Select Committee on Environment, Food and Rural Affairs Minutes of Evidence


Further supplementary memorandum submitted by British Waterways (BW 11d)

OVERVIEW

  BW is concerned that the information provided to the sub-committee on 23 April 2007 has caused confusion. It surprised us as we had spent the last nine to 12 months engaging with the Department about the long term funding needs of BW. It recognises that the figures related to this subject are complex and that we must clearly renew our efforts to explain them to the Department.

  The Minister raised a number of points—they are answered in detail below, via our answers to the Committee's questions. However, in essence he raised three main issues that need to be clearly addressed at the outset:

  A)  BW was not transparent—a process demonstrated by its failure to respond to his repeated requests until 20 April 2007. (eg Q429 or Q432)

  The Minister wanted a very specific comparison with our 2002 10 year plan. His detailed request for this was made on 16 April 2007 and BW provided the information on 20 April 2007 in the Chairman's letter to the Minister. See answer to Question 1 below.

  The Minister appeared to believe that the data provided on 20 April contained:

    —  information relating to elimination of arrears and "steady state" previously unknown to him or the Department. The Department was in fact aware of this information—see summary B below and answers in detail to Question 10. Documented discussion of these issues with the Department goes back at least to 22 June 2006.

    —  information showing that BW had in the past had more income than expected and would also do so in the period to 2012 thereby making the current grant cuts and any future ones irrelevant. This is not a helpful interpretation of the figures. See summary C below and answer in detail to Question 4.

  B)  BW got its projections about the future state of the network wrong (Q433) and the network is in a worse state than BW originally admitted (Q439)

  This statement seems to arise from the belief that "elimination of arrears by 2012" (ie no more than 10% principal assets in condition D and E) and achieving "steady state" are the same thing. They are not and BW has never claimed they are. Question 10 documents the discussions with the Department explaining this since June 2006—the discussions included a meeting with the Minister on 27 November 2006, as well as a subsequent fully documented CSR bid on 22 December 2006.

  This is important because the Minister seemed to believe that this constituted a revelation of a hitherto unknown deterioration of the state of the network. It does not.

  Quite simply, in 2002 BW used the arrears of maintenance on principal assets as its yardstick for assessing the condition of the system. The measure had served it well since the mid 1990s.

  From 2004, in keeping with developing best practice in asset management, BW began to develop a more holistic approach known as "steady state". Ongoing discussions to explain the changes were held with the Department throughout. The Department was formally aware of this at least from 22 June 2006, as BW prepared to integrate the "steady state" model into its business planning for the period 2007-08 to 2010-11.

  Use of the "steady state" model led BW to recommend a different profile of principal assets in condition D&E (15% by 2016). This is a new judgment, based on better information than available in 2002, representing in our view better value for the taxpayer. We are concerned that this has been represented as a worsening in condition of the system. It is not.

  C)  BW had had in the past more income than expected and would also do so in the period to 2012 thereby making the current grant cuts and any future ones irrelevant. (eg Q433)

  To make sense of the comparison, it is necessary to divide the period 2002-12 into two parts—the past (that money is after all now spent on agreed projects) and the future ie 2007-08 to 2010-11. The full answer is in our response to Question 4, but the summary position is:

  2002-03 to 2006-07

  BW delivered £61.6 million more commercial income during this period than planned in 2002 (see table in response to the committee's question 4)—an excellent result.

  BW is obliged by law to balance its income and expenditure and so this additional income plus additional grant of £8.9 million (from Scottish Executive) was spent (see table in response to committee's question 4) over the same period. The pros and cons of spending more on arrears during this period were fully discussed with the Department and Ministers at the time. All agreed we had the balance right.

  The main areas in which the money was used were:

    —  costs to support new business developments (£24.8 million);

    —  investment to reduce long term costs eg redundancy payments (£10.6 million);

    —  increased pension costs as a result of actuarial valuation (£7 million);

    —  accelerated investment in arrears with safety concerns (£7.4 million);

    —  spend on other assets and general repairs and maintenance (£4.5 million); and

    —  spend on waterway customer service improvements eg sanitary stations, water points etc. (£7.1 million).

