Select Committee on Public Accounts Fifty-Seventh Report


3  Facilitating the development of new waste processing infrastructure

13. An emphasis on recycling alone is unlikely to be sufficient to enable the United Kingdom to comply with the European Union's Landfill Directive. The Department's modelling indicated that new infrastructure capable of processing up to 15 million tonnes of waste each year may be necessary and that the cost of waste disposal will consequently have to increase from £2 billion in 2003-04 to £3.4 billion in 2009-10. Such infrastructure could include burning, anaerobic digestion, or composting waste to generate electricity, or using mechanical and biological treatment plants to recycle some materials and to compost organic materials. The Department's evidence from Europe suggests that the development of such infrastructure does not discourage household recycling.[14]

14. A significant minority of people (43%) recognised the need to build more facilities in their local area to provide an alternative to landfill. The development of waste infrastructure has tended to be unpopular with the public, however, and the United Kingdom, Italy and Spain are characterised by large scale protests and mobilisation of public opinion against new facilities. In 2004, the Department commissioned research to bring together the literature and evidence on the relative health and environmental effects of all the different waste management options. The Department found no evidence to suggest that properly managed and regulated energy-from-waste plants were likely to have an effect on human health. The Department's evidence suggested that the issues of public concern centred on the smell and appearance of the facility, and the volume of traffic to and from the site.[15]

15. The Department estimates that it takes around nine years for an energy-from-waste plant to progress from an identified need to becoming operational. By summer 2006 there was a significant risk that many of the waste treatment plants being proposed by waste disposal authorities would not be operational in time to comply with the European Union's Landfill Directive. The best performing local authorities have tended to work effectively with their local communities to respond to such concerns and the Department anticipates that the revision of the planning guidance in recent years (in conjunction with the Department for Communities and Local Government) will set out a much better framework for public consultation.[16]

16. Local authorities have stated that they would welcome more specific detailed advice on their approach to waste management. Encouraging and supporting waste disposal authorities to develop and introduce appropriate waste infrastructure necessitates the Department working closely with them to determine local circumstances and requirements. The anaerobic digestion plant in Shropshire, for example, is effective in processing biodegradable municipal waste into compost and generating electricity, but depends upon the adequate separation of biodegradable waste beforehand. The National Audit Office established that the Department has few staff available for liaising with local authorities, so more specific and tailored advice from the Department would require some prioritisation. Only six out of the 25 largest waste disposal authorities confirmed in 2006 that they expected to achieve their 2010 targets. The Department has encouraged local authorities to collaborate, although an Office of Government Commerce survey in 2005 found that local authorities had done so for only 15% of waste contracts.[17]


14   C&AG's Report, para 3.1-3.3; Qq 21, 75-76 Back

15   C&AG's Report, paras 3.6-3.9; Qq 97-98 Back

16   C&AG's Report, paras 3.3-3.5; Qq 21-22, 74, 97-98 Back

17   C&AG's Report, paras 3.13-3.14; Qq 54-57, 66, 76-77 Back


 