Select Committee on European Scrutiny Twenty-Sixth Report


1 Global navigation satellite system


(28660)

7828/07

+ ADD 1

COM(07) 261

Commission Communication: Galileo at a cross-road: the implementation of the European GNSS programmes

Legal base
DepartmentTransport
Basis of considerationMinister's letter of 14 June 2007
Previous Committee ReportHC 41-xxiii (2006-07), para 2 (6 June 2007)
Discussed in Council8 June 2007
Committee's assessmentPolitically important
Committee's decisionFor debate on the Floor of the House (decision reported on 6 June 2007)

Background

1.1 The Community has a two-phase policy for developing a global navigation satellite system (GNSS). The first phase, GNSS 1, is the European Geostationary Navigation Overlay System (EGNOS) programme. The second phase, GNSS 2, is the programme, named Galileo, to establish a new satellite navigation constellation with appropriate ground infrastructure. It has been intended that a public private partnership (PPP) be established for the Galileo programme and for sometime inconclusive, and latterly stalled, negotiations with a consortium about a concession have been underway.[1]

1.2 In March 2007 the Transport Council set a deadline of 10 May 2007 for the bidding consortium to put itself in a position to resume meaningful negotiations and asked the Commission to report back for the Council's 7-8 June 2007 meeting on how matters stood on the whole Galileo project and on alternative scenarios for carrying the project forward. This Commission Communication is the response to the Council's March 2007 request. In essence the Commission said that it is not satisfied that the consortium has fulfilled the conditions laid down by the Council in March 2007 and recommended to the Council that it should end the negotiations and reassess the way forward.

1.3 When we considered this document earlier this month we said that we would not find it acceptable if a Council Resolution or Conclusion at the June 2007 Council meeting went beyond accepting that:

  • the present PPP negotiations should not be continued; and
  • the Commission should produce a fully substantiated case for continuing the Galileo project in terms of methods of implementation (public procurement or PPP), governance and finances, including the total cost of the programme required, the level of risk, the sources of private sector revenue and the sources of funding from the Community Budget.

We also said that whatever the outcome of the Transport Council on 7-8 June 2007 we thought that Members would now want to debate where matters stand on the Galileo project. Accordingly we recommended that the Commission Communication be debated on the Floor of the House and that this debate should take place before the October 2007 Transport Council. We added that it would be helpful if the Government were to let us have as soon as possible an account of the June 2007 Council discussion so that we could report it to the House in time for the recommended debate.[2]

The Minister's letter

1.4 The Minister of State, Department of Transport (Dr Stephen Ladyman) writes now with the account we requested. He tells us that the Transport Council adopted a Resolution which meets the conditions we set. The Resolution:

  • concludes that the current concession negotiations have failed and should be ended;
  • asks the Commission to prepare detailed alternative proposals for taking the project forward, to be put to the October 2007 Transport Council;
  • underlines that these should be based on an additional thorough assessment of costs, risks, revenues and timetable; and
  • asks the Commission to submit financing options, a procurement strategy, concepts for the subsequent operation and exploitation phase, and proposals for a sound public sector governance structure.

The Minister adds that the Presidency made clear the possibility that, if suitable answers were not found, the project would be ended and that the Council should not rule out the involvement of private finance.

1.5 The Minister also tells us that in debate the Government:

  • accepted that Galileo had the potential to be a key project, as it is described in the Resolution, but that it should not be proceeded with unless the costs were justifiable;
  • stressed that, while the Government accepted that the current PPP negotiations had failed, it was committed to a PPP model;
  • argued that a PPP was the best way to ensure risk and cost are effectively managed, that the risks in terms of costs and timetable would not be reduced, and might be increased, by moving to a public procurement, and that open tendering and competitive procurement was essential;
  • said the Council had to ensure that it learned from the problems there have been, and improved governance and risk management;
  • said it was important that funding for Galileo had to be found within the limits of the current budget allocations, without reopening the current Community Financial Perspective; and
  • welcomed the Presidency's recognition that the project could be ended if acceptable solutions were not found, and that the involvement of private finance was not ruled out.

1.6 The Minister says that on this basis the Government was able to accept the Resolution, a copy of which he sends us and which we annex. He adds that the Government submitted, jointly with the Netherlands (and supported by Slovakia and Cyprus), a minutes statement. The statement:

  • stresses the Government's commitment to the PPP principle for major infrastructure projects, its concerns about the potential increased costs of public procurement, the need for a reassessment of the business case for Galileo, competitive procurement, better governance and sound risk management; and
  • requires that any additional funding be found within the limits of the Community's Financial Perspective.

The Minister sends us a copy of this statement too, which we also annex.

1.7 The Minister continues that in the discussion:

  • a clear majority of Member States underlined the strategic nature of the Galileo programme and the importance they attach to the project;
  • concerns were expressed that decisions should be taken as quickly as possible in order to avoid further delays;
  • the Government did, however, attract support for its robust stance on risk, cost and competition in the programme; but
  • by contrast, several of the major partners emphasised the need to respect existing industrial or infrastructure agreements.

1.8 Finally the Minister tells us that the Government:

  • expects the Transport Council to be asked in October 2007 to take a decision on the basis of the Commission's detailed proposals;
  • will continue to work to ensure there is a realistic, timely and detailed assessment of all proposals for taking the project forward;
  • will continue to argue that a fully substantiated case for continuing the Galileo project must be made by the Commission for Transport and Finance Ministers to take an informed decision; and
  • remains committed to its priority objectives for the programme.[3]

Conclusion

1.9 We are grateful to the Minister for this account of the Transport Council discussion of Galileo earlier this month. The information he gives us will be helpful to those participating in the debate we have recommended.


1   The consortium comprises eight companies - Aena, Alcatel, EADS, Finmeccanica, Hispasat, Inmarsat, Thales and TeleOp - from the Member States with major space industries, France, Germany, Italy, Spain and UK. Back

2   See headnote. Back

3   To achieve a robust and viable PPP, to influence the development and financial control of the project to ensure a transparent process which can deliver a value for money deal for the Community, to maintain Galileo as a civil programme under civil control and to secure maximum benefit for the UK and Community from Galileo, including promoting the bid for Cardiff to host the GSA.

 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2007
Prepared 2 July 2007