    This excellent performance left BW with an expanded network, a safety related backlog eliminated on time (April 2004) and also at 31 March 2007 the backlog of arrears reduced to £107 million (latest estimate—see answer to Committee question 9 just about exactly on the target of £110 million set out in our 2001-02 Annual Report and Accounts.

  2007-08 to 2010-11

  Looking forward, we do not recognise the figure suggested of an additional £10 million income in this period. We estimate it will be higher at £15.2 million. See table in answer to committee question 4.

  However despite this improvement in income, if an assumption of a decline in grant from its already substantially reduced level is made by the much-discussed RPI -5% (a figure the Department encouraged us to use for planning purposes), we believe that despite reducing our operating costs and expenditure on the waterways by £52.9 million compared with the 2002 10 year plan, there will be a net shortfall of £44.9 million in necessary expenditure over the period 2007-08 to 2010-11. It is not appropriate to assess total expenditure over the whole ten year period because the expenditure before 2007-08 is now made and cannot be redirected to future deficit, even if, with hindsight, the Government now wished to do so.

  This projected shortfall will not cause immediate crisis, but the positive gradual elimination of the consequences of thirty plus years of severe underinvestment will halt and we will be returning to old-style gradual and at first imperceptible decline. The Board believes it is responsible to make this clear to Defra. Although it is complicated, we know it concerns many of our stakeholders who have been delighted with the hard-won positive improvements of the past 10 years.

DETAILED ANSWERS TO COMMITTEE QUESTIONS

  In the oral evidence session on 23 April, Barry Gardiner MP provided the Sub-committee with a set of figures he received from British Waterways on 20 April.

1.  Bearing in mind the Minister's comments on 23 April, could British Waterways provide its own interpretation of the figures it sent to the Minister on 20 April?

  The request for the 2002 10 year Plan comparison was first received by BW on 16 April 2006 and the figures were provided the same week on 20 April.

  The only previous request came from Martin Hurst, a senior civil servant, to the BW Chairman on 6 March 2007. We provided these figures in a letter to the Minister on 11 April 2007.

  BW has been fully transparent with Defra in its provision of financial and management information. The detail relating to the figures is explained in the following questions. BW has changed its asset management strategy and deferred the Arrears target of 2012 because it believes best value can be obtained by a new "steady state" approach which involves diverting some funds from Arrears towards non-principal assets.

  BW could still achieve the 2012 Arrears target under current funding circumstances but at the expense of proper maintenance of all the network using the "steady state" model.

  See also our answer to Summary point C above.

2.  Please provide a breakdown of the "Operating and admin costs" row in the table, from 2006-07 onwards, by: (a) operating costs; (b) organisational running costs; and (c) works. Please provide this breakdown for both the planned (ie 2002 Plan) and the actual accounts/forecasts

  The schedule below provides an analysis of the actual operating costs over the nine years from 2002-03 to 2010-11. There have been many changes to the reporting structures during that period which makes explanation at a more detailed level impossible.

  The 2002 Plan for the Future was a high level forecast and the operating costs are not broken down in sufficient detail to enable any meaningful comparisons.

  With regard to future operating costs, a detailed analysis of operating costs and costs by business areas is provided in the BW Corporate Plan 07/08 to 10/11 below.


Analysis of Operating Costs £000s
2002-03
2003-04
2004-05
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11

Property
7,188
7,687
9,811
9,973
8,930
8,106
7,582
7,575
7,669
Leisure
8,799
9,998
7,332
6,537
7,098
7,452
7,046
7,259
7,415
Core Waterway (inc major Works)
129,741
136,246
116,623
110,851
102,583
106,513
100,957
106,335
111,323
Other
30,590
32,230
40,176
44,486
49,935
51,778
52,696
54,646
55,098
Operating costs excluding R&R*
176,318
186,161
173,942
171,847
168,545
173,848
168,281
175,815
181,505
Regeneration and restoration
33,782
19,080
5,777
13,527
22,032
63,516
41,563
11,191
11,922
Total operating costs
210,100
205,241
179,719
185,374
190,577
237,364
209,844
187,006
193,427
Deduct contingency
3,000
3,000
3,762
3,632
As per BW Business Plan 2007-11
234,364
206,844
183,244
189,795


  *  per the schedule provided to the Minster

  With regard to future operating costs, a detailed analysis of operating costs and costs by business areas is provided in the BW Corporate Plan 2007-08 to 2010-11 below.


