-900 concurrent RPA users. In October 2005, the average daily peak was above 1,000 concurrent RPA users.

8.   Whether Accenture could confirm if the system for handling claims processing creates a constant log of the number of claims that are awaiting validation and the number of tasks that remain outstanding.

  The RITA system enables reports to be generated which provide information about the number of claims awaiting validation and also the number of tasks outstanding.

  Additionally, it allows for provision of information on the number of fully validated claims and the number of claims awaiting authorisation that have had a definitive entitlement established.

  As the technology provider of RITA, Accenture provides a service from which these types of reports are and can be generated for use by the RPA.

9.   Accenture's response to Helen Ghosh's assertion that it would be "inconceivable" that Defra/RPA could have "delivered a programme of this scale without an outhouse partner" such as Accenture (Q 226).It would be usual to use an external partner for a programme of this scale for the following reasons:

    —  The scale of the IT enabled change programme.

    —  The complexity of the change programme.

    —  The skill set required to implement the change programme which has required RPA to employ other third party advisors as well as Accenture.

10.   Despite the questions already answered by Accenture on the subject of testing, you may feel there is something you could add to explain why the elements of the IT system could not have been tested with real data prior to January or February 2006 (Q 559).

  Each individual RITA Release was tested prior to go-live in accordance with our contractual obligations.

  In November 2005, the RPA requested Accenture, in a change request, to complete live-data tests. The live-data tests were outside of the original contractual scope of testing.

  The objective of these tests was to de-risk payment processing by executing the RITA batch processes from definitive entitlement processing through to the payments interface from RITA to the RPA payments system (OREGON). These tests aimed to confirm that the RITA batch processes could run successfully against live data and to flush out any issues caused by unforeseen data permutations ahead of time critical live processing by the RPA.

  These tests were conducted from January through February 2006. They identified issues which were resolved ahead of the time critical live processing by the RPA. These issues related essentially to unexpected data permutations.

  As the SPS 2005 scheme was new and there were no historical records or "live data" to use, the possibility of undertaking realistic live data testing which would provide more confidence over and above the contracted testing scope was limited. The tests conducted from January through February 2006 required the use of a recent clone of the live data on the RITA system. This clone was not available with sufficient quantity and quality of level 2 validations before this time.Both the testing of the individual RITA system releases and the live data testing achieved their objective of ensuring that the RITA system was stable and capable of making payments, as is evidenced by the fact that the RPA commenced making full payments on 20 February 2006.

  As we made clear during our oral evidence on 22 May, the RITA system did not "gum up" in February/March 2006.

11.   It would be very welcome if there was anything that Accenture could add to help clarify exactly what a "task" is, how tasks are generated, how they can be resolved, and the significance to the validation process of having task outstanding.

  The RITA system is built upon a software tool sometimes referred to as a workflow engine which, at its simplest, facilitates the movement of tasks through a work process.

  A "task" is an item of work for an RPA user to perform which is created by the RITA system and delivered to the user electronically. These tasks are generated based on defined business rules and require specific user actions to resolve them. That action may, for example, require contact with the customer that has submitted a claim form or land change. Once the user has performed the resolving actions, they close the "task", and the RITA system then progresses the claim to the next stage at which point a user may be required to undertake further tasks.

  For payments to be made, RPA users need to clear all outstanding validation tasks and authorise a payment. Authorisation of payments is done in batches of 100 claims, and without authorisation, no payment will be made.

June 2006





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 29 March 2007