Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Supplementary memorandum submitted by the Rural Payments Agency (RPA) (RPA Sub 17)

1.  DISALLOWANCE

  The Committee asked for a note to clarify how Defra had accounted for possible disallowance—financial penalties imposed on the UK by the European Commission for not implementing the requirements of Single Payment Scheme fully or for making payments after the deadline.

  Defra and the RPA jointly assess the risks of disallowance arising from the administration of CAP programmes in a working group chaired by Defra. Since Defra makes up the shortfall if penalties have been imposed, the Department makes provision for disallowance in their accounts. Defra made provision in its recently published 2005-06 accounts for £150 million in relation to possible penalties for payments funded by the European Agricultural Guidance and Guarantee Fund. This includes but is not confined to the Single Payment Scheme. The provision also covers EAGGF schemes funded by the devolved administrations.

  The actual extent and timing of any disallowance is not known since there are considerable negotiations between the Commission and Member States about possible disallowance. Where agreement cannot be reached, the Member State may request that the matter be referred to the independent Conciliation Body and, thereafter, to the European Court of Justice as the final arbiter. This process can take up a number of years. Defra have made a provision in their 2005-06 accounts based on RPA's performance on SPS 2005 during 2005-06. (ie the risk was identified at the time of the year end).

  The disallowance process has already begun for SPS 2005—RPA received a letter from the European Commission recently proposing disallowance following the EC's audit on inspections and the control environment in September this year. Based on recent audit results etc—the timeframe for the application of disallowance is between two to three years. Following results of the Conciliation Body the EC normally apply the appropriate disallowance correction—it is only after that that Member States can apply to the ECJ. So Defra will pay out disallowance monies before the results of an ECJ case are known.

  The estimate which underpins the provision in the Defra accounts is based on all cases where the EC has notified that a financial correction is being considered in respect of UK EAGGF administration and a UK appraisal of possible weaknesses in our administration of the Single Payment Scheme.

  The financial corrections vary depending on whether the matters concerned are considered to be key or ancillary controls and the extent to which Member States are deemed to have failed to comply.

  The key weaknesses in implementing SPS 2005 issues which could lead to disallowance include defining entitlements prior to validating all claims; a high level of keying errors resulting in incorrect payments to producers; inaccuracies in the Rural Land Register; a shortfall of 1.5% in the application of Extensification Premium Scheme scale-back has resulted in small overpayments to a third of SPS claimants. Ancillary control weaknesses include that RPA has discovered that some penalties may have been applied incorrectly.

  In addition to the £150 million mentioned above, the Defra accounts also include contingent liabilities of £63.5 million in relation to late payments and partial payments under the Single Payment Scheme made before claims were fully validated.

  The provision and contingent liabilities in the Defra accounts are based on an assessment of the risk of disallowance. The contingent liabilities are based on an assessment of risks that are considered less likely than those for which provision has been made in the accounts. The £63.5 million includes an additional possible penalty in respect of partial payments but is included as a contingent liability because action taken by the RPA may mitigate the risk of disallowance.

2.  RPA BUDGET

  The committee asked for a note clarifying how the 2005-06 budget for the Agency compares to the 2006-07 budget and whether the additional funds the RPA received this year were above the 2005-06 baseline.

  The RPA's final allocation for 2005-06 was £227.8 million. This included additional funds made available to the RPA during the year to assist with implementation of the Single Payment Scheme.

  The initial allocation for RPA for 2006-07 was £190 million. The planned reduction in RPA funding included anticipated savings resulting from the RPA change programme. The problems in delivering SPS 2005 mean that these savings will not now be achieved.

  The RPA's operating business plan explained that the RPA had at that point a running cost budget of £197.1 million but that additional funding of £46 million had been agreed with Defra which would be split between running costs (to cover staff costs associated with processing SPS claims) and capital costs (including software development to support the 2006 and 2007 schemes). Defra has recently agreed a £27 million running costs/£19 million capital costs split for the additional £46 million funding.

3.  MANAGEMENT INFORMATION

  The committee asked for a note clarifying what management information is still manually collated and when this will be collected automatically.

  Whilst the majority of data is now recovered through auto capture, the following management information currently remains produced manually ie not stored on one of the RPA's systems (together with the date where they will be automated) are listed below:

  Data capture: (Automation of data capture will occur by May 2007)

    —  Initial checks on receipt of claims.

    —  Progress through scanning.

    —  Optical Character Recognition/Intelligent Character Recognition quality checks.

  Initial (level 1) validation: (December 2007)

    —  Quality checks (Peer and management checks).

    —  Productivity (FTE component).

  Detailed (Level 2) validation: (January 2007)

    —  Productivity (How many full time equivalents are working on claims per day).

    —  Progress of claims through the additional checks which are not recorded on the main SPS system "RITA".

  Claims payment:

    —  All key management information is automatically produced.

  Representations, Appeals and Complaints: (December 2007)

    —  Capture of the number of representations, appeals and complaints Inspectorate: (April 2008).

    —  Inspection tasks completed.

4.  DEFRA CORVEN CONSULTANCY COSTS

  The committee asked for a clarification of the costs of the Corven consultancy element of the Hunter Review. Defra paid Corven £557,331 for this work.

5.  GARTNER REVIEW OF RPA INFORMATION TECHNOLOGY

  The Committee asked for details of the costs of the RPA's contract with Gartner Inc to review the Agency's information technology systems:

  (a)  The cost of the contract is £265,000 excluding VAT and expenses.

  (b)  The project began on 25 September 2006 and is due to be completed by 18 December 2006.

  (c)  13 consultants have been working on the project and have been additionally supported by five research analysts.

December 2006





 
previous page contents

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 29 March 2007