3.  How does capital expenditure fit into the table?

  The schedule shows revenue income and expenditure and therefore does not include capital expenditure.

  Waterways expenditure, both general works and major works (including Arrears) is treated as a revenue expense and fully written off to Profit and Loss accounts as incurred. These treatments have been standard accounting practice in BW for many years and are in accordance with UK GAAP and IFRS.

  BW separates capital cash flows from revenue cash flows and has separate bank accounts for each. Capital cash flows are primarily concerned with our commercial interests in particular property investments and disposals and joint venture activities. Property net rental income and dividends from joint ventures are treated as revenue income.

4.  Does British Waterways acknowledge that—even with an assumption of RPI -5% over the Comprehensive Spending Review (CSR) 08 period—it has received £30.1 million more than forecast (in 2002) over the 10year period in the table, and is estimated to receive about £10 million more than forecast between 2006-07 and 2010-11?

  The figures quoted in the above question are taken from the schedule supplied by BW to the minister on the 20 April. The figure of £30.1m million is the net of £78m of additional commercial income and £48m less grant over the 10 year period. The figure of £10m is not readily obvious from the table—we believe the correct figure is higher—£15.2m. For the purpose of separating the history from the future, the table below summarises the income and expenditure figures from 2002-03 to 2006-07 and from 2007-08 to 2010-11.

SUMMARY OF VARIANCES FROM 2002 PLAN FOR THE FUTURE


  Period 2002-03 to 2006-07—the past

  In summary commercial income exceeded the 2002 Plan for the Future by £61.6m, a remarkable performance, which together with additional grant income of £8.9m totals extra income of £70.5m over the five year period.

  There were of course additional costs totalling £25m incurred in achieving this income and supporting new business developments. We also invested £10m to reduce long term costs, for example redundancies that were not envisaged in 2002. A further £7m was spent on pension costs resulting from actuarial changes in life expectancy.

  Some £19m was spent on the waterways as follows:

    —  an additional £7.4m reducing the safety related backlog of arrears

    —  £4.5m on other repairs and maintenance

    —  £7.1m on waterway services enhancements.

  These variances in commercial income and operating expenditure are summarised in broad terms in the table below.



F10F/cast
*2002-03
2003-04
2004-05
2005-06
**2006-07
Total
2002-07

Analysis of Income variance
(approx) £m
  Ventures income
2.4
1.0
2.9
5.8
0.1
12.2
  Investment property income
4.0
2.7
2.4
1.9
2.2
13.2
  Severn Trent Water Discharge
    Income
8.0
4.0
4.0
2.9
5.5
24.4
  BWML Income
4.9
5.7
1.3
11.9
  Other
(0.1)
0.2
(0.1)
(0.1)
(0.1)
14.3
7.9
14.1
16.2
9.1
61.6

Analysis of Expenditure variance (approx) £m
  Customer service
    improvements
5.1
2.0
7.1
  Business reorganisation costs
5.0
5.6
10.6
  Liverpool Docks operating
    costs
1.1
1.1
1.1
1.1
1.1
5.5
  Costs to support new business
    developments
4.3
7.9
6.6
6.0
24.8
  Cost reductions and special
    factors 2006-07
(4.0)
(4.0)
  Safety backlog
5.6
1.8
7.4
  Other asset repairs and
    maintenance
(2.6)
3.9
6.0
3.6
(6.4)
4.5
  Pension fund deficit payments
2.3
2.3
2.4
7.0
  Other
(0.2)
0.4
1.0
(0.5)
(0.1)
0.6
3.9
21.6
20.3
13.1
4.6
63.5


  Period 2007-08 to 2010-11—the future

  Looking forward the additional commercial income of £15.2 million is negated by grant reductions of £56.7 million to result in a net adverse variance against the 2002 Plan of £41.5 million less income overall. This reduction includes additional commitments to future restoration and regeneration projects which have a forecast net cost of £8 million greater than the 2002 Plan. Taking these together, operating costs are forecast to be £52.9 million lower than forecast in the 2002 Plan. These operating cost reductions include some efficiencies but also means lower spend on maintenance and major works on the waterways.

  5.  What explains the predicted £25 million increase in earned commercial income between 2006-07 and 2010-11, compared with the amount forecast?

  The positive variance arises because, like any commercial company, BW seeks continually to improve its performance and it would be surprising of our current assessment for the years 2006-07 onwards did not differ from the forecast in 2002.

  The table below provides a high level analysis of the commercial income variance of £24.3 million between the latest Business Plan and the 2002 Plan for the five years to 2010-11.


F10F/cast
2006-07
2007-08
2008-09
2009-10
2010-11
Total 2006-11

Analysis of Income variance (approx) £m
Ventures income
0.1
0.1
(2.0)
(0.8)
6.9
4.3
Investment property income
2.2
2.9
(1.1)
(1.3)
0.3
3.0
Utility and other discharge income
5.5
7.2
6.9
6.7
6.9
33.3
BWML income
1.3
2.1
2.7
3.4
4.1
13.6
Consultancy
(1.0)
(1.7)
(1.8)
(1.7)
(6.2)
Retail
(1.8)
(1.8)
(1.9)
(1.9)
(7.4)
Freight
(1.4)
(1.5)
(1.5)
(1.6)
(6.0)
Other
(0.1)
(2.9)
(3.5)
(3.9)
(10.3)
9.1
8.1
(1.3)
(0.7)
9.1
24.3


  6.  How much of the expected earned commercial income from 2007-08 onwards will be generated through measures taken in direct response to the expected lower grant levels over the CSR 07 period (eg increased license fees)?

    BW's plan was prepared on the basis that it would always strive to optimise earned income from all sources. Therefore the reduction in grant had minimal effect on our earned revenue projections.

  The only specific change to BW's planned commercial income forecast that has arisen as a direct result of the grant cuts is the proposal to increase boat licence fees by 30% in real terms phase in over three years from April 2008.

  In oral evidence to the Sub-committee, British Waterways said:

    "our vision is to be increasingly self-sufficient... in an ideal world... …in 2012 we would like to have only 25% of our money coming from the Government... How do we get to that 25%?... firstly... we get rid of the backlog and we stop having these very expensive assets which are in poor repair to put right"

  7.  Can British Waterways confirm that its intention to become "largely self-sufficient"—and operate on a "Steady State" basis—by 2012 will now not be met? Can British Waterways confirm that it now aims to achieve Steady State status by 2016?

  See Summary point B above. This question repeats the confusion that elimination of arrears by 2012 and "steady state" are the same. They are not.

  This question brings together three related but different topics. Please refer to our previously submitted paper Network and Asset Management for a detailed explanation of "Steady State" and "Arrears" (ref. Sections 3 and 4). We explain each in turn.

LARGELY SELF SUFFICIENT

  It is BW's intention to become largely self sufficient.

  The phrase "largely self sufficient" is a relative term so it means that the proportion of grant funding should become a smaller percentage of total income over time. Hence the comment that, "in an ideal world… in 2012 we would like to have only 25% of our money coming from Government."

Generally, the 25% target can only be achieved if BW can grow commercial income at a faster rate than the growth in operating costs.

  Our Plan for the period 2007-08 to 2010-11 sees self sufficiency increase with government grant decreasing from 44% of income in 2006-07 to 36% in 2010-11.(It was 60% in 2002).

  BW has set stretching targets for commercial income growth. In our Plan for the period 2006-07 to 2010-11 commercial income grows by 29% from £88 million to £114 million. The strategy includes the growth of joint ventures to maximise returns from the development for its property assets. All available sources of commercial income are being sought from the waterways and the estate is managed in the most commercial manner possible, as is consistent with BW's values and standards. The Plan also includes a 30% plus inflation increase in boat licence prices spread over three years.

  Reducing costs and operating more efficiently will also help to achieve greater self sufficiency.

  Operating expenditure comprises routine waterway maintenance, expenditure on Major Works as well as routine administration and management costs. We have already delivered phase 1 of a continual efficiency programme to reduce costs. Circa 150 staff left BW in 2006-07 which will yield an annual payroll saving of around £5 million from 2007-08 onwards. Further reorganisation of the Business Units (particularly the operational bank staff) now underway will yield more efficiency savings and these are built into our Plan for 2007-08 to 2010-11.

STEADY STATE

  The term Steady State should not be confused with either the original 2012 target for the elimination of Arrears nor the "largely self sufficient" aspiration. It is a new model which BW has developed progressively since 2004. It allows BW to assess the ideal spend on the waterways taking account of a wider range of assets than simply the principal assets included in the original 2012 arrears target.

  Steady State is the estimated cost of maintaining the waterways in a constant condition under a planned maintenance regime. It assumes that there are no longer arrears of any type. BW's current estimate of the Steady State budget is £124 million per annum at 2006-07 prices. The Steady State concept has been developed over the last three years but only fully integrated into our planning for 2007-08 and beyond in the current CSR discussion. The latest BW business plan does not achieve Steady State at any point. Based on the levels of funding available in the Plan, general maintenance has been planned at 85% of the Steady State budget and major works expenditure has been planned at 80% of the Steady State budget. The consequence of this is that the general maintenance standards of the waterways remain below the desired customer service standards and that all the major assets are in gradual decline. The longer term projections show that there is not sufficient funding or commercial income to achieve Steady State at any point in the foreseeable future, which includes 2016 and beyond.

THE 2012 ARREARS ELIMINATION TARGET

  The 2012 Arrears elimination target was an estimate of the cost to bring the percentage of principal assets with condition grade D&E from around 30% in 2002 to 10% by 2012. At the time it was made (2002) principal assets were still seen as the priority for repair. The steady state model has now replaced this target in our thinking.

  Arrears are a tightly defined group of Principal Assets that have significant operational implications or high consequences of failure. The term Arrears specifically excludes all other non principal assets and other major liabilities.

  The achievement of the 2012 Arrears target will not achieve Steady State and will not make BW largely self sufficient.

  Based on the assumed level of funding and income, BW has reassessed its arrears elimination strategy and redefined the target as the number of assets in D&E condition of no greater than 15%. The projections show that this may be achieved by 2016. This does not mean that the state of the waterways has in any way worsened, simply that with a more sophisticated assessment technique than was available in 2002 and in order to achieve best value, BW is now recommending that the available money be spent in a different way ie with some greater spend on Non-principal assets and slightly less spend on arrears of principal assets.

  8.  Is the current maintenance back-log £97 million or £107 million?

  The figure of £97 million given in BW's submission to the Committee was the figure we had planned to achieve when we created the business plan for 2006-07.

  The figure of around £107m provided to the Minister on 20 April was BW's latest estimate based on year end asset management assessment, a process explained below. It should be noted that if the figure is confirmed at £107 million, it will be very close to the target set for 2006-7 in our Annual Report & Accounts for 2001-02—see also answer to Committee question 9.

  Each year following the year end BW re-assesses the arrears based on an analysis of the actual impact of the works carried out in year, an adjustment for continuing asset deterioration, additional assets, and an assessment of construction cost inflation. This is done by our asset management teams and takes some time. Indeed the exercise is not yet complete and the estimate is still subject to change.

  This is a process we follow every year prior to the finalisation of our Annual Report and Accounts.

  The asset management assessment is normally different from the expenditure shown in the management accounts. This is because all the costs allocated to a project involving a principal asset will not necessarily be associated with improving its condition grade. An example would be a project to refurbish a lock. The costs associated with the structure itself are those which are truly associated with the arrears as it is the structural condition which is important. More money may be spent on non structural issues for good sensible value for money reasons. For example the lock approaches may be improved and some additional mooring points added. These latter costs are properly posted through the management accounts against the project, but do not finally impact on the arrears backlog.

  When BW provided the £97m figure to the Committee, we were aware that, due to our broader asset management approach, grant cuts, and emergency works arising in the year such as two canal breaches, we were expecting to spend less than originally planned on our principal assets (arrears). We therefore checked the best information we had at that time—our forecast spend on Arrears at that time. Our management accounts forecast predicted a year end spend on arrears of £22 million. Since the outstanding Arrears at the start of 2006-07 was £119 million, this seemed to confirm that the £97 million was a reasonable out-turn figure.

  What we were not able to do at that time was make the assessment of the split of expenditure from a strictly asset management view. In the run up to the year end we are extremely busy in actually completing projects and working hard to have the network available for the new cruising season. There were 91 major works projects that both started and were completed in the financial year 2006-07. However, many projects run over two or three financial years. The total number of projects that had an expenditure greater than £20,000 during 2006-07 was 190.

  The difference between our management accounts and our asset management assessment is larger than normal this year. This largely arises from our progressive shift of spending almost exclusively on arrears in the past to a broader range of projects under the general heading of major works.

  The headline arrears figure is now less important to us under steady state than the annual major works expenditure.

  9.  Why was £25 million not spent in 2006-07 on the maintenance arrears back-log as expected, and why? How much was spent on the back-log during this period?

  In our 2006-07 Business Plan we planned to spend a total of £25.4 million (excluding externally funded works) on Arrears and other Major Works, £25.2 million of which was allocated to Arrears.

  The estimated final expenditure on Arrears and other Major Works is £22 million (excluding externally funded works), of which around £15.5 million was spent on Arrears.

  The overall reduction in expenditure results firstly from our decision to defer £5.6 million of expenditure as a response to the grant cuts made by Defra in late 2005-06 and "in year" in 2006-07. With such short notice, this is the only significant change in expenditure BW can make. Due to our success in earning more commercial income than expected, we were able late in the year, to allocate £2.2 million back into Arrears and Major Works, resulting in a final overall reduction of £3.4 million.

  The reduction in Arrears spending of around £9.9 million is greater than the overall reduction in expenditure for a number of reasons.

  The first reason is that as a result of the move during the year to a broader approach looking at all our assets, principal and non principal, we decided to reduce the amount of expenditure on arrears and allocate some funding to projects involving non principal assets. This amount is estimated to be around £2.2 million.

  The second reason is that during the year we also allocated funds to some of our reservoirs to complete works which were required as a result of inspections by Independent Statutory Reservoir Engineers. These works were required under the Reservoirs Act 1974 . The cost of these works was £2.8 million.

  The third reason is that we had some asset failures and emergency works during the year which required funds totaling around £1.5 million.

  In our 2001-02 Annual Report we predicted that the outstanding Arrears liability at March 2007 would be in the region of £110 million. We expect the current figure, once we have completed the year end assessments, to be in the region of £110 million. This shows that despite our decision to reduce spending on arrears in the last year we are actually on plan re the original 2012 target. It is our clearly stated intention to take a different approach from now on looking at all our assets together while ensuring public safety.

  10.  When did British Waterways first confirm to the Department that it would not meet its 2012 maintenance arrears target, and what did it say were the reasons for this? Did British Waterways previously tell Defra about the need to take account of new non-principal assets? If so, when?

(a)  June 2006 Quarterly Shareholder Meeting

  The first recorded mention of 2012 Arrears target not being met was in the minutes of a Quarterly Shareholder Meeting with Defra and the Shareholder Executive on 22 June 2006. Paragraph 7 of those minutes records that "The current level of grant (pre-any cuts) would lead to a `steady state' but any reduction would mean that the target date of 2012 for the elimination of the statutory maintenance arrears would not be achievable, with knock on consequences for steady state."

(b)  July 2006 CSR07 Submission

  BW submitted its first CSR07 paper in late July 2006. That paper included an explanation of the new Steady State approach. Annex D to that paper includes a detailed description of Steady State, Customer Standards and the new Asset Management Strategy and notes in section 1.4 that:

    "To date we concentrated on our Arrears programme, on dredging and on lock gate replacement. We believe that the risks posed by our principal assets allow us to move away from the concept of Arrears. We have a backlog of non arrears major works required on our infrastructure. We need to balance this demand against our previous determination to focus on Arrears. It is now our view that we should consider both aspects as a single issue."

  Section 1.4 goes on to provide greater detail.

  The CSR07 submission was discussed in subsequent correspondence and telephone conferences and is evidenced by an email from Robin Evans to Sabine Mosner (the senior official in the Department then responsible for British Waterways) dated 14th August 2006 which includes the statement:

    "Our submission suggests that it is wrong to seek elimination of arrears before tackling other major works. Now that the worst arrears projects have been dealt with, it is more sustainable to look at principal assets and other major works together and prioritise using our business criticality index."

(c)  November 2006 Briefing to Minister

  On 27 November 2006, The BW Chairman and Chief Executive met the Minister and (amongst other things) explained the "steady state" and major works concept and the forward funding issues that arose. This was a prelude to BW's second CSR submission—see below.

(d)  December 2006 CSR07 submission

  BWs second CSR submission was made on 22nd December 2006 by letter and supporting schedules to Sabine Mosner. This is a comprehensive document and includes clear references to major works underspends in the Summary and in section 8, particularly paragraph 8.3.9 which says,

    "Following our analysis under Steady State, we concluded that we could not afford to reduce D and E assets to these levels [8% plus 2%] if we are also to keep on top of other major works of repair and renewal to non principal assets."

  Paragraph 8.3.10 also clarifies that the revised approach is to aim for D assets of 12% and E assets of 3%. Annex J to that letter shows Arrears expenditure profiles extending out to 2015-16.

(e)  January 2007 Arrears schedules

  BW submitted a schedule of planned arrears expenditure and principal asset condition profiles to Sabine Mosner on the 19 January 2007. The schedule shows that the 2012 target will not be met and that by 2015-2016 15% of Principal Assets will be in condition D&E.

(f)  February 2007 Capital grant submission

  BW submitted a letter to Sabine Mosner on 9 February 2007 in respect of an application for a further capital grant allocation from Defra. The letter explains again the new Asset Management Strategy. In particular paragraph 4.3 states:

    "Our original asset management target was to have no more than 8% in condition D and 2% in condition E by 2012."

  and paragraph 4.4 states:

    "Following all our analysis under the reduced funding scenarios proposed in CSR07, we have concluded that BW will not be able to afford to reduce D and E assets to the levels in 4.3 above."

  Paragraph 4.5 goes on to explain that BW's revised approach is to aim for 12% in condition D and 3% in condition E by the time all repair arrears have been eliminated.

  In addition to the above documentary evidence there have been extensive discussions of these subjects in meetings between Defra, the Shareholder Executive and BW.

(g)  March 2007 EFRA Committee submission

  BW submitted a paper to EFRA Committee on 8 March 2007 titled Network and Asset Management.[1] This clearly sets out the relationship between Principal Assets, Non Principal Assets, Arrears and Steady State.

  In paragraph 4.7 it states, "Because we have tackled the worst of the Principal Asset arrears, we believe we can now reduce our targets for reduction of arrears and reallocate funds to non-principal assets and day to day maintenance".

  In paragraph 4.8 it states, "Our previous target of removing outstanding arrears by 2012 will, therefore, not now be met."

  11.  When did British Waterways first inform the Department about the new 2016 maintenance arrears target date?

  See above answer.

  12.  How significant were (a) funding pressures (b) non-principal assets and (c) other factors in the decision to move back the maintenance arrears target by 2016? Please quantify each factor by cost.

  As explained in the answer to Question 10 and in the paper titled Network and Asset Management, the decision to plan to change the arrears target was the result of a reassessment of how to obtain best value for money in maintaining the whole of the network.

  The revised targets are clearly influenced by the level of grant we receive as the more resources available to us the more major works we can undertake.

  It is important to recognise that if it wished BW could still achieve the original 2012 target of 8% D and 2% E. We just do not consider this to deliver best value for our customers and stakeholders.

  In oral evidence to the Sub-committee, the Minister said:

    "...every time [British Waterways] expanded the network... there were new principal assets which they had to maintain and the maintenance of those had not been factored into the [Asset Management] programme; a very simple error in the calculations".

  13.  How many new principal assets have been added by restoration of the network since 2002?

  As restorations or additions to the network are completed the assets are added to the asset management system. The principal assets are graded and any in condition D and E would be considered in the year end assessment of the outstanding arrears. The new or restored canals are also added to our Steady State cost model, but as previously explained, the model assumes that the additions have no backlogs of maintenance.

  Therefore, the year end arrears figure (see answers to Q8 and Q9 above) will include all the restorations or additions except the Stroudwater Canal (Cotswolds). Our Steady State estimate of £124 million per annum also includes all except the Stroudwater.

  The Minister's assertion (Q453) that the principal assets arising from restorations are not included in BW figures is therefore not correct.

  Not all restorations add significantly to principal asset numbers. The restoration of the Lowland Canals in Scotland and the Huddersfield Narrow Canal in England, for example, were largely already included within our asset register before restoration because we already owned and managed them albeit in a non navigable state. Some new assets were added where new structures or new lengths of canal were built, but most existing assets were improved or brought back into active use. The number of new assets added in these type of restorations, all in condition A or B, was 44.

  Some restorations did add additional assets some of which were in condition D or E. The Rochdale Canal is the major example. The total number of principal assets added was 216 of which 48 are in condition D or E, and 19 are currently ungraded.

  BW has not yet fully assessed the asset grades on the Stroudwater Canal which is subject to a current restoration project as the grades will change through restoration.

  In total we estimate (assuming the 19 ungraded assets to be in categories D or E) that the restorations have added 68 assets in category D or E—approximately 0.6% of all principal assets.

  14.  How do you react to the Minister's comments that British Waterways has not been "transparent about their own failure to properly assess the needs of the network"?

  There has been no "failure to properly assess the needs of the network". The answers to the question above and the documents supplied to the Committee and referred to support this.

  15.  What formal reporting system is in place between the Department and British Waterways? What is reported as part of this system, and how often? What discussions regularly take place as a result?

  A new formal reporting system was put in place this year under a revised Financial Memorandum. Annex C&D of the Financial Memorandum is attached that sets out what reports are made and when. Prior to this arrangement, the following arrangements were in place:

    —    Quarterly Meetings between Chairman, Chief Executive and Finance Director of BW with Defra and Shareholder Executive—reporting on latest P&L position against plan, network condition and current issues.

    —    Half yearly Estates Liaison Meetings between BW (Commercial Director), Defra, Shareholder Executive and DCLG—comprehensive update on property activities including full financial reporting against plan.

    —    Submission of three yearly Corporate Plan after Board approval in March each year.

    —    On average two meetings per annum with Minister to report on end of year achievement and future plans.

    —    On average a diaried phone conversation between BW Chief Executive and Defra once per week to cover any current issues or information requirements.

  16.  


Actuals/Business Plan 2007-08—2010-11
2005-06
2006-07
2007-08
2008-09
2009-10
2010-11

Net Interest
(1,052)
(1,337)
(2,107)
(1,998)
(2,208)
(2,187)
CBT—Revenue after Contingency
3,890
(390)
(2,085)
(3,006)
CBT—Revenue after Contingency Check
Revenue after Contingency Check
3,890
(390)
(2,085)
(3,006)


  Please explain the significance of the above figures in the table.

  The figures in the above table were workings originally included by the creator of the spreadsheet to ensure that the figures provided to the Committee balanced correctly by reference to our management accounts. The figures in the table provided to the Minister show the net operating profit before interest. The figures above provide a link to the figures in the management accounts and business plan as shown in the table below. They were "workings" rather than part of the final information. If you have further questions please let us know.


£000s
2005-05
Actual
2006-07
F10
forecast
2007-08
Plan
2008-09
Plan
2009-10
Plan
2010-11
Plan

CBIT before contigency
4,942
1,947
3,022
1,992
5,967
5,826
Contingency in F10 forecast   and Business Plan
(1,000)
(3,000)
(3,000)
(3,759)
(3,639)

Actual CBIT shown in the   Minister's table
4,942
947
22
(1,008)
2,208
2,187
Net interest payable
(1,052)
(1,337)
(2,107)
(1,998)
(2,208)
(2,187)

Profit before tax
3,890
(390)
(2,085)
(3,006)
0
0


  CBIT means Contribution before tax and interest

  Contingencies are included in Forecasts and Business Plans to allow for forecasting errors and unknown events.

SUPPLEMENTARY POINT

  The Department provided a supplementary memorandum to the Committee at its session on 23 April. It was produced without checking with BW. Unfortunately, it therefore contains the erroneous assertion that BW (along with IWA) held a meeting with Ed Balls to discuss greater commercial freedoms for BW on 3 November 2006. The memo implies that BW took this action "behind the Department's back."

  The Chair of IWA did indeed have a chance to discuss his organisation's view on future funding, including greater commercial freedom, when he sat next to Ed Balls at a strategy launch by the Barnsley, Dearne and Dove Canal Society on 3 November 2006. However, although local BW junior staff were also at the event, they were not party to the IWA discussion with Ed Balls and the event was not a meeting to discuss BW. The IWA Chair is prepared to confirm this if the Committee so requires.

British Waterways

May 2007





1   Ev 74. Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 31 July 2007